| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.0 CrAdmitted-Finance | ₹1.0 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.0 Cr+₹2.1 L (2.03%)Admitted-Finance | ₹1.0 Cr+₹2.1 L (2.03%) | L2 | Admitted-Finance |
| 3 | L3₹1.1 Cr+₹7.6 L (7.53%)Admitted-Finance | ₹1.1 Cr+₹7.6 L (7.53%) | L3 | Admitted-Finance |
| 4 | L4₹1.1 Cr+₹9.8 L (9.70%)Admitted-Finance | ₹1.1 Cr+₹9.8 L (9.70%) | L4 | Admitted-Finance |
| 5 | L5₹1.1 Cr+₹11.3 L (11.1%)Admitted-Finance | ₹1.1 Cr+₹11.3 L (11.1%) | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | R.ANDI L1 | RD CONSTRUCTIONS L2 | KANDASAMY IRULAPPAN L3 | RML MARI L4 | S PANDI L5 |
|---|---|---|---|---|---|---|---|---|
| 1.00Strengthening of the road from Pallithambam to Uruvathi Periyanagi Ammankovil road 0/0 - 4/0(R-57) in Kalayarkoil Block. | ||||||||
| 2.00 | Clearing the scrub Jungle including removing from the site, disposal by burying or burning etc., complete as directed by the departmental officers | 4,320 | Sqm | - | - | - | - | - |
| 3.00 | Earthwork excavation and depositing on bank with initial lead of 10 m and lift of 2.0 m in hard gravel soil including cost and conveyance of all labour charges etc., complete as per SS 20 A | 4,749.6 | Cum | - | - | - | - | - |
| 4.00 | Picking the Existing Worn out BT Surface including all charges etc., complete. | 4,898.03 | Sqm | - | - | - | - | - |
| 5.00Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, water and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire and fuel charges for power roller, water sprinkler and all other incdidental charges such as traffic barricading and providing danger lights etc., complete. | ||||||||
| 6.00 | Km 0/0 - 1/0 | 150 | Cum | - | - | - | - | - |
| 7.00 | Km 1/0 - 2/0 | 143.7 | Cum | - | - | - | - | - |
| 8.00 | Km 2/0 - 3/0 | 150 | Cum | - | - | - | - | - |
| 9.00 | Km 3/0 - 4/0 | 150 | Cum | - | - | - | - | - |
| 10.00Providing and laying WBM 75mm compacted thickness with grade II metal using 1 cum of 75-22.4mm IRC HBG metal with 0.24 cum of gravel for blindage per 10sqm incl. cost and conveyance of all materials and stacking to departmental gauge for premeasureemnt labour charges for spreading metal and hand packing to Camber watering with all leads for Water and Compacting by 80-100KN power roller rolling incl. hire charges etc., completed. | ||||||||
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
14 May 2020, 3:00 pmClosed
The Project Director, DRDA, Sivagangai
O/o The Project Director, DRDA, Sivagangai
Strengthening of 1 Road work at Package No.TNSVG/2/KKOIL/ NABARD XXV 2019-20 in Kalaiyarkoil Block of Sivagangai District
2020_RDTN_162373_1
DIPR/1487/TENDER/2020 NABARD XXV PK2
Open Tender
Civil Works - Roads
Item Rate
180 days
Sivagangai
Refer Tender Documents
6 documents required · 6 mandatory
₹0
₹1.1 L
O/o The Project Director, DRDA, Sivagangai
11 Aug 2020
13 Apr 2020
14 May 2020
13 Apr 2020
14 May 2020
13 Apr 2020
22 Apr 2020
Amount
Strengthening of the road from Pallithambam to Uruvathi Periyanagi Ammankovil road 0/0 - 4/0(R-57) in Kalayarkoil Block.
Clearing the scrub Jungle including removing from the site, disposal by burying or burning etc., complete as directed by the departmental officers
Earthwork excavation and depositing on bank with initial lead of 10 m and lift of 2.0 m in hard gravel soil including cost and conveyance of all labour charges etc., complete as per SS 20 A
Picking the Existing Worn out BT Surface including all charges etc., complete.
Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, water and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire and fuel charges for power roller, water sprinkler and all other incdidental charges such as traffic barricading and providing danger lights etc., complete.
Providing and laying WBM 75mm compacted thickness with grade II metal using 1 cum of 75-22.4mm IRC HBG metal with 0.24 cum of gravel for blindage per 10sqm incl. cost and conveyance of all materials and stacking to departmental gauge for premeasureemnt labour charges for spreading metal and hand packing to Camber watering with all leads for Water and Compacting by 80-100KN power roller rolling incl. hire charges etc., completed.
Providing and laying WBM 75mm compacted thickness with grade III metal using 1 cum of 63-11.2mm IRC HBG metal with 0.24 cum of gravel for blindage per 10sqm incl. cost and conveyance of all materials and stacking to departmental gauge for premeasureemnt labour charges for spreading metal and hand packing to Camber watering with all leads for Water and Compacting by 80-100KN power roller rolling incl. hire charges etc., completed.
Providing and laying tack coat over WBM unprimed surface using 4.00 kg. of emulsion bitumen for 10 sqm area including cost of bitumen, including labour charges for preparing the surface and applying the required quantity of emulsion bitumen as tack coat etc., complete MOST specification.
Providing and laying premix carpet with seal coat type 'A' for 20mm thickness using 0.18 cum of 13.2 mm IRC HBG metal and 0.09 cum of 11.2mm IRC with 14.6 kg. of bitumen per 10sqm. of premix carpet and 0.09 cum of 6.70cum IRC HBG metal with 9.8kg. of bitumen for seal coat type 'A' per 10sqm including cost and conveyance fo all materials mixing them with bitumen in mini hot mix plant for premix carpet only rolling by 80/100KN power roller for premix carpet and seal coat separately including labour charges for spreading the mix for premix carpet application of bitumen for seal coat over premix carpet including hire charges for fuel charges for mini hot mix plant, bitumen boiler, power roller and all other T&P's employed etc., complete.
Provision for KM Stone & HM Stone
KM Stone
HM Stone
Provision for Sign Board
Construction of 2 row Pipe culvert @ Chainage 3/950
Earthwork excavation and depositing on bank in all classes of soil with initial lead & lift as per SS 20B for foundation etc complete
Collection and filling with good river sand including all cost & conveyance of all materials to site & all labour charges etc complete
CC 1:4:8 mix using 40mm metal including all cost & conveyance of all materials to site & all labour charges etc complete
Supply and errecting sheet centering of size 90 cm x 60cm 10 G sheet laid over silver oak joist and supported by casurina post of size 10 cm x 13 cm dia spaced at 75 cm center to center etc. complete for Below ground
CC 1:3:6 mix using 40mm metal including all cost & conveyance of all materials to site & all labour charges etc complete
Supply of NP3 Class RCC Pipe confirming to IS 458/2003 including cost of pipe as a finished work including all other incidental charges, testing chargs including loading, unloading, transport and delivery in good condition at work site etc., complete as directed by the Departmental officers, as per Standard specifications.
Hoisting and Fixing of NP3 class RCC Pipe and collars in proper gradient including all labour charges and all other incidental charges, etc., complete as directed by the Departmental officers, as per Standard specifications.
filling gravel to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, water and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire and fuel charges for power roller, water sprinkler and all other incdidental charges such as traffic barricading and providing danger lights etc., complete.
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
RD CONSTRUCTIONS
KANDASAMY IRULAPPAN
RML MARI
S PANDI
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.18 MB
PriceBid2kkoil.pdf
Tender Documents • 0.23 MB
TechnicalBid2kkoil.pdf
Tender Documents • 0.31 MB
BOQ_194264.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .