Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹2.4 Cr
EMD Value
₹3.7 L
Closing Date
28 Dec 2026, 4:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
the Executive Engineer NH Dn Hubli
Office of the Executive Engineer NH Dn Vishweshwar Nagar Hubli-580032
Improvements to Gajendragad Sorab SH-136 from km 161.45 to Km.163.55 Mundaragi Taluk Gadag Dist under Central Road Infrastructure Fund.(Job No CRF-KNT-2026-27-241)
2026_MoRTH_935889_1
EE/NH/HBL/PB1/2026/27/1593-3 Dt26/11/2026
Open Tender
Civil Works - Roads
Item Rate
Mundaragi
As per Tender Doc
6 documents required · 6 mandatory
₹6,120
he Executive Engineer NH Dn Hubli
₹3.7 L
the Executive Engineer NH Dn Hubli
26 Nov 2026
26 Nov 2026
29 Dec 2026
26 Nov 2026
28 Dec 2026
26 Nov 2026
10 Dec 2026
135 days
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness including all labour, hire charges of all machineries etc., complete.with all lead and lift and as per the direction of Engineer in-charge of work In the area of light Jungle by Mechanical means using Dozer. | 0.21 | Ha | 32,646 | ₹6,725.08 |
| - | Scarifying the existing bituminous surface to a depth of 50 mm and disposal of scarified material within all lifts including all labour, usage charges of all machinery etc., complete with all lead and lift and as per the direction of Engineer in-charge of work By Mechanical Means using Hydraulic excavator | 4,730 | Sqmt | 8.1 | ₹38,313 |
| - | Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be usedincluding all lead, lifts, all labour, usage charges of all machinery etc., complete.A) Mechanical Means with all lead and lift and as per the direction of Engineer in-charge | 3,440 | Rmt | 59 | ₹2,02,960 |
| - | Compacting original ground supporting sub grade Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for subgrade construction including all lead, lifts, loading, unloading, all labour, usage charges of all machinery etc.,complete.with all lead and lift and as per the direction of Engineer in-charge | 2,051.1 | Cum | 93 | ₹1,90,752.3 |
| - | Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 laid in layers not exceeding 250 mm thick and compacting it by mechanical means after adding water to its OMC, so as to achieve 97% compaction of maximum dry density and finish the surface to the required camber, grade and cross section etc., speading, grading by motor grador, consolidation by roller including all lead, lifts, loading, unloading, all labour, usage charges of machinery etc., complete. with all lead and lift and as per the direction of Engineer in-charge of work(New road formation) | 1,479.2 | Cum | 475 | ₹7,02,620 |
| - | Granular Sub-Base with Close /Coarse Graded Material (Table:- 400-1)By Mix in Place Method :Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 including protection of edges of GSB layer, cost of all materials, labour, usage charges of all machinery, lighting, guarding, barricading, maintenance of diversion road, loading & unloading all lead, lifts etc., complete with all lead and lift and as per the direction of Engineer in-charge of work (Compacted Thickness)Grading V Material(Loose Graded) | 2,261.8 | Cum | 2,246 | ₹50,80,002.8 |
| - | Construction of wet mix macadam by providing laying, spreading and compacting of graded stone aggregates as per table 400-12&13, including premixing the materail with water at OMC in mechanical mix plant carriage of mixed material tipper to site paver, laying in uniform layers in sub base/ base course on well prepared surface and compacting with vibratory roller to achieve the desired density of 98% including protection of edges of WMM layer, cost of all materials, labour, hire charges of machinery, lighting, guarding, barricading, maintenance of diversion road, loading & unloading, with all lead and lift and as per the direction of Engineer in-charge of work, (Compacted Thickness)laying using grader | 2,365 | Cum | 2,440 | ₹57,70,600 |
| - | Providing and applying primer coat with slow setting (SS1) bitumen emulsion complying with IS 8887 on prepared surface of granular Base including cleaning of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per table -500-3, including cost of all materials, labour, hire charges of machinery, loading, unloading etc., complete, with all lead and lift and as per the direction of Engineer in-charge of work | 9,460 | Sqm | 101.47 | ₹9,59,906.2 |
| - | Providing and applying tack coat with bitumen emulsion (RS1) using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom & dusting by air compressor and spraying including cost of all materials, labour, usage charges of all machinery, loading & unloading etc., complete, with all lead and lift and as per the direction of Engineer in-charge of work | 9,460 | Sqm | 21.34 | ₹2,01,876.4 |
| - | Providing and laying Dense Graded Bituminous Macadam with higher capacity batch type HMP using crushed aggregates as per table 500-7 of specified grading premixed with bituminous binder VG-30 grade paving bitumen as per clause 504.3.1 complying with IS -73-2013 of specified grading, premixed with bituminous binder at 4.5% by weight of total mix and filler,transporting the hot mix to work site, laying with the hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause no. 505 complete in all respects including cost of all materials, labour, usage charges of all machinery, all lead, lifts, loading, unloading, stacking, transporting etc complete, (Compacted thickness), 50 - 75 mm compacted thickness (Grading 2) with 4.50% Bitumen using 60/70 (VG-30) ,with all lead and lift and as per the direction of Engineer in-charge of work | 473 | Cum | 13,551.85 | ₹64,10,025.05 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.35 MB
241KW4.pdf
Tender Documents • 1.11 MB
Generalconditions.pdf
Additional Documents • 0.23 MB
Documentstosubmit.pdf
Additional Documents • 0.38 MB
BOQ_983447.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .