Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.3 CrAccepted-AOC | ₹1.3 Cr Quoted ₹1.5 Cr | L1 | Accepted-AOC L1 Bidder |
| 2 | L2₹1.6 CrRejected-Finance | ₹1.6 Cr | L2 | Rejected-Finance Not L1 Bidder |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Others-As per clause 14.12 of BDS, physical copy shall reach NTPC office within 10 days of bid submission date. Physical copy of EMD BG is not received within 10 days of bid submission date. There is no valid EMD present in bid as per T&C. Bid Not Accepted. |
| Sl No | Description | Qty | Unit | MAITHILY SHARAN CONSTRUCTION COMPANY L1 | AURUM CONSTRUCTION L2 |
|---|---|---|---|---|---|
| 10.00 | PART 10: SCHEDULED ITEMS (CIVIL) | 1 | Nos | 13.99 ₹1.4 Cr | 9.77 ₹1.5 Cr |
| 20.00 | PART 20: NON-SCHEDULED ITEMS (CIVIL) | 1 | Nos | 3.39 ₹3.4 L | 9.77 ₹3.2 L |
| 30.00 | PART 30: SCHEDULED ITEMS (ELECTRICAL) | 1 | Nos | 5.1 ₹7.5 L | 3.77 ₹8.2 L |
| 40.00 | PART 40: NON-SCHEDULED ITEMS (ELECTRICAL | 1 | Nos | 10 ₹2.2 L | 3.77 ₹2.1 L |
Tender Value
Refer Docs
EMD Value
₹2 L
Closing Date
23 Mar 2026, 3:00 pmClosed
DGM (CnM CPG-2)
USSC CPG-2 Naya Raipur
Construction of community hall in ward no-38 and additional facilitiesat DDRC under CSR Budget
2026_NTPC_105935_1
NTPC/USSC-CPG2/9900320924
Limited
Miscellaneous Works
270 days
Vindhyachal Super Thermal Power Station
2 documents required · 2 mandatory
₹0
₹2 L
1 Apr 2026
11 Mar 2026
24 Mar 2026
11 Mar 2026
23 Mar 2026
11 Mar 2026
11 Mar 2026 - 16 Mar 2026
PART 10: SCHEDULED ITEMS (CIVIL)
PART 20: NON-SCHEDULED ITEMS (CIVIL)
PART 30: SCHEDULED ITEMS (ELECTRICAL)
PART 40: NON-SCHEDULED ITEMS (ELECTRICAL
Scheduled Items List
BoQ_Ver3.0
Reference No: 9900320924
Bidder Name :
PRICE SCHEDULE (This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender.
NUMBER #
PART 10: SCHEDULED ITEMS (CIVIL)
DSR2023 item: 1.1.2(i)
DSR2023 item: 2.8.1
DSR2023 item: 2.25
DSR2023 item: 2.27
DSR2023 item: 2.28.1
DSR2023 item: 4.1.5
DSR2023 item: 4.1.8
DSR2023 item: 5.9.1
DSR2023 item: 5.9.3
DSR2023 item: 5.9.5
DSR2023 item: 5.9.6
DSR2023 item: 5.9.16.1
DSR2023 item: 5.11.1
DSR2023 item: 5.22.6
DSR2023 item: 5.33.1.1
DSR2023 item: 5.33.2.1
DSR2023 item: 6.1.1
DSR2023 item: 6.34.2
DSR2023 item: 6.15
DSR2023 item: 6.44
DSR2023 item: 6.45.2
DSR2023 item: 8.10.1
DSR2023 item: 8.31
DSR2023 item: 9.20.1
DSR2023 item: 9.48.2
DSR2023 item: 9.96.2
DSR2023 item: 9.97.3
DSR2023 item: 9.98
DSR2023 item: 9.100.2
DSR2023 item: 9.101.2
DSR2023 item: 9.118.2
DSR2023 item: 10.14.1.1
DSR2023 item: 11.37
DSR2023 item: 11.41.3
DSR2023 item: 12.21.1
DSR2023 item: 12.22
DSR2023 item: 12.41.2
DSR2023 item: 12.42.6.2
DSR2023 item: 12.43.2
DSR2023 item: 12.44
DSR2023 item: 13.1.2
DSR2023 item: 13.2.2
DSR2023 item: 13.7.2
DSR2023 item: 13.16.1
DSR2023 item: 13.83.2
DSR2023 item: 13.47.1
DSR2023 item: 13.61.1
DSR2023 item: 13.80
DSR2023 item: 17.1.1
DSR2023 item: 17.4.2
DSR2023 item: 17.7B
DSR2023 item: 17.28.1.1
DSR2023 item: 17.31
DSR2023 item: 17.72
DSR2023 item: 17.74
DSR2023 item: 18.7.2
DSR2023 item: 18.7.3
DSR2023 item: 18.8.1
DSR2023 item: 18.8.2
DSR2023 item: 18.8.3
DSR2023 item: 18.13.1
DSR2023 item: 18.17.1
DSR2023 item: 18.18.3
DSR2023 item: 18.48A
DSR2023 item: 18.54.1
DSR2023 item: 18.54.3
DSR2023 item: 18.55.3
DSR2023 item: 18.63
DSR2023 item: 18.64
DSR2023 item: 18.74.2
DSR2023 item: 18.75.3
DSR2023 item: 19.4.1.1
DSR2023 item: 19.7.1.1
DSR2023 item: 19.33
DSR2023 item: 22.14.1
DSR2023 item: 22.22A
DSR2023 item: 16.68
DSR2023 item: 11.1.2
DSR2023 item: 11.13.1
DSR2023 item: 10.25.2
DSR2023 item: 4.1.3
DSR2023 item: 11.3.1
DSR2023 item: 21.1.1.2
DSR2023 item: 21.1.2.2
DSR2023 item: 21.3.1
DSR2023 item: 21.18
DSR2023 item: 10.3
DSR2023 item: 8.2.2.2
DSR2023 item: 9.100.1
DSR2023 item: 10.2
DSR2023 item: 12.42.1.2
DSR2023 item: 12.42.5.2
DSR2023 item: 15.2.1
DSR2023 item: 15.7.4
DSR2023 item: 15.3
PART 20: NON-SCHEDULED ITEMS (CIVIL)
Grouting inside of pressed steel frames
Providing, fixing, jointing and testing
Providing and fixing UPVC Floor Trap of
Construction of 2.3m (L) x 1.1m (W) x 1.
Breaking into pieces, filling, spreading
"Drilling of perfectly vertical bore hol
Providing And Installation ISI marked, U
Providing And Installtion ISI mark, 32 m
with socket finolex/ kishan/prince/sudh
Providing 01 no. sumbersible pump of mak
Providing and fixing miscelaneous items-
Providing and fixing miscelaneous items-
(c ) MS clamp 32mm with nut and bolt set
Providing and fixing miscelaneous items-
Providing and fixing miscelaneous items-
Sumbersible pump installation and commis
PART 30: SCHEDULED ITEMS (ELECTRICAL)
PART 40: NON-SCHEDULED ITEMS (ELECTRICAL
70Watt LED flood light
Supply of 20W LED Tube Light
Supply of Ceiling Fan 1200 mm
Supply of 250mm exhaust fan
supply of 3.5Cx35 sqmm AR Al cable
Supply of 36W 2X2 LED Light
supply of 3.5Cx50 sqmm AR Al cable
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.42 MB
TD9900320924.rar
Tender Documents • 18.53 MB
BOQ_109168.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid