| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 CrAccepted-Finance BBMB SUNDERNAGAR HIMACHAL PRADESH | SHIMLA | HIMACHAL PRADESH | 172101 | ₹2.4 Cr | L1 | Accepted-Finance L1 |
| 2 | L2₹2.5 Cr+₹2.2 L (0.91%)Rejected-Finance | ₹2.5 Cr+₹2.2 L (0.91%) | L2 | Rejected-Finance L2 |
Tender Value
₹2.3 Cr
EMD Value
₹4.7 L
Closing Date
15 Jul 2026, 5:00 pmClosed
Executive Engineer Bharmour Division HPPWD Bhar
Executive Engineer Bharmour Division HPPWD Bharmour
Construction of Civil supplies Godown at Thalla, Bharmour, Distt. Chamba, SH Building portion including Water Supply Sanitary Installation, Septic tank with Soak pit, Rain Water Harvesting System, Site developement.
2026_PWD_138499_1
8139-8238 dated 25-06-2026
Open Tender
Civil Works
Percentage
Bharmour
Please refer Tender documents.
11 documents required · 11 mandatory
₹7,000
₹4.7 L
21 Jul 2026
9 Jul 2026
16 Jul 2026
9 Jul 2026
15 Jul 2026
9 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Excavation work by mechanical means (hydraulic excavator)/ manual in all height and depths and in all kind of soil including saturated soils comprising of pick work, jumper work, pick jumper work, blasting work both in soft and hard rocks, chiseling/ wedging out of rock (where blasting is prohibited) and their intermediate classification of soil , setting out true to the required line, grades, width, cutting and trimming of side slopes as shown in the drawing and if water is met with in the excavation due to springs, seepage, rain and other causes it shall be removed by the suitable diversion pumping or bailling out and excavation shall be kept dry wherever so required by the contractor at his own cost as directed by the Engineer-In-Charge and disposal all surplus excavated soil in acquired width or at an approved dumping site including its stacking leveling dressing including all lead and lifts by head load, mechnical transportation or by any oyher mode of transportation with all cost of labours, machineries and other incidentals to complete the work as per HP PWD specification. Any loss to the public/ private property during the course of execution and disposal of unserviceble meterial shall be the absolute responsibility of the contractor which shall have to be compensated by him in all case. The rate is including octroi, royality, Malkana, toll tax, GST or other taxes imposed by the Government. | 8,070.23 | - | 357.4 | ₹28,84,300.2 |
| 2.01 | Excavation work by mechanical means (hydraulic excavator)/ manual in foundation trenches or drains in earth work of all kind of soil such as pick work, jumper work, blasting work, jumper blasting work soft and hard blasting and saturated soil, de-watering, including wedging out rocks where blasting is prohibited, chiseling or any other mixed variety of soil, including shoring, strutting or bailing out water upto any depth or any height quantum of water including dewatering removal of slush and stacking the serviceable and unserviceable material clear from the edge of excavation and as per direction of Engineer-In-Charge and returning the stacked soil in 15 cm (Fifteen centimetre) layers, when required into plinths, side of foundation etcetera consolidating each deposited layer by ramming watering and then disposing of all excavated earth as directed by the Engineer-In-Charge, within all leads, lifts and other incidentals as per specifications, approved drawing, design and as directed by the Engineer-In-Charge. The rate is inclusive of octroi, royality, Malkana, Toll tax, sale tax, GST and any other taxes imposed by the Government. | 659.67 | - | 531.2 | ₹3,50,416.7 |
| 3.01 | Excavation work by mechanical means (hydraulic excavator)/ manual overall areas in earth work of all kind of soil such as pick work, jumper work, blasting work, jumper blasting work soft and hard blasting and saturated soil, de-watering, including wedging out rocks where blasting is prohibited, chiseling or any other mixed variety of soil, including shoring, strutting or bailing out water upto any depth or any height quantum of water including dewatering removal of slush and stacking the serviceable and unserviceable material clear from the edge of excavation and as per direction of Engineer-In-Charge and returning the stacked soil in 15 cm (Fifteen centimetre) layers, when required into plinths, side of foundation etcetera consolidating each deposited layer by ramming watering and then disposing of all excavated earth as directed by the Engineer-In-Charge, within all leads, lifts and other incidentals as per specifications, approved drawing, design and as directed by the Engineer-In-Charge. The rate is inclusive of octroi, royality, Malkana, Toll tax, sale tax, GST and any other taxes imposed by the Government. | 49.64 | - | 411.3 | ₹20,416.93 |
| 4.01 | Excavating trenches of required width for pipes, cables, etcetera including excavation for sockets, and dressing of sides, ramming of bottoms, upto any depth including getting out the excavated soil, then returning the soil as required, in layers not exceeding 20 cm (Twenty centimetre) in depth, including consolidating each deposited layer by ramming, watering, etcetera and disposing of surplus materials/excavated soil as per specification, approved drawing, design, specification and as per the entire satisfaction of Engineer-In-Charge, including carriage of material within all leads, lifts and other incidentals as per specifications, approved drawing, design and as directed by the Engineer-In-Charge. The rate is inclusive of octroi, royality, Malkana, Toll tax, GST and any other taxes imposed by the Government. . | 125 | - | 196.2 | ₹24,525 |
| 5.01 | Consolidation of sub grade with Road Roller 8-10 (eight - ten) Tonne, including making good the undulation etcetera with earth or quarry soil etcetera and rerolling the sub-grade completed as per HP.PWD specifications including carriage of material within all leads, lifts and other incidentals, as per approved specifications drawing, design and as directed by the Engineer-In-Charge. The rate is inclusive of octroi, royality, Malkana, Toll tax, GST and any other taxes imposed by the Government. | 300 | - | 1.4 | ₹420 |
| 6.01 | Providing and construction of granular sub-base 150mm (one hundered fifty milimeters) compacted thickness by providing well graded materials as per table 400.1 spreading in uniform layers with tractor mount grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel roller 80-100 (Eighty-hundred) kN static roller to achieve the desired density, complete as per MORD Technical Specification section 400 for grading-I material, including carriage of material within all leads, lifts and other incidentals, as per approved specifications drawing, design and as directed by the Engineer-In-Charge. The rate is inclusive of octroi, royality, Malkana, Toll tax, GST and any other taxes imposed by the Government. | 45 | - | 4,083.6 | ₹1,83,762 |
| 7.01 | Providing, laying, spreading and compacting by mechanically means stone aggregate size 53mm to 22.4mm (fifty three millimeter to twenty two point four millimeter) Grading-III size [75mm( seventy five millimeters) compacted thickness] to water bound macadam specification including spreading in uniform thickness using template, hand packing, rolling with three wheel 80-100 (eighty-Hundred) K.N. static roller in stages to proper grade and camber, applying and brooming, stone screening type-B of size 11.2mm (eleven point two milimetres) nominal size at the rate of 0.18Per cubic metre (zero point eighteen) cubic metres per 10 Per square metre (per ten square metres) and to fill up the interstices of coarse aggregate, watering and compacting to the required density as per MORD technical specifications section 400 and as per the entire satisfaction and direction of Engineer–In-Charge including carriage of materials within all leads, lifts and other incidental. The rate is including octroi, royality, Malkhana, toll tax, GST and any other taxes imposed by the Government. | 22.5 | - | 4,828.8 | ₹1,08,648 |
| 8.01 | Supplying and filling in plinth with sand under floors,including watering, ramming, consolidating and dressing complete including carriage of material within all leads, lifts and other incidentals. The rate is inclusive of octroi, royality, Malkana, Toll tax, GST and any other taxes imposed by the Government. | 39.48 | - | 3,368.5 | ₹1,32,988.38 |
| 9.01 | Providing & Filling in plinth with hard stone under floors & stone boulder behind retaining walls, including watering, ramming, consolidating and dressing complete including carriage of material within all leads, lifts and other incidentals. The rate is inclusive of octroi, royality, Malkana, Toll tax, GST and any other taxes imposed by the Government. | 200.9 | - | 1,847.7 | ₹3,71,202.93 |
| 10.01 | Providing and laying mechanically mixed and vibrated plain cement concrete 1:4:8 (One cement isto four sand isto eight graded stone aggregate 40mm (Forty millimetre) nominal size) and curing complete excluding cost of form work in Retaining wall/return wall/ breast wall and foundation & plinth complete as per architectural drawings including carriage of material within all leads, lifts and other incidentals, as per approved specifications drawing, design and as directed by the Engineer-In-Charge. The rate is inclusive of octroi, royality, Malkana, Toll tax, GST and any other taxes imposed by the Government. | 586.4 | - | 8,366.7 | ₹49,06,232.88 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.29 MB
GODDAN.pdf
Tender Documents • 4.72 MB
BOQ_205192.xls
BOQ • 0.51 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .