Tender Value
₹93.8 L
EMD Value
₹1.9 L
Closing Date
29 Oct 2026, 4:00 pm
DC ENGR SHQ HGI ITBP
OFFICE OF THE DIG SHQ HGI
Construction of 07 Nos Log bridge at various location in Kilo 1 Axis of 54 Bn ITBP Ar.P
2026_ITBP_929172_1
NO-1060-67 DTD-06/10/2026
Open Tender
Civil Works - Bridges
Percentage
360 days
Location as per mentioned in tender Doc
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹1.9 L
7 Oct 2026
7 Oct 2026
30 Oct 2026
7 Oct 2026
29 Oct 2026
7 Oct 2026
7 Oct 2026 - 29 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | 1.B/w Milli -Wate Approx 7 km away from last road head Milli ):- Earth work in excavation by manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kind of soil | 0.86 | Cum | 1,116 | ₹964.22 |
| 2.01 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level :1:5:10 (1 Cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) | 0.14 | Cum | 30,132 | ₹4,339.01 |
| 3.01 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate20 mm nominal size) | 1.44 | Cum | 48,079 | ₹69,233.76 |
| 4.01 | Centering and shuttering including strutting. propping etc. and removal of form work for: Foundations, footings, bases for columns | 7.2 | Sqm | 380 | ₹2,736 |
| 5.01 | 40 mm wooden planking,tougued and grooved in flooring, including fixing with iron srews complete with:local wood | 20 | Sqm | 9,735 | ₹1,94,700 |
| 6.01 | Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position : Local wood | 8.22 | Cum | 1,13,921 | ₹9,36,088.86 |
| 7.01 | Providing & supplying of U / L clips with washer, nut and bolts complete for fixing of wooden column. (Non scheduled item). Double U-clip set of 5mm thickness, length 22" and width 2" inner column fixing 4", along with nuts/bolts of dia 1"/1.5" and length 5"-6'' | 8 | Nos | 597 | ₹4,776 |
| 8.01 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level: Thermo-Mechanically Treated bars | 135.65 | KG | 188 | ₹25,501.82 |
| 9.01 | 2. B/w Milli -Wate Aprrox 14 km away from last road head Milli :- Earth work in excavation by manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kind of soil | 0.86 | Cum | 1,116 | ₹964.22 |
| 10.01 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level :1:5:10 (1 Cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) | 0.14 | Cum | 33,463 | ₹4,818.67 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.37 MB
tenderdockilo1o7Nos.pdf
Tender Documents • 2.57 MB
BOQ_976433.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .