| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 CrAccepted-AOC KOLLIDAM | ₹1.6 Cr | L1 | Accepted-AOC Lowest Amount Quoted |
| 2 | L2₹1.6 Cr+₹2.1 L (1.28%)Rejected-Finance | ₹1.6 Cr+₹2.1 L (1.28%) | L2 | Rejected-Finance Highest Amount Quoted |
Tender Value
₹1.7 Cr
EMD Value
₹1.7 L
Closing Date
10 Jan 2025, 3:00 pmClosed
District Collector office,mayiladuthurai
District Collector office,mayiladuthurai
Strenthening 5 Year Maintence Of Road From Mahendirapalli - kattur Road (R-29) Mahendrapalli Panchayat in Kollidam Block Km 0/0 - 2/500 At Mayiladuthurai district under NABARD XXX - 2024-25
2024_RDTN_515149_1
DIPR/5603/TENDER/2024 dt 26.12.2024
Open Tender
Civil Works - Roads
Item Rate
180 days
Mahendrapalli
Please refer Tender documents.
12 documents required · 12 mandatory
₹0
₹1.7 L
District Collector office,mayiladuthurai
11 Mar 2025
30 Dec 2024
10 Jan 2025
31 Dec 2024
10 Jan 2025
31 Dec 2024
30 Dec 2024
Amount
Strenthening Of Road From Mahendirapalli - Kattur Road(R - 29) Km 0/0 - 2/500 Mahendrapalli Pachyat in Kollidam Block At Mayiladuthuai district
Picking the existing black top/ WBM surface to 50 MM depth including labour, hire charges d plants and all other incidental charges etc. complete as per MOST specification.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A
Construction of subgrade for 300mm depth by using picked material obtained from the existing surface by mechanical means and then adding 50% of defict materials by using stone dust obtained from quarry with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.( subgrade using stone dust to improve CBR 7 to 9))
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM/WBM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM/WBM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and
BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 c
Road marking with hot applied thermoplastic compound with reflecting glss beads on bituminous surface
Provision for ,Hm stone,
Provision for ,Km stone,
Const of Retainning wall
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering shuttering including necessary supports for planesurface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etcusing mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (countrywood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centrecomplete complying with standard specifications and as directed by departmental Officers etc.Complete.
Up to Ground Level
Provision for Name board
90 cm Equilateral triangle (Cautionary) sign Bord
Towards the charges for routline maintenance of the road work executed under NABARD including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonalgrowth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost For the First Year from the date of completion of work
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
Vijaya Builders (BID ID -1231129)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .