Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹21.0 LAccepted-Finance | ₹21.0 L | L1 | Accepted-Finance L1 |
| 2 | L2₹21.0 LRejected-Finance | ₹21.0 L | L2 | Rejected-Finance L2 |
Tender Value
₹21.2 L
EMD Value
₹42,360
Closing Date
21 Apr 2026, 12:00 pmClosed
EE
EE RED VARANASI
Pragatishil khatik kalyan samiti taktakpur varanasi ke sonakar dharmshala me samudaik haal ka nirman karya.
2026_REDUP_1131737_11
3492 Date 23-03-2026
Open Tender
Civil Works
90 days
EE RED VARANASI
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹42,360
Yes
8 May 2026
6 Apr 2026
21 Apr 2026
6 Apr 2026
21 Apr 2026
6 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. for All kinds of soil.As per DSR:Vol.1:2023 item 2.8.1 | 1 | cum | - | - | BI01010001010000000000000515BI0100001113 |
| 2 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete,As per DSR:Vol.1:2023 item 2.25A | 1 | cum | - | - | BI01010001010000000000000515BI0100001114 |
| 3Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources).As per DSR:Vol.1:2023 item 4.1.8 | ||||||
| 4 | Providing and laying in position, 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources), of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level.As per DSR:Vol.1:2023 item 5.1.2 | - | cum | 1 | - | BI01010001010000000000000515BI0100001116 |
| 5Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : in 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natu- ral sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) as per DSR:(Vol.-1):2023 Item 5.2.2 | ||||||
| 6 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).as per DSR:(Vol.-1):2023 Item 5.3 | - | cum | 1 | - | BI01010001010000000000000515BI0100001118 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete as per DSR:(Vol.-1):2023 Item 5.9.1 | 1 | sqm | - | - | BI01010001010000000000000515BI0100001119 |
| 8Centering and shuttering including strutting, propping etc. and removal of form for Suspended floors, roofs, landings, balconies and access platform as per DSR:(Vol.-1):2023 Item 5.9.3 | ||||||
| 9Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers as per DSR:(Vol.-1):2023 Item 5.9.5 | ||||||
| 10Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts as per DSR:(Vol.-1):2023 Item 5.9.6 | ||||||
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.28 MB
sbd.pdf
Tender Documents • 1.31 MB
BOQ_2112121.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid