Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 LAccepted-AOC A 58 DDU NAGAR BEHIND DIGAMBER JAIN MANDIR SUKHLIYA INDORE M P 452010 | INDORE | INDORE | MADHYA PRADESH | 452010 | ₹1.1 L Quoted ₹96,000 | L1 | Accepted-AOC Accepted on L1 basis |
| Sl No | Description | Qty | Unit | INSPECTTA L1 |
|---|---|---|---|---|
| 1.00Safe load testing and Proof load testing of Hooks of all models of cranes working at FWS, Jayant Project. | ||||
| 1.01 | Cost of load testing & proof load testing of hooks of Rhine 90C Crane 9T working at Jayant Project as per scope. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost. | 3 | Nos | 6,000 ₹18,000 |
| 1.02 | Cost of load testing & proof load testing of hooks of 01 no Escort 11T and 01 no Escort 12T crane working at Jayant Project as per scope of work.Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost. | 2 | Nos | 6,000 ₹12,000 |
| 1.03 | Cost of load testing & proof load testing of hooks of Husky crane 620,20T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost. | 1 | Nos | 6,000 ₹6,000 |
| 1.04 | Cost of load testing & proof load testing of hooks of 02 nos. Escort crane RT 30T and 01 no TILRT630C 30T working at Jayant Project as per scope of work.Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost. | 3 | Nos | 6,000 ₹18,000 |
| 1.05 | Cost of load testing & proof load testing of hooks of TIL RT 880 Crane 70T/80T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost. | 2 | Nos | 6,000 ₹12,000 |
| 1.06 | Cost of load testing & proof load testing of hooks of TIL RT9130E 120T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost. | 1 | Nos | 6,000 ₹6,000 |
| 1.07 | Cost of load testing & proof load testing of hooks of EOT Crane 10T/5T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost. | 2 | no | 6,000 ₹12,000 |
| 1.08 | Cost of load testing & proof load testing of hooks of EOT Crane 35T/10T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost. | 2 | Nos | 6,000 ₹12,000 |
| 2.00 | Total impact of GST for the purpose of CTC | 1 | Nos | - |
Updated dates
Tender Value
₹2.1 L
EMD Value
₹2,600
Closing Date
31 Jan 2026, 11:00 amClosed
GM(Excv), Jayant Project
GM office, Jayant project, Singrauli, M.P-486890
Safe load testing and Proof load testing of Hooks of all models of cranes working at FWS, Jayant Project.
2026_NCL_351193_1
JNT/GM(Excv)/E-tender/25-26/53
Open Tender
Excavation Department Work
30 days
Jayant Project
As per NIT
3 documents required · 3 mandatory
₹2,600
21 Mar 2026
14 Jan 2026
2 Feb 2026
14 Jan 2026
31 Jan 2026
15 Jan 2026
14 Jan 2026 - 19 Jan 2026
Cost of load testing & proof load testing of hooks of Rhine 90C Crane 9T working at Jayant Project as per scope. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost.
Cost of load testing & proof load testing of hooks of 01 no Escort 11T and 01 no Escort 12T crane working at Jayant Project as per scope of work.Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost.
Cost of load testing & proof load testing of hooks of Husky crane 620,20T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost.
Cost of load testing & proof load testing of hooks of 02 nos. Escort crane RT 30T and 01 no TILRT630C 30T working at Jayant Project as per scope of work.Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost.
Cost of load testing & proof load testing of hooks of TIL RT 880 Crane 70T/80T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost.
Cost of load testing & proof load testing of hooks of TIL RT9130E 120T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost.
Cost of load testing & proof load testing of hooks of EOT Crane 10T/5T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost.
Cost of load testing & proof load testing of hooks of EOT Crane 35T/10T working at Jayant Project as per scope of work. Cost includes testing charge including manpower ,contractor profit, tools & tackles, to & fro transportation charges and any other cost.
Total impact of GST for the purpose of CTC
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.16 MB
BOQ_363950.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid