| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹24.8 LAdmitted-Finance | ₹24.8 L | L1 | Admitted-Finance |
| 2 | L2₹24.8 LAdmitted-Finance | ₹24.8 L | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | Sree Sreenivasa Contractorss L1 | K SUBRAMANIYAM L2 |
|---|---|---|---|---|---|
| 1.00Strengthening the road from Santhiyur TS road to Santhiyur Colony km 0/0 - 1/240. H/O Santhiyur | |||||
| 2.00 | Clearing Scrub jungle including cutting all trees and other vegetation and depositing them beyond the road as directed by the departmental officers Including all labour charges etc., complete. | 1,116 | Sqm | 6 ₹6,696 | 7 ₹7,812 |
| 3.00 | Picking 5 cm to 10 cm old metalled surface and sectioning Including all labour charges etc., complete. | 1,720 | Sqm | 23 ₹39,560 | 24 ₹41,280 |
| 4.00 | Providing and Laying Gritty Gravel to 150 mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compact | 74.34 | Cum | 340 ₹25,275.60 | 342 ₹25,424.28 |
| 5.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 258 | Cum | 2,430 ₹6.3 L | 2,431.44 ₹6.3 L |
| 6.00 | Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Complete | 2,580 | Sqm | 86.5 ₹2.2 L | 86.55 ₹2.2 L |
| 7.00 | Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Complete | 2,580 | Sqm | 20 ₹51,600 | 20.26 ₹52,270.80 |
| 8.00 | Applying tack coat over BT surface (not treated with primer) using 3Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete | 1,140 | Sqm | 34 ₹38,760 | 34.37 ₹39,181.80 |
| 9.00 | Bituminous Concrete (Table 500-17) : Providing and Laying bituminous concrete of required thickness with central hot mix plant using crushed aggregates of specified grading premixed with bituminous binder (Viscocity Grade 40) at percentage specified by JMF of mix and filler transporting to the hot mix plant to site laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause no 111, 112, 501, 507, and 900 of MORTH vth revision complete in all respects Ratio. | 93 | Cum | 11,657.5 ₹10.8 L | 11,657.5 ₹10.8 L |
| 10.00 | Provision for Name Board charges etc., complete | 1 | Nos | 1,500 ₹1,500 | 1,500 ₹1,500 |
Tender Value
₹25 L
EMD Value
₹25,000
Closing Date
2 Mar 2026, 3:00 pmClosed
BDO(VP)
panamarathupatti
Strengthening the road from Santhiyur TS Road to Santhiyur Colony Km 1/240 at Santhiyur Panchayat Panamarathupatti Block Salem Dt
2026_RDTN_666594_1
5558/2025/T5
Open Tender
Civil Works - Roads
120 days
panamarathupatti
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹25,000
4 Mar 2026
25 Feb 2026
2 Mar 2026
25 Feb 2026
2 Mar 2026
25 Feb 2026
Strengthening the road from Santhiyur TS road to Santhiyur Colony km 0/0 - 1/240. H/O Santhiyur
Clearing Scrub jungle including cutting all trees and other vegetation and depositing them beyond the road as directed by the departmental officers Including all labour charges etc., complete.
Picking 5 cm to 10 cm old metalled surface and sectioning Including all labour charges etc., complete.
Providing and Laying Gritty Gravel to 150 mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compact
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Complete
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Complete
Applying tack coat over BT surface (not treated with primer) using 3Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete
Bituminous Concrete (Table 500-17) : Providing and Laying bituminous concrete of required thickness with central hot mix plant using crushed aggregates of specified grading premixed with bituminous binder (Viscocity Grade 40) at percentage specified by JMF of mix and filler transporting to the hot mix plant to site laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause no 111, 112, 501, 507, and 900 of MORTH vth revision complete in all respects Ratio.
Provision for Name Board charges etc., complete
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.81 MB
BOQ_800749.xls
BOQ • 0.29 MB
TenderDoc.pdf
Tender Documents • 1.27 MB
Download all tender documents and submit your bid