| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.0 LAccepted-Finance BHAGWATI NAGAR JAMMU | L1 | Accepted-Finance lowest | |
| 2 | L2₹1.0 L+₹900 (0.87%)Rejected-Finance | L2 | Rejected-Finance not lowest | |
| 3 | L3₹1.0 L+₹1,500 (1.46%)Rejected-Finance 25 PRATAP COMPLEX GULAB SINGH MARG JAMMU | L3 | Rejected-Finance not lowest |
Tender Value
₹1.1 L
EMD Value
₹2,100
Closing Date
30 Oct 2024, 2:00 pmClosed
Executive Engineer
MID JAMMU
Replacement of damaged components and rewinding of 250 KVA transformer installed at lift irrigation station Pindi Sarochana New.
2024_IFC_261274_1
MID/J/e-NIT/2024-25/85
Open Tender
Repair and Maintenance Works
Item Wise
10 days
Pindi Sarochana new
as per eNIT
8 documents required · 8 mandatory
₹200
EXECUTIVE ENGINEER MID JAMMU
₹2,100
Yes
6 Nov 2024
19 Oct 2024
31 Oct 2024
19 Oct 2024
30 Oct 2024
20 Oct 2024
Replacement of damaged components and rewinding of 250 kva transformer installed at lift irrigation station Pindi Sarochana New
Dismantling of 250kva transformer from its installed position by way of disconnecting of the electric transformer from input and output power connections, lifting of electric transformer from its installed position by using manual labour, crane and then shifting to workshop by using carriage vehicle.Replacement of damaged parts and rewinding to 250kva transformer installed at Lift irrigation station Pindi Sarochana New by way of dismantling of the transformer at workshop and extracting out the damaged coils, LT bushes, HT bushes, HT bush rods, LT bush rods and gasket. Strengthening of the cooling fins of transformer by welding damaged and leaking portions. Rewinding of threenumber HT legs coils with standard gauge wire with proper insulation& taping. Reconditioning of three no’s LT leg coils using quality insulation material. Replacing the flashed core material. Heating to repaired transformer in oven to get required meager value. Properly cleaning the oil tank with scrubbers to remove all carbon deposits. Lowering of the coils inside the sump of the transformer. Providing and fitting of LT bush, HT bush, LT bush rods and HT bush rod sets, new insulator, and sundry items. Refitting of the top cover of transformer by providing and fitting of new gasket sheet. Providing/ filling of 150 liters of fresh transformer oil in oil tank. Testing the continuity of each phase and secure all connection. Shifting back after carrying out repaired transformer to site. Complete job includes cost of material, installation charges and skilled labour charges,loading and un-loading of transformer at Lift irrigation station Pindi Sarochana New and workshop, carriage charges of vehicle (to & fro), testing on no load/ full load , tools & tackles, hire charges of crane. Note:- The Tenderers are requested to visit the site and quote the rate as per site conditions. Any modifications/ alterations of the job, felt necessary if required at the time of actual execution may be /done as per actual site conditions. The firm should offer rebate on old material.
Rebate on Old Parts
M/S RAGHUNATH MECHANICAL AND ELECTRICAL ENGINEERING WORKS (BID ID -2192821)
NATIONAL ELECTRO-MECH COMPANY (BID ID -2198850)
PERFECT ELECTRICAL WORKS
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .