Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 CrAccepted-AOC | ₹4.9 Cr | L1 | Accepted-AOC Admit |
| 2 | L2₹4.9 Cr+₹29,363.73 (0.06%)Rejected-AOC | ₹4.9 Cr+₹29,363.73 (0.06%) | L2 | Rejected-AOC L2 |
Tender Value
Refer Docs
EMD Value
₹9.3 L
Closing Date
10 Nov 2022, 3:00 pmClosed
JOINT DIRECTOR/PROJECT DIRECTOR
2nd floor, DRDA, Collectorate, Tiruvarur
MRL15- Udhayamarthandapuram- Melaperumalai Road km 0/0 - 4/285
2022_RDTN_121596_1
TN21329
Open Tender
Civil Works - Roads
Item Rate
270 days
Muthupet block
As per Tender Document
3 documents required · 3 mandatory
₹0
₹9.3 L
2nd floor, DRDA, Collectorate, Tiruvarur
22 Dec 2022
26 Oct 2022
10 Nov 2022
26 Oct 2022
10 Nov 2022
28 Oct 2022
2 Nov 2022
Amount
MRL15-Udhayamarthandapuram-Melaperumalai Road km 0/0 - 4/285
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201.
Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.
Construction embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification (Carted Earth borrow pits)
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Gravel shoulder)
Construction of subgrade for 300mm depth by using picked material obtained from the existing surface by mechanical means and then adding 50% of defict materials by using fly ash obtained from industries with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.( subgrade using fly ash to improve CBR 7 to 9))
Providing, laying and spreading soil on a prepared sub-grade, pulverising, adding the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired 7 days unconfined compressive strength of 1.7Mpa and to form a layer of sub-base as per Technical Specification Clause 404.(Cement Treated Soil Sub-Base)
Providing, laying and spreading soil on a prepared sub-grade, pulverising, adding the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired 7 days unconfined compressive strength of 2.76Mpa and to form a layer of sub-base as per Technical Specification Clause 404.(Cement Treated Soil Base)
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. (Grading III)
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 503.
Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508.
Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeding vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground levels as per drawings and Technical Specification Clause 801
logo board
sign board
Citizen board
Name board
Maintanance board
Provision for kilometre stones
Provision for Hectametre stones
Construction of 1.50 m RCC Slab culvert @ Ch.0/010,1/395,2/950.
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.0/010 Below sill
Culvert @ Ch.1/395 Below sill
Culvert @ Ch.2/950 Below sill
Culvert @ Ch.0/010 Above sill
Culvert @ Ch.1/395 Above sill
Culvert @ Ch.2/950 Above sill
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Culvert @ Ch.2/950
Construction of 2.00 m RCC Slab culvert @ Ch.1/495,3/670.
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Culvert @ Ch.1/495
Culvert @ Ch.3/670
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.1/495 Below sill
Culvert @ Ch.3/670 Below sill
Culvert @ Ch.1/495 Above sill
Culvert @ Ch.3/670 Above sill
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Culvert @ Ch.0/010
Culvert @ Ch.1/395
Construction of 6.00 m RCC Slab culvert @ Ch.0/600,2/625.
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.0/600 Below sill
Culvert @ Ch.2/625 Below sill
Culvert @ Ch.0/600 Above sill
Culvert @ Ch.2/625 Above sill
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Culvert @ Ch.0/600
Culvert @ Ch.2/625
Construction of Pipe culvert @ Ch. 3/475,4/235
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Below Sill)
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Above Sill)
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of Protective work @ Ch. 0/010 L,1/695 R,2/805 L,3/310 L,3/400 L Side
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Ch.3/310 L,3/400 L Side
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Ch.3/310 L,3/400 L Side
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Ch.3/310 L,3/400 L Side
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Below Sill)
Ch.3/310 L,3/400 L Side
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Above Sill)
Ch.3/310 L,3/400 L Side
Providing weepholes in brick masonry / stone masonry , plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(v) : 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709,1024.3.7
Ch.3/310 L,3/400 L Side
Providing and fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing and technical specifications
Ch.3/310 L,3/400 L Side
Construction of Revetment @ Ch.0/265 R,0/685 R,
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Below Sill)
Providing and laying filter material underneath pitching in slopes completed as per drawing and technical specification clause 1302
Providing and laying of pitching of slope /laying of apron with cement concrete blocks of size 300mmX300mm X300mm as per table 1300.1 cast in situ and made with nominal mix of M-15 grade cement concrete as per drawing and technical specifications clause 1301.
Cement concrete 1 : 2: 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.(Above sill)
Dismantling Existing CD works @ 0/010,1/395,1/495,2/625,2/950,3/475,3/670,4/235
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.
Foundation @Ch.0/010,1/395,1/495,2/625,2/950,3/475,3/670,4/235
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.
Body wall,Parapet wall Concrete @ Ch 0/010,1/395,1/495,2/625,2/950,3/475,3/670,4/235
Removing all type of Hume pipe and stacking with a lead of 1000 m including earth work and dismantling of masonry works as per technical specification clause 202
Culvert / Dry Fixing Ch -0/010,1/395,1/495,2/625,2/950,3/475,3/670,4/235
Towards the charges for routline maintenance of the road work executed under PMGSY including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
S.T.RAVICHANDRAN
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .