Loading…
Loading…
Tender Value
₹19.7 Cr
EMD Value
₹39.3 L
Closing Date
15 Jun 2026, 3:00 pm
General Manager Zone-3 UPPCL Lucknow
Office of the General Manager Zone-3 UPPCL Lucknow
Tourism Development work of Guru Gorakhnath Taposthali at Jayas Distt. Amethi
2026_UPPRC_1156288_1
16/GM-3/UPPCL/2026-27 DATE-30.05.2026
Open Tender
Civil Works - Buildings
360 days
Amethi
As per bid documents
2 documents required · 2 mandatory
₹17,700
₹39.3 L
4 Jun 2026
4 Jun 2026
15 Jun 2026
4 Jun 2026
15 Jun 2026
4 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge.All kinds of soil
0.00 LVL. TO 1.50 MTR. | 7,261.77 | CUM | 128.85 | ₹9,35,679.06 | 1 |
| 2 | 1.50 LVL. TO 3.00 MTR. | 46.16 | CUM | 220.9 | ₹10,196.74 | 2 |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth,sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 2,044.19 | CUM | 142.28 | ₹2,90,847.35 | 3 |
| 4 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. | 226.58 | CUM | 508.51 | ₹1,15,218.2 | 4 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-lll) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 996.84 | CUM | 4,944.96 | ₹49,29,333.93 | 5 |
| 6 | Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 kms. from the site of work and including watering, dressing etc rate to include cost of all materials labour T & P etc required for proper completion of work. | 112.52 | CUM | 1,541.67 | ₹1,73,468.71 | 6 |
| 7 | Construction of drain along with apron. 150X150MM | 91.39 | RM | 794.47 | ₹72,606.61 | 7 |
| 8 | Providing and injecting chemical emulsion for pre constructional antitermite treatment and creating a chemical barrier under and alround the column pits wall trenches basement excavation top surface if plinth filling junction of wall and floor, along the the external perimeter of binding expansion joints, surrounding of pipes and conduits etc, complete.
(plinth area of the building at Ground Floor only shall be measured as per I.S.6313 (PartII 1981) Alderine emulsifiable concentrate or any other approved material such as Heptrachlor or Chlordane will be used. The rate of application of chemical emulsion shall be as follows : (1) Treatment for masonary & foundation 5 liters per sqm. (2) Back fill in immediate contact with foundation 7.5 liters/sqm (3) Treatment of top surface of plinth filling 5 liters/sqm
(4) Treatment junction of wall and the floor 7.5 liters /sqm (5) Treatment of soil along external perimeter of building 7.5 liters/sqm (6) Treatment of soil under apron along external perimter 5 liters/sqm. (As per manufacturer's standard dilution) | 1,945.99 | SQM | 225.07 | ₹4,37,983.97 | 8 |
| 9 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). Lintel
Ground Floor (Plinth band)
Ground Floor (Lintel) | 42.18 | CUM | 8,352.06 | ₹3,52,289.89 | 9 |
| 10 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)Slab | 272.02 | CUM | 8,352.06 | ₹22,71,927.36 | 10 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.78 MB
BOQ_2166392.xls
BOQ • 1.38 MB
BID_DOCcc.pdf
Tender Documents • 14.18 MB
Download all tender documents and submit your bid