| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹19.0 LAccepted-AOC | L1 | Accepted-AOC Tender Finalized | |
| 2 | L2₹19.0 L+₹4,000.80 (0.21%)Rejected-Finance | L2 | Rejected-Finance Above the estimate rate |
| Sl No | Description | Qty | Unit | Meenu Industries PVT.LTD. L2 | P PARINATHAN L1 |
|---|---|---|---|---|---|
| 1.00 | Cutting the Existing BT Road including all labour charges etc., complete complying with standard specifications. | 35 | 1 cum (One cubic meter) | 996 ₹34,860 | 994 ₹34,790 Lowest |
| 2.00 | Earth work excavation for foundation by Mechanical means for Isolated & Combined Footing etc in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 100 mts and clearing and levelling including dressing of sides and raming of bottoms etc., complete complying with standard specification and as directed by the departmental officers.- Upto 2.40m Footing Depth. | 353 | 1 cum (One cubic meter) | 200 ₹70,600 | 198 ₹69,894 Lowest |
| 3.00 | Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers -Mixing by mechanical means | 77 | 1 cum (One cubic meter) | 5,820 ₹4,48,140 | 5,815 ₹4,47,755 Lowest |
| 4.00 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, Sill slabs etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid with silver oak joists of size 10cm x 5cm & 7.5cm x 5cm as support runner , vertical stiffener, side support and Top Horizontal stiffener spaced at about 60cm to 90cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid). | 363.8 | 1 Sqm (One square meter) | 690 ₹2,51,022 | 685 ₹2,49,203 Lowest |
| 5.00 | Cement Concrete 1:3:6 (One Cement, Three crushed stone sand and Six broken stone jelly) using 20mm size hard broken stone jelly for dummy columns,etc., excluding cost of centering shuttering reinforcement grills and fabrication charges but including Cost of Mortar Plasticizer, curing etc. complete and as directed by the departmental officers. (Dummy columns should be at least 1 metre height)-Mixing by mechanical means | 3.2 | 1 cum (One cubic meter) | 6,825 ₹21,840 | 6,820 ₹21,824 Lowest |
| 6.00 | Plain Cement Concrete 1:2:4 (one cement, two crushed stone sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.-Mixing by mechanical means | 98.7 | 1 cum (One cubic meter) | 7,100 ₹7,00,770 | 7,096 ₹7,00,375.2 Lowest |
| 7.00 | Providing and fixing Bitumen Pad for Expansion joint in between pavement slabs to 12mm thick and fixed as shown in the drawing including cost and conveyence of expansion joints including shalimar pad and joint sealent etc, complete as per standard specification | 22.4 | 1 Sqm (One square meter) | 485 ₹10,864 Lowest | 485 ₹10,864 Lowest |
| 8.00 | Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two Crushed Stone Sand and Four aggregate) using 6 to12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trowel, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers) | 161.7 | 1 Sqm (One square meter) | 450 ₹72,765 Lowest | 450 ₹72,765 Lowest |
| 9.00 | Provision for GST 18% CGST-9%, SGST-9% | 1 | 1 No (One Number) | 2,89,954 ₹2,89,954 | 2,89,344 ₹2,89,344 Lowest |
Tender Value
Refer Docs
EMD Value
₹19,500
Closing Date
12 Dec 2025, 3:00 pmClosed
Commissioner Kottakuppam Municipality
Commissioner Kottakuppam Municipality.
Providing Cement Concrete Road with Storm Water Drain at ward no 07, Sudhakar Beach Cross Street - 1 (175007R0152), Sudhakar Beach Cross Street - 2 (175007R0153), Indira Nagar Pazhaya Pattinam Pathai(175007R0151) in Kottakuppam Municipality.
2025_MAWS_631082_1
926/2025/E1
Open Tender
Civil Works
Works
180 days
Kottakuppam Municipality
Yes Enclosed
3 documents required · 3 mandatory
₹0
₹19,500
18 Feb 2026
11 Dec 2025
12 Dec 2025
11 Dec 2025
12 Dec 2025
11 Dec 2025
11 Dec 2025 - 12 Dec 2025
Cutting the Existing BT Road including all labour charges etc., complete complying with standard specifications.
Earth work excavation for foundation by Mechanical means for Isolated & Combined Footing etc in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 100 mts and clearing and levelling including dressing of sides and raming of bottoms etc., complete complying with standard specification and as directed by the departmental officers.- Upto 2.40m Footing Depth.
Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers -Mixing by mechanical means
Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, Sill slabs etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid with silver oak joists of size 10cm x 5cm & 7.5cm x 5cm as support runner , vertical stiffener, side support and Top Horizontal stiffener spaced at about 60cm to 90cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid).
Cement Concrete 1:3:6 (One Cement, Three crushed stone sand and Six broken stone jelly) using 20mm size hard broken stone jelly for dummy columns,etc., excluding cost of centering shuttering reinforcement grills and fabrication charges but including Cost of Mortar Plasticizer, curing etc. complete and as directed by the departmental officers. (Dummy columns should be at least 1 metre height)-Mixing by mechanical means
Plain Cement Concrete 1:2:4 (one cement, two crushed stone sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.-Mixing by mechanical means
Providing and fixing Bitumen Pad for Expansion joint in between pavement slabs to 12mm thick and fixed as shown in the drawing including cost and conveyence of expansion joints including shalimar pad and joint sealent etc, complete as per standard specification
Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two Crushed Stone Sand and Four aggregate) using 6 to12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trowel, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers)
Provision for GST 18% CGST-9%, SGST-9%
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_754732.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.57 MB
ConditionsNN.pdf
Tender Documents • 6.24 MB
BOQ_754732.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .