Construction of Toe Wall & Bricks Edge Solling From House of Pankaj Yadav via Shankar Sah House to Arun Sharma House AND Construction of Drain With Cover & PCC Road from House of Arvind Jaiswal to Binod Bhagat House AND Construction of Drain With Cover from House of Binod Bhagat to Sikendra Pandit House AND Construction of RCC Drain with Cover Road Crossing From Near House of Sikendra Pandit in Ward No -- 08
135292
03/2026-2027/NAUGACHIA/GR 18
Open Tender
CIVIL
Bhagalpur
• VALID CLASS-IV REGISTRATION WITH RCD (As per NIT) (Attached or Not Attached)
• PAN CARD (As per NIT) (Attached or Not Attached)
• G.S.T. (As per NIT) (Attached or Not Attached)
• EARNEST MONEY (As per TENDER) (Attached or Not Attached)
• AFFIDAVIT (As per NIT) (Attached or Not Attached)
• VALID CHARACTER (As per NIT) (Attached or Not Attached)
• EXISTING COMMITMENT (As per NIT) (Attached or Not Attached)
• COST OF BOQ (As per TENDER) (Attached or Not Attached)
• BID PROCESSING FEE (As per TENDER) (Attached or Not Attached)
CIVIL
PERCENTAGE
L1
1
2 documents required · 2 mandatory
₹5,000
Processing Fee: 1180
₹49,500
Office Nagar Parishad, Naugachia
5 Jul 2026
5 Jul 2026
14 Jul 2026
5 Jul 2026
13 Jul 2026
5 Jul 2026
9 Jul 2026
NAGAR PARISHAD NAUGACHIA, BHAGALPUR (BIHAR)
Bill of Quantity for Construction of Toe Wall & Bricks Edge Solling From House of Pankaj Yadav via Shankar Sah House to Arun Sharma House AND Construction of Drain With Cover & PCC Road from House of Arvind Jaiswal to Binod Bhagat House AND Construction of Drain With Cover from House of Binod Bhagat to Sikendra Pandit House AND Construction of RCC Drain with Cover Road Crossing From Near House of Sikendra Pandit in Ward No -- 08
Estimated cost:- Rs. 2,474,159
Earnest money:- Rs. 49,500.00
Time of Completion:- 03 Months
Cost of BOQ:- Rs. 5,000.00
S.NO. ITEM OF WORKS UNIT QTY. RATE (in fig.) Amount
1 BCD/ 15.2.1 Demolishing cement concrete including disposal of material within 50 metre lead: 1:3:6 or richer mix M³ 16.832 970.9 Rs. 16,342
2. BCD/ 15.7.4 Demolishing brick work including stacking of serviceable material and disposal of unserviceable material within 50 meters lead:In cement mortar M³ 6.372 823.7 Rs. 5,249
3. BCD/ 15.24 Demolishing dry brick pitching in floors, drains etc. including stacking serviceable material and disposal of unserviceable material within 50 metres lead. M³ 2.867 535.6 Rs. 1,536
4. BCD 2.8 Earth work in excavation in foundation trenches or drains(not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m . including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All Kinds of soil M³ 80.075 360.70 Rs. 28,883
5. BCD 2.28 Supplying and Filling in plinth with local sand and under floors including, watering, ramming consolidating and dressing complete. M³ 759.299 287.30 Rs. 218,147
6. BCD 11.72 Providing designation 100 A one brick on flat soling joints filled with local sand including cost of watering, taxes, royalty all complete as per building specification and direction of E/l, M² 234.192 283.30 Rs. 66,347
7. BCD/ 11.73 Providing 100A Brick Edge soling joints filled with local sand including cost of watering, taxes, royalty all complete as per building specification and direction of E/l, M² 754.647 444.80 Rs. 335,667
8. BCD 4.1.3 Providing and laying in position cement concrete of specified grade exluding the cost of centring and shuttering-all work upto plinth level.1:2:4(1 Cement: 2 coarse sand:4 graded stone aggregate 20 mm nominal size) all Complete job as per direction of E/I. M³ 10.929 3998.10 Rs. 43,695
9. BCD 4.1.2 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering-all work upto plinth level. 1:1.5:3(1 Cement :1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) M³ 22.634 4420.80 Rs. 100,060
10. BCD 6.1.12/1 Brick work with bricks of class designation 100A in foundations and plinth in : Cement mortar 1.:4 (1 cement: 4 coarse sand ) M³ 56.619 5017.90 Rs. 284,108
11. BCD 13.11.2+ 13.26 Cement plaster in course sand 12 mm cement plaster of mix: 1:4(1 cement :4 coarse sand) Neat cement punning M³ 172.862 193.40 Rs. 33,432
12. BCD 5.1.2 Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring, shuttering, finishing and reinforcement-All work puto plinth level 1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) M³ 28.755 4688.30 Rs. 134,812
13. BCD/ 5.2.2 Reinforced cement concrete work in wall (any thickness), including attached pilasters, buttresses ,plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts, etc. upt floor five level excluding cost of centring, shuttering, finishin and reinforcement. 1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20mm nominal size) M³ 7.431 5670 Rs. 42,134
14. BCD 5.22. Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.
14.(i) BCD 5.22.7B Thermo Mechanically Treated bars TMTC-500-10 mm dia. KG 2096.84 92.60 Rs. 194,168
14.(ii) BCD 5.22.7C Thermo Mechanically Treated bars TMTC-500-12 mm dia. KG 1521.75 90.80 Rs. 138,175
15. BCD 4.3.1 Centring and shuttering including strutting,propping etc. and removal or form work for Foundations,footings, bases Columns M² 417.443 211.10 Rs. 88,122
16. RCD 3.11 Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.) M³ 72.0675 122.09 Rs. 8,799
17 Carriage of Materials
(i) Coarse sand- 65 KM(P)+ 1KM(K) M³ 47.965 1586.55 Rs. 76,099
(ii) Stone Chips-95 KM(P) + 1KM (US) M³ 59.72 2194.23 Rs. 131,046
(iii) Bricks-7KM (P)+ 1KM(K) %/Nos. 74724.692 940.97 Rs. 70,314
(iv) Local Sand-2KM (P)+1KM (K) M³ 785.452 310.42 Rs. 243,820
18 Difference cost of Material with G.S.T.
(ii) Bricks %/Nos. 74725 365.61 Rs. 27,320
19 Recovery of Servicable bricks Less (-) 30 % %/Nos. -1369 6,081.05 Rs. -8,326
20 Add seignorate fee
(i) Coarse sand M³ 47.97 17.58 Rs. 843
(ii) Stone Chips M³ 59.72 59.54 Rs. 3,556
(iii) Bricks %/Nos. 74725 512.80 Rs. 38,319
(iv) Local Sand M³ 785.45 14.19 Rs. 11,146
Total Rs. 2,342,291
21. L.S. Add for sign.board,scheme name plate,Quality test & Colour photo graph (Payment after providing actual voucher) Set 1 6000.00 Rs. 6,000
Total Rs. 2,348,291
22 18 % GST IN PLACE OF 12 % GST (MULTIPLYING FACTOR = 1.0536) Rs. 2,474,159
G.Total Rs. 2,474,159
Executive Officer
Nagar Parishad Naugachia
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
NIT 03.pdf
NIT • 4.73 MB
Corrigendum 01.pdf
NIT • 0.31 MB
Corrigendum 02.pdf
NIT • 0.43 MB
B.O.Q Final_Gr-18.(W-08).xlsx
NIT • 0.02 MB
Download all tender documents and submit your bid