Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹21.7 LAccepted-AOC FLAT NO 1004 BUILDING NO L 11 KEDAR HOUSING SOCIETY 10TH FLOOR SECTOR NO 21 TALOJA PHASE 2 PANVEL RAIGAD NAVI MUMBAI 410208 | NAVI MUMBAI | RAIGAD | MAHARASHTRA | 410208 | L1 | Accepted-AOC L1 | |
| 2 | L2₹24.5 L+₹2.5 L (11.6%)Rejected-AOC | L2 | Rejected-AOC Not L1 | |
| 3 | L3₹24.6 L+₹2.7 L (12.2%)Rejected-AOC COLABA MUMBAI | L3 | Rejected-AOC Not L1 | |
| 4 | L4₹32.2 L+₹10.3 L (46.9%)Rejected-AOC COLABA MUMBAI | YAVATMAL | MAHARASHTRA | 445001 | L4 | Rejected-AOC Not L1 |
Tender Value
₹29.7 L
EMD Value
₹59,320
Closing Date
26 May 2025, 6:00 pmClosed
COL SAIKAT DE CWE NAVY VASCO
CWE NAVY VASCO VASCO DA GAMA GOA 403802
COMPREHENSIVE MAINTENANCE OF LIFTS INSTALLED AT DCRA COLONY AND ACHARAYA ENCLAVE UNDER AGE (E/M) II OF GE (NW) VASCO
2025_MES_705931_1
88941
Open Tender
Civil Works
Item Rate
330 days
Vasco
As per tender
9 documents required · 9 mandatory
₹500
Yes
GE (NW) Vasco
₹59,320
Yes
2 Jul 2025
29 Apr 2025
28 May 2025
29 Apr 2025
26 May 2025
12 May 2025
Amount
Comprehensive maintenance of electrically operated passengers lifts of OTIS make Per Month total 03 Nos lifts at DCRA (13 passengers (884kg) 03 Nos for G+5 floors). (1) Monthly servicing, maintenance shall be carried out by trained lift technician. (2) Monthly servicing, maintenance will be carried out once in a month and servicing report will be submitted to Engr-in-Charge. (3) For any breakdown of any lift will be attended within 06 to 24 Hours (depend on type of fault) and made serviceable subject to availability of stores. (4) Spare parts/material required for replacement shall be provided free of cost. (5) Contractor has to undertake repair/servicing required periodically to UPS & Battery of ARD system as per company recommendation for its smooth functioning complete all as specified and as directed.
Comprehensive maintenance of electrically operated passengers lifts of OTIS make Per Month total 01 Nos lift installed at Acharaya enclave (13 passengers (884kg) 01 Nos for G+8 floors. (1) Monthly servicing, maintenance shall be carried out by trained lift technician. (2) Monthly servicing, maintenance will be carried out once in a month and servicing report will be submitted to Engr-in-Charge. (3) For any breakdown of any lift will be attended within 06 to 24 Hours (depend on type of fault) and made serviceable subject to availability of stores. (4) Spare parts/material required for replacement shall be provided free of cost. (5) Contractor has to undertake repair/servicing required periodically to UPS & Battery of ARD system as per company recommendation for its smooth functioning complete all as specified and as directed.
Comprehensive maintenance of electrically operated passengers lifts of OTIS make Per Month total 01 Nos lift installed at Acharaya enclave (8 passengers (544kg) 01 Nos for G+8 floors. (1) Monthly servicing, maintenance shall be carried out by trained lift technician. (2) Monthly servicing, maintenance will be carried out once in a month and servicing report will be submitted to Engr-in-Charge. (3) For any breakdown of any lift will be attended within 06 to 24 Hours (depend on type of fault) and made serviceable subject to availability of stores. (4) Spare parts/material required for replacement shall be provided free of cost. (5) Contractor has to undertake repair/servicing required periodically to UPS & Battery of ARD system as per company recommendation for its smooth functioning complete all as specified and as directed.
Disconnecting and taking out old/unserviceable Main rope of size 13 mm dia(8/19 Construction) un-galvanised including necessary connection with pulley in machine room and shaft pit complete with clamps, nuts bolts, and washers etc, for high rise building for 8/13/Goods/ passenger lifts complete all as specified and directed. Make:Usha Martin
Disconnecting and taking out old/unserviceable Main rope of size 8 mm dia(8/19 Construction) un-galvanised including necessary connection with pulley in machine room and shaft pit complete with clamps, nuts bolts, and washers etc, for high rise building for 8/13/Goods/ passenger lifts complete all as specified and directed. Make:Usha Martin
Disconnecting and taking down unserviceable Door assembly and Replace with new, including making good of all disturbed places without any extra cost complete all as specified and directed.
Inspection of lift by lift inspector authorised by the Goa State Govt and submission of lift test certificate complete all as specified and directed.
Disconnecting and Taking down unserviceable Elevator Control panel, Supply and installation of New Elevator Control panel with ARD (OGEN2) V3F Geared, Auto door, Full collective, overload relay, Display 12 DC, Brake 110V DC with V3F AC Drive KDL 16 R22A 440V ) complete all as specified and directed.
J D ENTERPRISES (BID ID -3305587)
Veer High Tech Solution (BID ID -3297481)
Escon Elevators Pvt Ltd (BID ID -3300044)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .