| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 LAccepted-AOC BAJRANG COMPLEX JAYANT P O JAYANT DISTT SINGRAULI M P PIN 486890 | JAYANT | SINGRAULI | MADHYA PRADESH | 486890 | L1 | Accepted-AOC As per NIT and L1 | |
| 2 | L2₹1.9 L+₹6,174.94 (3.38%)Rejected-Finance BHAGAT SINGH COLONY WARD NO 9 MORWA SINGRAULI DIST SINGRAULI M P 486889 | SINGRAULI | SINGRAULI | M P | 486889 | L2 | Rejected-Finance As per NIT and L2 | |
| 3 | L3₹2.0 L+₹17,375.03 (9.51%)Rejected-Finance WARD NO 9 BHAGAT SINGH COLONY NEAR SINGRALI SINGRAULI | SINGRAULI | SINGRAULI | MADHYA PRADESH | 486889 | L3 | Rejected-Finance As per NIT and L3 |
Tender Value
₹2.7 L
EMD Value
₹3,420
Closing Date
3 Oct 2022, 11:00 amClosed
STAFF OFFICER (EXCV) BLOCK-B AREA
OFFICE OF GM BLOCK B AREA
Fabricating 01 no. Water Tank body from Dump body of BH100 Dumper and installation of pump motor combination with necessary water pipe connection at Block-B Project
2022_NCL_257055_1
BLB/EXCV/ETN/22-23/485
Open Tender
Excavation Department Work
Item Rate
25 days
BLOCK B PROJECT SINGRAULI
Please refer Tender documents.
6 documents required · 6 mandatory
₹3,420
10 Nov 2022
22 Sept 2022
4 Oct 2022
22 Sept 2022
3 Oct 2022
23 Sept 2022
22 Sept 2022 - 29 Sept 2022
Amount
Scope of Job: 1. Removal of Dump Body from Dumper 2. Cleaning of Dump body 3. Cutting of MS Plates as per required size 4. Welding of plates in the Dump body to make different compartments 5. Painting of compartments 6. Mounting of tanker body 7. Fabrication of Pipe line network as desired 8. Installation of Pump-Motor Assembly 9. Connecting all pipelines 10. Painting of full Dumper 11. Testing of the sprinkling system by water filling. Terms & Conditions: 1. Work to be carried out at company workshop 2. All safety materials required during job are to be provided by the party 3. No child labour will be engaged in the job Material to be provided by company: 1. MS plate 10mm size as per requirement 2. MS Angle 75 X 75 X 6 mm as per requirement 3. GI Pipe 25 Metre, 4 mm thickness 4. Crane when required 5. DA & Oxygen gas
Cleaning of Dump body by wire brush, cutting of uneven steel material, Area 341.25 Sqft including skilled welder 03 men X 02 shifts X 03 days, unskilled 03 men X 02 shifts X 03 days with CMPF/EPF, contractor's profit on labour charges @10% & grinding of surface by grinding machine approx. 24 hours
Fabrication of tank body chamber, cutting of plates as per below sizes (in feet) 16.25 X 3.25 - 01 no. 16.25 X 3.50 - 01 no. 16.25 X 5.00 - 01 no. 7.50 X 3.25 - 03 nos. 7.50 X 2.25 - 03 nos. including skilled welder 02 men X 02 shifts X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor's profit on labour charges
Making of V groove by gas cutting including skilled welder 02 men X 02 shifts X 03 days, unskilled 02 men X 02 shifts X 03 days with CMPF/EPF, contractor's profit on labour charges
Complete welding of chamber plate by 4mm electrodes 7016 & total cover 268.96 Sqft = 8199.12 Sqmm, Total welding deposit = 0.0078 X 1.2 X 8199 cm = 76 Kg (65% deposit efficiency = 118 Kg) including skiled welder 02 Men X 02 shifts X 06 days, unskilled 02 men X 02 shifts X 06 days with CMPF/EPF, contractor's profit on labour charges
Fabrication of & installation of Sprinkler unit containing valve & GI pipe, drilling of 6 mm dia holes on pipe size 6 metres length X 4 inch dia (920 holes approx.) including drill machining charges with drill bit for 23 mandays and cost of manpower including skilled fitter 01 man X 01 shift X 23 days, unskilled 01 man X 01 shift X 23 days (drilling @5 holes per hour per shift =40 holes) with CMPF/EPF, contractor's profit on labour charges
Fabrication & Alignment of bed plate for installation of pump & motor station including skilled fitter 01 man X 02 shifts X 05 days, skilled welder 01 man X 02 shifts X 05 days, unskilled 02 men X 02 shifts X 05 days with CMPF/EPF, contractor's profit on labour charges
Painting of tank body approx. 1018.20 Sqft
Painting of complete machine with green paint, environment friendly approx. 1506.94 Sqft
Dump body removal from chassis including skilled fitter 02 men X 02 shift X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor's profit on labour charges
Mounting of Dump body on the chassis including skilled fitter 02 men X 02 shift X 02 days, unskilled 02 men X 02 shifts X 02 days with CMPF/EPF, contractor's profit on labour charges
Hiring of two nos welding machines alongwith welding accessories, gas cutting set for 25 days, 02 shifts = 50 Mandays
Cost of electrodes approx. 110 Kgs and Supervisor for 24 Mandays with CMPF/EPF, contractor's profit on labour charges
Total impact of GST for the purpose of CTC
NIRBHAY SALES AND SUPPLY AGENCY
M s Banarsilal and Sons Associates
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_265794.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.07 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .