Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹25.5 LAccepted-Finance | ₹25.5 L | 1 | Accepted-Finance OK |
| 2 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹25.5 L
EMD Value
₹51,000
Closing Date
11 Aug 2026, 10:00 amClosed
executive officer
NAGAR PALIKA MAHWA
NAGAR PALIKA SEEMA KSHETRE KE WARD N 01 SE 35 ME NALI MARAMAT KARYA
2026_DLB_582277_1
501
Open Tender
Civil Works
Percentage
365 days
WORK
gst pan aadhar emd fees pross fees reg copy
2 documents required · 2 mandatory
₹500
executive officer nagar palika mahwa
₹51,000
Yes
15 Aug 2026
5 Aug 2026
11 Aug 2026
5 Aug 2026
11 Aug 2026
5 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling of existing structures like culverts, bridges, retaining walls, CC road and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all
lifts and lead of 50 metres as directed by Engineer.Prestressed /Reinforced cement concrete with separating, cleaning, straightening and cutting of bars | 130.5 | CUM | 1,692 | ₹2,20,806 |
| 2 | Dismantling of existing structures like culverts, bridges, retaining walls, CC road and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all lifts and lead of 50 metres as directed by Engineer.Cement Concrete Grade M-15 and above and PCC blocks | 210 | CUM | 678 | ₹1,42,380 |
| 3 | Earth work in excavation in foundation, trenches etc. including
dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. | 342.9 | CUM | 229.5 | ₹78,695.55 |
| 4 | Random rubble masonry with hard stone in foundation and plinth : Cement mortar 1:6 (1 cement : 6 coarse sand) | 102.2 | CUM | 4,860 | ₹4,96,692 |
| 5 | Reinforcement for R.C.C. work at all levels including straightening, cutting, bending, placing in position and binding all complete Cold twisted bars | 1,264.85 | KG | 83.3 | ₹1,05,362 |
| 6 | Providing and laying lean cement concrete 1:4:8 in Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm,
aggregate cement ratio not to exceed 15:1, aggregate gradation
after blending to be as per table 600-1, cement content not to be
less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in concrete mixer, laid manually, compacted with surface vibrator, finishing and curing complete as per clause 601, 112 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. | 36 | CUM | 2,955 | ₹1,06,380 |
| 7 | Providing and laying un-reinforced, dowel jointed, plain cementconcrete mix With Concrete Mixer & vibrator pavement over aprepared sub base with 43 grade cement , coarse and fineaggregate conforming to IS: 383, maximum size of coarse aggregatenot exceeding 25 mm, mixed as per approved mix design, laid,spread, compacted and finished in a continuous operation including
provision of contraction, expansion, construction and longitudinaljoints, joint filler, separation membrane, sealant primer, joint sealant,debonding strip, admixtures (if required) as approved, curingcompound, finishing to lines and grades complete as per drawingand as per clause 602, 112 of MoRT&H specification including allmaterial, labour, machinery, lighting, guarding and maintenance of diversion.9.5.1 PCC M-20 cum 5,790.00 | 76.05 | CUM | 5,790 | ₹4,40,329.5 |
| 8 | Centring and shuttering with plywood or steel sheet upto two stories ( each story of height upto 3.5 metre from floor level) including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete. | 540 | SQM | 236.5 | ₹1,27,710 |
| 9 | Cement plastering including T&P, scaffolding, material and complete labour, including cost of water, curing, racking of joints etc. with 15
mm cement plaster on the rough side of single or half brick wall of mix : including Providing /mixing of synthetic fibers compulsorily
complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to
900 gms per cum of Concrete/ mortar | 288 | SQM | 263.5 | ₹75,888 |
| 10 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position
and applying a priming coat of approved steel primer all complete: | 2,500 | KG | 114.5 | ₹2,86,250 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.36 MB
BOQ_1034572.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .