| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 CrAccepted-Finance 0 BAGHI NAUGARH NAUGARH CHANDAULI UTTAR PRADESH 232111 | CHANDAULI | UTTAR PRADESH | 232111 | ₹1.6 Cr | L1 | Accepted-Finance LOWEST |
| 2 | L2₹1.6 Cr+₹273.51 (<0.01%)Rejected-Finance MOB BAJDAARIPURA DISTRICT BAHRAICH | BAHRAICH | UTTAR PRADESH | 271801 | ₹1.6 Cr+₹273.51 (<0.01%) | L2 | Rejected-Finance HIGH RATE BIDDER |
| 3 | L3₹1.7 Cr+₹2.7 L (1.67%)Rejected-Finance GRAM DERE RRAJA POST PANAPUR TEHSIL GAUSPUR DISTRICT BARABANKI UTTAR PRADESH | GAUSPUR | BARABANKI | UTTAR PRADESH | ₹1.7 Cr+₹2.7 L (1.67%) | L3 | Rejected-Finance HIGH RATE BIDDER |
| 4 | L4₹1.7 Cr+₹4.5 L (2.72%)Rejected-Finance | ₹1.7 Cr+₹4.5 L (2.72%) | L4 | Rejected-Finance HIGH RATE BIDDER |
| 5 | L5₹1.7 Cr+₹4.5 L (2.77%)Rejected-Finance | ₹1.7 Cr+₹4.5 L (2.77%) | L5 | Rejected-Finance HIGH RATE BIDDER |
| Sl No | Description | Qty | Unit | M/S K.K. TRADERS L4 | Mohammad Abdulla L2 | BHOLENDRA PRATAP SINGH L5 | M/S RADHIKA CONSTRUCTION COMPANY L6 | MAMTA SHARMA CONTRACTOR CO BARABANKI L3 | M/S S K CONSTRUCTION COMPANY L9 | AKANKSHA ASSOCIATES L1 | M/S SUSHIL KUMAR SINGH THEKEDAR L7 | M/S PRATAP NIRMAN SANSTHAN L8 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Earth work in excavation of side drain in all type of soil with proper disposal of earth including all lead & lift, levelling, dressing to profile and manual compaction etc required for proper completion of work. as per direction of Engineer in charge. | 17,947.5 | M3 | 29.99 ₹5,38,245.53 Lowest | 41 ₹7,35,847.5 | 50 ₹8,97,375 | 41 ₹7,35,847.5 | 59.9 ₹10,75,055.25 | 50 ₹8,97,375 | 40 ₹7,17,900 | 40 ₹7,17,900 | 45 ₹8,07,637.5 |
| 2.00 | Earth work in excavation of foundation in all type of soil with back filling and proper disposal of surplus earth including all lead & lift, levelling, dressing and manual compaction etc required for proper completion of work | 6,281 | M3 | 49.99 ₹3,13,987.19 | 50 ₹3,14,050 | 52 ₹3,26,612 | 50 ₹3,14,050 | 99 ₹6,21,819 | 70 ₹4,39,670 | 49 ₹3,07,769 Lowest | 60 ₹3,76,860 | 60 ₹3,76,860 |
| 3.00 | Supplying & laying Geotextile sheet 200 GSM woven multifilament polypropylene yarn on slope with pegs including all cost of material, labour, T&P etc required for proper completion of work | 6,518.93 | M2 | 99.99 ₹6,51,827.81 | 85 ₹5,54,109.05 | 78.6 ₹5,12,387.9 | 90 ₹5,86,703.7 | 99 ₹6,45,374.07 | 100 ₹6,51,893 | 78 ₹5,08,476.54 Lowest | 80 ₹5,21,514.4 | 90 ₹5,86,703.7 |
| 4.00 | Laying C.C 1:2:4 with cement, Hamirpur coarse sand and 4.75mm to 20mm Kabrai stone grit with mixing, laying, curing, ramming, including cost of all material, labour T&P etc required for proper completion of work. | 87.21 | M3 | 8,111.99 ₹7,07,446.65 | 8,000 ₹6,97,680 Lowest | 8,824.2 ₹7,69,558.48 | 9,500 ₹8,28,495 | 8,382 ₹7,30,994.22 | 10,000 ₹8,72,100 | 9,200 ₹8,02,332 | 9,500 ₹8,28,495 | 9,500 ₹8,28,495 |
| 5.00 | Supplying & laying Mirzapur cut stone boulder 25 kg to 60 kg of size approx. 20cm x 20cm x 15cm manually placed and closely packed in pitching including cost of all material, labour T&P etc required for proper completion of work. | 1,889.55 | M3 | 4,149.99 ₹78,41,613.6 | 4,300 ₹81,25,065 | 4,649.15 ₹87,84,801.38 | 4,550 ₹85,97,452.5 | 4,016 ₹75,88,432.8 Lowest | 5,000 ₹94,47,750 | 4,200 ₹79,36,110 | 4,500 ₹85,02,975 | 4,500 ₹85,02,975 |
| 6.00 | Supplying & laying Mirzapur cut stone boulder 25 kg to 60 kg of size approx. 20cm x 20cm x 15cm manually placed & closely packed in 8 SWG G.I. wire crate of size 1.0M x 1.0M x 1.0M, Mesh size 20cm x 20cm double knotted including all cost of material, labour, T&P etc required for proper completion of work including cost of wire crate | 80 | M3 | 5,449.99 ₹4,35,999.2 | 5,200 ₹4,16,000 | 5,525.53 ₹4,42,042.4 | 5,900 ₹4,72,000 | 4,990 ₹3,99,200 | 5,500 ₹4,40,000 | 5,100 ₹4,08,000 | 5,400 ₹4,32,000 | 4,500 ₹3,60,000 Lowest |
| 7.00 | Laying C.C 1:1.5:3 with cement, Hamirpur coarse sand & 4.75 to 20mm Kabrai stone grit with mechanical mixing, vibration, laying, curing including cost of all material, labour, T&P etc required for proper completion of work. | 22.49 | M3 | 9,999.99 ₹2,24,899.78 | 9,200 ₹2,06,908 | 9,297.6 ₹2,09,103.02 | 10,542 ₹2,37,089.58 | 9,090 ₹2,04,434.1 Lowest | 10,200 ₹2,29,398 | 9,800 ₹2,20,402 | 9,500 ₹2,13,655 | 10,500 ₹2,36,145 |
| 8.00 | Centering & Shuttering for C.C work with cost of shuttering including cost of all material, labour, T&P etc required for proper completion of work | 470.5 | M2 | 251.99 ₹1,18,561.29 | 150 ₹70,575 Lowest | 240 ₹1,12,920 | 392 ₹1,84,436 | 350 ₹1,64,675 | 300 ₹1,41,150 | 200 ₹94,100 | 300 ₹1,41,150 | 200 ₹94,100 |
| 9.00 | Making subgrade for boulder pitching work including watering, ramming and preparation of surface including all lead & lift, levelling, dressing etc required for proper completion of work as per direction of Engineer in charge | 6,180.5 | M2 | 17.99 ₹1,11,187.19 | 10 ₹61,805 Lowest | 10 ₹61,805 Lowest | 14 ₹86,527 | 13 ₹80,346.5 | 10 ₹61,805 Lowest | 14 ₹86,527 | 10 ₹61,805 Lowest | 15 ₹92,707.5 |
| 10.00 | First class 150 Brick work in 1:4 C.M. with cement & coarse sand including all cost of material, labour, T&P etc required for proper completion of work | 650.54 | M3 | 6,899.99 ₹44,88,719.49 | 5,975 ₹38,86,976.5 | 6,552.57 ₹42,62,708.89 | 6,170 ₹40,13,831.8 | 4,990 ₹32,46,194.6 Lowest | 5,800 ₹37,73,132 | 5,100 ₹33,17,754 | 6,400 ₹41,63,456 | 7,000 ₹45,53,780 |
Tender Value
₹2.2 Cr
EMD Value
₹4.3 L
Closing Date
3 Aug 2026, 3:00 pmClosed
SUPERINTENDING ENGINEER
IX CIRCLE IRRIGATION WORKS BAHRAICH
Construction of Side drain and protection work on Left bank of Rapti Main canal From km 28.000 to km 29.300 in District Shrawasti.
2026_UPIDC_1167986_4
01/SE-IX/2026-27
Open Tender
Civil Works
Item Rate
180 days
BHINGA, SHRAWASTI
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,555
₹4.3 L
IX CIRCLE IRRIGATION WORKS BAHRAICH
11 Sept 2026
13 Jul 2026
3 Aug 2026
13 Jul 2026
3 Aug 2026
13 Jul 2026
13 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0.0 | Earth work in excavation of side drain in all type of soil with proper disposal of earth including all lead & lift, levelling, dressing to profile and manual compaction etc required for proper completion of work. as per direction of Engineer in charge. | 17,947.5 | M3 | 67.5 | ₹12,11,456.25 |
| 0.0 | Earth work in excavation of foundation in all type of soil with back filling and proper disposal of surplus earth including all lead & lift, levelling, dressing and manual compaction etc required for proper completion of work | 6,281 | M3 | 104 | ₹6,53,224 |
| 0.0 | Supplying & laying Geotextile sheet 200 GSM woven multifilament polypropylene yarn on slope with pegs including all cost of material, labour, T&P etc required for proper completion of work | 6,518.93 | M2 | 131 | ₹8,53,979.83 |
| 0.0 | Laying C.C 1:2:4 with cement, Hamirpur coarse sand and 4.75mm to 20mm Kabrai stone grit with mixing, laying, curing, ramming, including cost of all material, labour T&P etc required for proper completion of work. | 87.21 | M3 | 11,030.26 | ₹9,61,948.97 |
| 0.0 | Supplying & laying Mirzapur cut stone boulder 25 kg to 60 kg of size approx. 20cm x 20cm x 15cm manually placed and closely packed in pitching including cost of all material, labour T&P etc required for proper completion of work. | 1,889.55 | M3 | 5,437.62 | ₹1,02,74,654.87 |
| 0.0 | Supplying & laying Mirzapur cut stone boulder 25 kg to 60 kg of size approx. 20cm x 20cm x 15cm manually placed & closely packed in 8 SWG G.I. wire crate of size 1.0M x 1.0M x 1.0M, Mesh size 20cm x 20cm double knotted including all cost of material, labour, T&P etc required for proper completion of work including cost of wire crate | 80 | M3 | 6,462.62 | ₹5,17,009.6 |
| 0.0 | Laying C.C 1:1.5:3 with cement, Hamirpur coarse sand & 4.75 to 20mm Kabrai stone grit with mechanical mixing, vibration, laying, curing including cost of all material, labour, T&P etc required for proper completion of work. | 22.49 | M3 | 11,622 | ₹2,61,378.78 |
| 0.0 | Centering & Shuttering for C.C work with cost of shuttering including cost of all material, labour, T&P etc required for proper completion of work | 470.5 | M2 | 400 | ₹1,88,200 |
| 0.0 | Making subgrade for boulder pitching work including watering, ramming and preparation of surface including all lead & lift, levelling, dressing etc required for proper completion of work as per direction of Engineer in charge | 6,180.5 | M2 | 20 | ₹1,23,610 |
| 0.0 | First class 150 Brick work in 1:4 C.M. with cement & coarse sand including all cost of material, labour, T&P etc required for proper completion of work | 650.54 | M3 | 7,280.64 | ₹47,36,347.55 |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.94 MB
LOT04.pdf
Tender Documents • 5.28 MB
BOQ_2190584.xls
BOQ • 0.28 MB
BOQ_2190584.xls
PDF • 0.31 MB
DATE.pdf
PDF • 0.26 MB
BOQ04.xls
PDF • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .