| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹33.4 LAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹33.6 L+₹25,527.40 (0.76%)Admitted-Finance | L2 | Admitted-Finance | |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | KRISHNA ENTERPRISES L2 | M/s Raj Brothers and Suppliers Contractor L1 |
|---|---|---|---|---|---|
| 1.01 | E/W in excavation in Pond in all types of Soil by poclain machine including all charges for first step.Quantity same as rear with 30m Lead and Lift upto 1.50m | 90.1 | cum | 87.12 ₹7,849.51 | 86.46 ₹7,790.05 Lowest |
| 1.02 | E/W in excavation in Pond in all types of Soil by poclain machine including all charges for second step. | 9,330.28 | cum | 87.12 ₹8,12,853.99 | 86.46 ₹8,06,696.01 Lowest |
| 1.03 | E/W in excavation in Pond of slush Soil by poclain machine including all charges for first and second step Quantity same as rear with extra for slush | 8,067.85 | cum | 138.11 ₹11,14,250.76 | 137.06 ₹11,05,779.52 Lowest |
| 1.04 | E/W in excavation in Pond on bund ordanary Soil dresing | 4,704 | cum | 6.38 ₹30,011.52 | 6.33 ₹29,776.32 Lowest |
| 1.05 | Excavation in foundation in ordinary soil i\c lift upto 1.5 and lead upto 30 m etc all comp work for INLET 900MM , Ramp. | 206.38 | cum | 89.1 ₹18,388.46 | 88.43 ₹18,250.18 Lowest |
| 1.06 | C.C IN 1:3:6 CEMENT ,C/SAND AND 40 MMGAUGE Stone BALLAST ETC ALL COMP. WORK FOR INLET 900MM (3 NO.) , Ramp . | 42.07 | cum | 5,989.5 ₹2,51,978.27 | 5,944.13 ₹2,50,069.55 Lowest |
| 1.07 | M-150 B/W IN 1:4 CEMENT & C/SAND ETC ALL COMP. WORK FOR INLET 900MM (3 NO.), Ramp . | 102.03 | cum | 4,900.5 ₹4,99,998.02 | 4,863.38 ₹4,96,210.66 Lowest |
| 1.08 | 12 MM THICK PLASTER IN 1:4 CEMANT AND C/SAND ETC ALL COMP. WORK | 196.6 | sqm | 163.35 ₹32,114.61 | 162.11 ₹31,870.83 Lowest |
| 1.09 | C.C IN 1:2:4 CEMENT,C/SAND WITH 20 MM GAUGE S/GRIT ETC ALL COMP. WORK FOR INLET 900MM (3NO.), Ramp | 5.22 | cum | 6,930 ₹36,174.6 | 6,877.5 ₹35,900.55 Lowest |
| 1.10 | SUPPLY OF RCC HUME PIPE NP-3 (S&S TYPE ) ISI MARK FOR INLET 900MM (3NO.) | 30 | RM | 4,729.33 ₹1,41,879.9 | 4,693.5 ₹1,40,805 Lowest |
Tender Value
Refer Docs
EMD Value
₹3.4 L
Closing Date
16 Feb 2021, 11:00 amClosed
SUPERINTENDING ENGINEER, MINOR IRRIGATION CIRCLE
OFFICE OF SUPERINTENDING ENGINEER, MINOR IRRIGATION CIRCLE, JAGRITI VIHAR, MEERUT
RENOVATION OF POND IN VILLAGE-SIKANDRABAD DEHAT, BLOCK-SIKANDRABAD, DISTT-BULANDSAHAR
2021_UPMID_553139_1
4259/E-5/2020-21
Open Tender
Civil Works - Water Works
Item Rate
30 days
SIKANDRABAD DEHAT
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION
₹3.4 L
Yes
17 Feb 2021
10 Feb 2021
16 Feb 2021
10 Feb 2021
16 Feb 2021
10 Feb 2021
Amount
E/W in excavation in Pond in all types of Soil by poclain machine including all charges for first step.Quantity same as rear with 30m Lead and Lift upto 1.50m
E/W in excavation in Pond in all types of Soil by poclain machine including all charges for second step.
E/W in excavation in Pond of slush Soil by poclain machine including all charges for first and second step Quantity same as rear with extra for slush
E/W in excavation in Pond on bund ordanary Soil dresing
Excavation in foundation in ordinary soil i\c lift upto 1.5 and lead upto 30 m etc all comp work for INLET 900MM , Ramp.
C.C IN 1:3:6 CEMENT ,C/SAND AND 40 MMGAUGE Stone BALLAST ETC ALL COMP. WORK FOR INLET 900MM (3 NO.) , Ramp .
M-150 B/W IN 1:4 CEMENT & C/SAND ETC ALL COMP. WORK FOR INLET 900MM (3 NO.), Ramp .
12 MM THICK PLASTER IN 1:4 CEMANT AND C/SAND ETC ALL COMP. WORK
C.C IN 1:2:4 CEMENT,C/SAND WITH 20 MM GAUGE S/GRIT ETC ALL COMP. WORK FOR INLET 900MM (3NO.), Ramp
SUPPLY OF RCC HUME PIPE NP-3 (S&S TYPE ) ISI MARK FOR INLET 900MM (3NO.)
LAYING OF HUME PIPE IN POSITION(LABOUR ONLY ) I/C LABOUR AND T& P ETC ALL COMPL. WORK FOR INLET 900MM (3NO.)
FIXING OF JOINT IN HUME PIPE WITH JUIT AND CEMENT ETC I/C COST OF ALL MATERIAL LABOUR AND T&P ETC REQUIRD FOR PROPER COMPLETION OF THE WORK FOR INLET 900MM (3NO.)
FLUSH POINTING WORK IN 1:2 WITH CEMENT & C/SAND ETC ALL COMPL WORK
DEWATERING BEFORE AND DURING DIGGING
PLANTATION OF TREE (224 nos.) , R.C.C. PILLERS (SIZE 0.15X0.12X1.80M) GROUTING (220 Nos.) & barbed wire fancing (3360 mtr) for RCC pole complete work
PHOTO GRAPHY BEFOR AND DURING THE WORK
Supply & Fixing of Signing Board/STONE BOARD
KRISHNA ENTERPRISES
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .