| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance MUZAFFARNAGAR MEERUT ROAD GEHRA BAGH OPP PWD WARE HOUSE MUZAFFARNAGAR UTTAR PRADESH 251002 | MUZAFFARNAGAR | UTTAR PRADESH | 251002 | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Admitted-Finance 23 B NEW MANDI NEW MANDI MUZAFFARNAGAR MUZAFFARNAGAR UTTAR PRADESH 251001 INDIA | MUZAFFARNAGAR | UTTAR PRADESH | 251001 | Admitted-Finance |
| 4 | Admitted-Finance 19 A DURGA BARI SADAR BAZAR MEERUT MEERUT MEERUT UTTAR PRADESH 250001 | MEERUT | UTTAR PRADESH | 250001 | Admitted-Finance |
Tender Value
₹6.9 L
EMD Value
₹7,000
Closing Date
2 Feb 2024, 12:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE ETC MUZAFFARNAGAR
NEAR 132 KV SUB STATION BHOPA ROAD MUZAFFARNAGAR
ETC MU T 47 2023 24
2024_UPTCL_882467_1
ETC MU T 47 2023 24
Open Tender
Electrical Works
Item Rate
60 days
MUZAFFARNAGAR
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
EE ETD MUZAFFARNAGAR
₹7,000
13 Feb 2024
18 Jan 2024
2 Feb 2024
18 Jan 2024
2 Feb 2024
18 Jan 2024
Amount
Following work is to be carried out for construction of 132 KV & 33 KV bay for New 40 MVA T/F-III at 132KV S/S Purkazi.
Erection of Main & Auxiliary structure consisting of AKR, BKR, ABR, APR, YMR, DKR, BBL, BTI, BCT, ALP, ABL etc. including all allied works complete in all respect. Department shall provide structure & nut and bolts etc. The works shall be strictly carried out as per drawing & technical specification.
Erection of equipment as per instructon manual of various equipments and technical specification including shifting of material, equipments from store to erection site including all their associated work with the help of crane provided by the contractor at their own cost for completion of the job satisfactorily:-
145 KV CB with structure
145 KV CTs
145 KV PTs
145 KV Bus isolator
145 KV Tandem isotator
132 KV CT & PT Junction Box
33 KV VCB with structure
33 KV CTs
33 KV PTs
33 KV Bus isolator
33 KV Line isolator
33 KV PI on ALP type structure
33 KV CT & PT Junction Box
T/F Control & Relay Panel
T/F RTCC Panel
Apex Energy Meter Panel
Safe Dismantling of equipment with structure as per instructon manual of various equipments and technical specification including shifting of material, equipments including all their associated work with the help of crane provided by the contractor at their own cost for completion of the job satisfactorily:-
145 KV Bus isolator
33 KV VCB
33 KV CTs
33 KV Bus isolator
Stringing and proper sagging of new 132 KV Main bus bar section (R, Y & B-phase) by ACSR Moose conductor for 12m Span. The work include cutting of conductor, making of bus bar of appropriate length, hoisting of 70 KN Disc insulator with tension fitting etc.
Stringing and proper sagging of new 132 KV Transfer Bus Bar section (R, Y & B-phase) by ACSR Moose conductor for 12m Span. The work include cutting of conductor, making of bus bar of appropriate length, hoisting of 70 KN Disc insulator, tension fitting etc.
Stringing and proper sagging of new 132 KV Overhead Jack Bus section (R, Y & B-phase) by ACSR Panther conductor for approx. 40 Mtr. span. The work include cutting of conductor, making of bus bar of appropriate length, hoisting of 70 / 120 KN Disc insulator, tension fitting etc.
Complete jumpering work of different equipments i.e. BI, CB, CT, PT, LI, HV & LV Bushing etc. by Single / Twin ACSR Moose / Zebra / Panther conductor including cutting, tilting & tightening with PG Clamps/terminal clamps at both ends as per technical standard and direction of supervising engineer to complete the following 132 KV Bay in all respect. 1. 132 KV Bus Coupler Bay 2. 40 MVA T/F-I HV & LV Bay Side Bay 3. 40 MVA T/F-III HV & LV Bay Side Bay
Complete jumpering work of different equipments i.e. BI, CB, CT, PT, LI, HV & LV Bushing etc. by Single / Twin ACSR Moose / Zebra / Panther conductor including cutting, tilting & tightening with PG Clamps/terminal clamps at both ends as per technical standard and direction of supervising engineer to complete the 33 KV Purkazi Bay in all respect.
Laying and dressing of control cable in trenches after removal of trench cover as per cable schedule including clamping with 25x3mm Al. strip and GI Nut and Bolts including cutting, peeling of the control cable.
2X2.5 Sq.mm.
4X2.5 Sq.mm.
6X2.5 Sq.mm.
Termination of cables as laid above as per cable schedule including making necessary holes in panel base plate or junction box as per site requirement. Fixing of cable glands of appropriate size. Supply & providing ferrules on each core of cable & its terminaton at both ends and all other associated work.
2X2.5 Sq.mm.
4X2.5 Sq.mm.
6X2.5 Sq.mm.
Earthing of structure and equipments:-
Cutting, straightening, bending, laying 800 mm. below in side ground and above ground of following size of MS flat for earthing of Main structure, Auxiliary structure, equipments structure including welding with main earthmat and with object to be earthed, excavation of soil & its back filling, painting and all other associated works as required to complete the work satisfactorily.
MS flat of size 75x10 mm.
MS flat of size 50x6 mm.
MS flat of size 25x6 mm.
Earthing of 33 KV LAs with 75x10 mm MS flat after making rectangular configuration along with Six Nos. (3 meter length) 40 mm dia M.S. electrodes as per drawing & technical specification.
Earthing of 120 KV LAs with 75x10 mm MS flat after making rectangular configuration along with Six Nos. (3 meter length) 40 mm dia M.S. electrodes as per drawing & technical specification.
Sorting /Counting stacking erection mark wise and proper loading of structure in truck/trailer
Safe carriage of loaded structure from EFU naini , Allahabad to 132 KV Sub-station Purkazi approximate distance 880 Km.
Unloading of carriage structure from the truck/trailer. Its sorting, counting & proper stacking at the respective Sub-station premises as per direction of supervision engineer
Shifting of 132 KV Bus Coupler Bay and 40 MVA T/F-I HV Bay to newly constructed 132 KV Bay. Work includes shifting of CB control cable connection from 132 KV Bus Coupler Panel to 40 MVA T/F-I Panel and shifting of CT and CB cable connections from 40 MVA T/F-I Control & Relay Panel to 40 MVA T/F-III Control & Relay Panel and other necessary work to complete the job.
M/s S.S. Refregeration
KARAN SINGH
Technocrat Electrical
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .