| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.4 LAccepted-Finance | ₹7.4 L | L1 | Accepted-Finance BOQ Rate accepted |
| 2 | L2₹7.9 LAccepted-Finance | ₹7.9 L | L2 | Accepted-Finance BOQ Rate accepted |
| Sl No | Description | Qty | Unit | ASHWATH MARINE INFRA PRIVATE LIMITED | MRP ENTERPRISES |
|---|---|---|---|---|---|
| 1.00 | Forming and raising the existing ash dyke bund using wet ash & mill reject with the ratio of 60:40 and laying to the required shape in layers with compaction including diversion of ash slurry in the ash dyke, collecting the mill reject from TTPS mill reject yard, weighing in department weigh bridge and transporting, mixing with ash, laying as directed by the Engineer at site, with all leads, lift etc., complete [But excluding the cost of mill reject] | 157.5 | M3 | 48,825 ₹57,613.50 | 51,975 ₹61,330.50 |
| 2.00 | Forming and raising the existing bund with approved red gravel in layer of 300mm thick compacting each layer with power roller and consolidation to achieve 95% proctor density, forming the bund with an allowance of 300mm on both side in each layer such that section is to be formed only from the roller compacted portion including trimming, sectioning, sizing to the required line to have firm and compact level embankment including cost of all material, labour, lead, lift, etc., complete and as directed by the Engineer at site. | 855 | M3 | 6,88,275 ₹8.1 L | 7,35,300 ₹8.7 L |
Tender Value
Refer Docs
EMD Value
₹7,900
Closing Date
7 Jan 2026, 2:00 pmClosed
Chief Engineer TTPS Tuticorin
Office of the Superintending Engineer Civil TTPS Tuticorin
Protection arrangements to the existing bund in the East side of Secondary Pond from CH 0m to CH 150m from Main Spillway towards Cross Bund for a length of 150m in Ash Dyke area
2025_EB_632811_1
CE SE C TTPS Spec.No. 347 25 26
Open Tender
Civil Works - Others
90 days
Tuticorin Thermal Power Station
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹7,900
Yes
9 Jan 2026
16 Dec 2025
8 Jan 2026
16 Dec 2025
7 Jan 2026
16 Dec 2025
Forming and raising the existing ash dyke bund using wet ash & mill reject with the ratio of 60:40 and laying to the required shape in layers with compaction including diversion of ash slurry in the ash dyke, collecting the mill reject from TTPS mill reject yard, weighing in department weigh bridge and transporting, mixing with ash, laying as directed by the Engineer at site, with all leads, lift etc., complete [But excluding the cost of mill reject]
Forming and raising the existing bund with approved red gravel in layer of 300mm thick compacting each layer with power roller and consolidation to achieve 95% proctor density, forming the bund with an allowance of 300mm on both side in each layer such that section is to be formed only from the roller compacted portion including trimming, sectioning, sizing to the required line to have firm and compact level embankment including cost of all material, labour, lead, lift, etc., complete and as directed by the Engineer at site.
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.26 MB
BOQ_757094.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid