| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.7 CrAccepted-AOC 1ST FLOOR FLAT NO A 104 ANANT EMEGINE SOCIETY PURANA BUS STAND KORBA DISTT KORBA C G 495678 | 495678 | ₹4.7 Cr | L1 | Accepted-AOC Duly approved and recommended for award of work. |
| 2 | L2₹5.2 CrRejected-Finance | ₹5.2 Cr | L2 | Rejected-Finance Being L-2 Bidder |
| 3 | L3₹5.5 CrRejected-Finance FLOOR NO 4 FLAT NO 402 ASHOKA RATAN SHANKAR NAGAR RAIPUR CG 492001 | RAIPUR | CHHATTISGARH | 492001 | ₹5.5 Cr | L3 | Rejected-Finance Being L-3 Bidder |
| 4 | Rejected-Technical MISSION HOSPITAL CHOWK KEDARPUR AMBIKAPUR DIST SURGUJA CG 497001 | SURGUJA | CHHATTISGARH | 497001 | - | - | Rejected-Technical Rejected due to non-compliance with the cl. no. 8.4A and cl. no. 9.E.1 of NIT pertaining to work experience eligibility criteria and not responded to shortfall confirmatory documents. |
| 5 | Rejected-Technical | - | - | Rejected-Technical Rejected due to non-compliance with the cl. no. 8.4A and cl. no. 9.E.1 of NIT pertaining to work experience eligibility criteria |
| Sl No | Description | Qty | Unit | Resilient Infratech Pvt. Ltd. L2 | R R GLOBAL ENERGY PVT LTD L3 | AARNA Constructions L1 |
|---|---|---|---|---|---|---|
| 1.00DESIGN AND ENGINEERING COST (for 2X500 KVA, 11/0.440kV Substation) | ||||||
| 1.01 | Design and Engg on PLANT & MACHINERY ( P&M - Electrical) to be supplied by bidder inlcusive of Overhead constuction cost, Contigencices, but excluding GST | 1 | Complete work as per tender document | 5,00,000 ₹5,00,000 | 8,00,000 ₹8,00,000 | 4,00,000 ₹4,00,000 Lowest |
| 1.02 | Design and Engg on Civil & Structural work | 1 | Complete work as per tender document | 1,50,000 ₹1,50,000 Lowest | 4,00,000 ₹4,00,000 | 3,00,000 ₹3,00,000 |
| 2.00CIVIL CONSTRUCTION AND STRUCTURAL WORKS for 2X500 KVA, 11/0.440kV Substation on Turnkey Basis at Ambika OCP, Korba Area inclusive of Insurance,Contingencie but excluding GST | ||||||
| 2.01 | Sub-station Building with Chain Link Fencing and Gate with Security Guard Room | 1 | Lumpsump | 95,00,000 ₹95,00,000 | 88,00,000 ₹88,00,000 Lowest | 92,00,000 ₹92,00,000 |
| 2.02 | Room for DG | 1 | Lumpsump | 2,50,000 ₹2,50,000 Lowest | 2,80,000 ₹2,80,000 | 2,50,000 ₹2,50,000 Lowest |
| 2.03 | Bore well with submersible pump | 1 | Lumpsump | 3,50,000 ₹3,50,000 | 2,80,000 ₹2,80,000 Lowest | 3,50,000 ₹3,50,000 |
| 2.04 | Drain around the Substation | 1 | Lumpsump | 2,50,000 ₹2,50,000 Lowest | 4,80,000 ₹4,80,000 | 2,64,579.84 ₹2,64,579.84 |
| 2.05 | Surface Dressing and Antiweed treatment | 1 | Lumpsump | 50,000 ₹50,000 Lowest | 50,000 ₹50,000 Lowest | 50,000 ₹50,000 Lowest |
| 3.00 | Survey & Soil testing | 1 | Lumpsump | 55,000 ₹55,000 | 50,000 ₹50,000 Lowest | 50,000 ₹50,000 Lowest |
Tender Value
₹6.6 Cr
EMD Value
₹8.3 L
Closing Date
16 Jan 2026, 5:00 pmClosed
GM(CMC)/HOD, SECL
Office of GM (CMC), SECL, CMC Deptt., SECL HQ, Seepat Road, Bilaspur-495006
Construction of 2X500 KVA, 11/0.440 kV Substation including Operation and Maintenance during DLP on Turnkey Basis at Ambika OCP, Korba Area, SECL
2025_SECL_348554_1
SECL/BSP/CMC/KRB/25-26/AMBIKA SS/e-T/625 DTD 03.12.2025
Turnkey
Electrical and Maintenance Works
Item Rate
2190 days
Ambika OCP, Korba Area, SECL
As per NIT
7 documents required · 7 mandatory
₹8.3 L
Office of GM (CMC), SECL
3 Aug 2026
4 Dec 2025
19 Jan 2026
4 Dec 2025
16 Jan 2026
16 Dec 2025
4 Dec 2025 - 9 Jan 2026
12 Dec 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1DESIGN AND ENGINEERING COST (for 2X500 KVA, 11/0.440kV Substation) | |||||
| 1.01 | Design and Engg on PLANT & MACHINERY ( P&M - Electrical) to be supplied by bidder inlcusive of Overhead constuction cost, Contigencices, but excluding GST | 1 | Complete work as per tender document | 10,01,307.36 | ₹10,01,307.36 |
| 1.02 | Design and Engg on Civil & Structural work | 1 | Complete work as per tender document | 5,81,582.45 | ₹5,81,582.45 |
| 2CIVIL CONSTRUCTION AND STRUCTURAL WORKS for 2X500 KVA, 11/0.440kV Substation on Turnkey Basis at Ambika OCP, Korba Area inclusive of Insurance,Contingencie but excluding GST | |||||
| 2.01 | Sub-station Building with Chain Link Fencing and Gate with Security Guard Room | 1 | Lumpsump | 1,46,39,955 | ₹1,46,39,955 |
| 2.02 | Room for DG | 1 | Lumpsump | 4,10,362.38 | ₹4,10,362.38 |
| 2.03 | Bore well with submersible pump | 1 | Lumpsump | 4,66,875 | ₹4,66,875 |
| 2.04 | Drain around the Substation | 1 | Lumpsump | 5,21,214.5 | ₹5,21,214.5 |
| 2.05 | Surface Dressing and Antiweed treatment | 1 | Lumpsump | 52,041 | ₹52,041 |
| 3 | Survey & Soil testing | 1 | Lumpsump | 77,544.33 | ₹77,544.33 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.06 MB
Tendernotice_1.pdf
PDF • 0.56 MB
Tendernotice_2.pdf
PDF • 8.98 MB
Tendernotice_3.pdf
PDF • 1.42 MB
Tendernotice_4.pdf
PDF • 2.21 MB
BOQ_361287.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].