| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹3.5 LAccepted-Finance | ₹3.5 L | 1 | Accepted-Finance Accepted |
| Sl No | Description | Qty | Unit | MATHI CONSTRUCTION L1 |
|---|---|---|---|---|
| 1.00 | Demolition R.C.C.work by Existing foundation manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. | 3 | Cum | 5,700 ₹17,100 Lowest |
| 2.00Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. | ||||
| 2.01 | In cement mortar | 1.6 | Cum | 2,100 ₹3,360 Lowest |
| 3.00Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. | ||||
| 3.01 | For thickness of tiles 10 mm to 25 mm | 14 | Sqm | 75 ₹1,050 Lowest |
| 4.00 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. | 4 | Cum | 280 ₹1,120 Lowest |
| 5.00 | Supplying HILTY, 9HIT-REIO) Anchoring chemical of 580ml capacity tube. | 8 | Nos | 1,600 ₹12,800 Lowest |
| 6.00 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal sizederived from natural sources). | 3.6 | Cum | 12,300 ₹44,280 Lowest |
| 7.00Centering and shuttering including strutting, propping etc. and removal of form for : | ||||
| 7.01 | Lintels, beams, plinth beams, girders, bressumers and cantilevers | 21 | Sqm | 785 ₹16,485 Lowest |
Tender Value
Refer Docs
EMD Value
₹6,496
Closing Date
27 Apr 2026, 6:00 pmClosed
Executive Engineer (C), BSNL Civil Division,Madura
Executive Engineer(C), Civil Division,Level IV Building, CTO Compound,Tallakulam, Madurai.
Demolition of existing Roof Top Tower foundation,Replacement of fallen RTT with new RTT at NBSNL site Achampathu Madurai
2026_BSNL_274770_1
NIT No 01/BSNL/CDMA/2026-27
Open Tender
Civil Works
Item Rate
30 days
MADURAI
Please refer tender document
3 documents required · 3 mandatory
₹590
AO (Cash) O/o PGM, BSNL Madurai
₹6,496
29 Apr 2026
15 Apr 2026
29 Apr 2026
15 Apr 2026
27 Apr 2026
15 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Demolition R.C.C.work by Existing foundation manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. | |||||
| 2Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. | |||||
| 2.01 | In cement mortar | - | Cum | - | - |
| 3Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. | |||||
| 3.01 | For thickness of tiles 10 mm to 25 mm | - | Sqm | - | - |
| 4Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. | |||||
| 5Supplying HILTY, 9HIT-REIO) Anchoring chemical of 580ml capacity tube. | |||||
| 6Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal sizederived from natural sources). | |||||
| 7Centering and shuttering including strutting, propping etc. and removal of form for : | |||||
| 7.01 | Lintels, beams, plinth beams, girders, bressumers and cantilevers | - | Sqm | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
Tendernotice_2.pdf
PDF • 1.48 MB
BOQ_320965.xls
BOQ • 0.29 MB
Corrigendum1.pdf
PDF • 0.19 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].