Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹25.4 LAdmitted-Fee/PreQual/Technical/Finance | L1 | Admitted-Fee/PreQual/Technical/Finance | ||
| 2 | L2₹29.3 L+₹3.9 L (15.3%)Admitted-Fee/PreQual/Technical/Finance AT BANGALPUR PO BAMARA DIST KENDRAPARA PIN 754153 | BANGALPUR | KENDRAPARA | ODISHA | 754153 | L2 | Admitted-Fee/PreQual/Technical/Finance | ||
| 3 | L3₹30.5 L+₹5.1 L (20.3%)Admitted-Fee/PreQual/Technical/Finance | L3 | Admitted-Fee/PreQual/Technical/Finance | ||
| 4 | L4₹31.7 L+₹6.3 L (24.9%)Admitted-Fee/PreQual/Technical/Finance | L4 | Admitted-Fee/PreQual/Technical/Finance | ||
| 5 | L5₹32.1 L+₹6.7 L (26.5%)Admitted-Fee/PreQual/Technical/Finance | L5 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹40.7 L
EMD Value
₹40,700
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Divisional Officer
RURAL WORKS DIVISION, KENDRAPARA
Nadiaborai to Karilopatana_Road_ Boxcell Culvrert-2X6X3-, Approach and WallAt 3.000 km
2026_CERWI_136007_1
RWD KPD 01 OF 2026-2027
Open Tender
Civil Works - Roads
Percentage
90 days
Kendrapara
2 documents required · 2 mandatory
₹6,000
₹40,700
Yes
5 Oct 2026
17 Jul 2026
28 Jul 2026
17 Jul 2026
27 Jul 2026
17 Jul 2026
17 Jul 2026 - 24 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation of fondation in hard soil within the initial lead & lift including dressing & levelling the bed & depositiong the excavated earth away from the site etc. all complete as per the direction of Engineer in Charge. | 408.46 | Per Cum | 282.88 | ₹1,15,545.16 |
| 2 | Filling sand-Supplying & filling good clean river sand of approved quality including watering to complete saturation & ramming complete with all leads & lifts including cost, conveyance, royalty & taxes of all materials & cost of all labour & T&P required for the work etc. complete as per specification & direction of Engineer in charge. | 39.24 | Per Sqm | 672.13 | ₹26,374.38 |
| 3 | Plain cement concrete P.C.C. Grade M-15 in Sub-structure complete as per drawings and technical specification Clauses 802, 803, 1202 and 1203 of MORD specification for Rural roads and as per the direction of the Engineer-in-Charge. | 154.24 | Per Cum | 5,861.74 | ₹9,04,114.78 |
| 4 | Plain cement concrete P.C.C. Grade M-15 in Sub-structure complete as per drawings and technical specification Clauses 802, 803, 1202 and 1203 of MORD specification for Rural roads and as per the direction of the Engineer-in-Charge. | 63.63 | Per Cum | 6,003.77 | ₹3,82,019.89 |
| 5 | R.C.C work of M-25 grade with 20mm and down grade black hard granite (crusherbroken) stone chips including cost, conveyance, royalty & taxes of all materials & cost of all labour & T&P required for the work etc. complete as per specification & direction of Engineer in charge. Raft | 51.75 | Cum | 7,124.95 | ₹3,68,716.16 |
| 6 | Deck Slab | 51.75 | Cum | 10,087.83 | ₹5,22,045.2 |
| 7 | RIB , Pier Rib, Hunch | 41.18 | Cum | 9,179.73 | ₹3,78,021.28 |
| 8 | Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal size aggregate, true to line and grade, tolerance of vertical railing post not to exceed 1 in 500, centre-to-centre spacing between vertical posts not to exceed 2000 mm as per drawing and technical specifications direction of Engineer in charge. | 27.6 | Rmt | 2,404.14 | ₹66,354.26 |
| 9 | Proving R.C.C M-30 Casting in Wearing Coat including cost canveyance rayality & taxes of all materials cost of all labour T&P etc, complete.technical specifications direction of Engineer in charge. | 7.76 | Cum | 7,155.58 | ₹55,527.3 |
| 10 | Providing HYSD bar reinforcement for R.C.C. work including Straightening, cutting, bending, binding, welding, tying the grills, laying and placing in proper position as per approved design and drawing including cost, conveyance of 18 to 20 gauge binding wire, cost and conveyance of HYSD bars of Fe 500D complete in all respect as as per the specification and direction of the Engineer-in-charge. | 96.86 | Qntl | 9,502.12 | ₹9,20,413.35 |
stage.html
html • 0.04 MB
boq_comp_chart.xlsx
xlsx
cancelled_1.pdf
pdf • 1.61 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_3.pdf
PDF • 0.21 MB
Tendernotice_2.pdf
PDF • 2.65 MB
Tendernotice_1.pdf
PDF • 0.95 MB
BOQ_601784.xls
BOQ • 0.47 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .