Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | Ist₹4.6 LAccepted-AOC AASHIYANA SECTOR N 304 KILA CHAURAHA KANPUR ROAD AASHIYANA LUCKNOW UTTAR PRADESH 226012 | LUCKNOW | UTTAR PRADESH | 226012 | Ist | Accepted-AOC L1 | |
| 2 | 2nd₹5.4 LRejected-AOC 01 KATYANI CONSTRUCTION COMPANY H NO 1 SHOP NO 1 RATAN LAL NAGAR KANPUR NAGAR UTTAR PRADESH 208022 | KANPUR NAGAR | UTTAR PRADESH | 208022 | 2nd | Rejected-AOC L2 | |
| 3 | 3rd₹5.8 LRejected-AOC | 3rd | Rejected-AOC L3 |
Tender Value
₹7.8 L
EMD Value
₹8,000
Closing Date
19 May 2023, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Superintending Engineer
Electricity Transmission Circle-I, U.P. Power Transmission Corporation Ltd. 57- George Town, Prayagraj
31-ETC-I(A)/ 2023-2024
2023_UPTCL_800191_1
31-ETC-I(A)/ 2023-2024
Open Tender
Electrical Works
Item Rate
60 days
Fatehpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
SE,ETC,PRAYAGRAJ
₹8,000
9 Aug 2023
4 May 2023
20 May 2023
4 May 2023
19 May 2023
4 May 2023
Amount
The following work to be carried out for attending breakdown work for replacement of damaged 63MVA T/F-I with new 63MVA T/F along with its shifting, Erection & Commissioning at 220KV S/S Fatehpur under ETD-Fatehpur
Complete dismantling the accessories of damaged 63MVA, 132/33KV M/s TAL make power transformer (ESD-482) No-2 at 220KV substation Fatehpur, after opening of jumpers, removal of earthing and opening of cable connection , draining out the transformer oil up to required level in 209 liters capacity oil drums/tanker, removal of all radiators, conservator tank , oil pipe lines, all bushings, turrets , fan motors, marshaling box , etc., blanking the radiators, oil pipe lines, conservator tank turrets etc. with proper gaskets alongwith nuts and bolts to complete the job satisfactorily including proper stacking. Blanking plates, nuts and bolts and gaskets shall be provided by the department. All other T&P etc. shall be arranged by the contractor at his own cost.
Shifting of main tank of new 63MVA, 132/33KV power transformer from stacking place to loading point, turning of tank if required, including all T&P, men and all other works required to complete the job satisfactorly at 220KV Substation Fatehpur, under ETD, Fatehpur
Upto 20 meter
additional shifting of T/F ( 01 job for every 5 meter)
Safe handling &Shifting of all accessories of damaged 63MVA, 132/33KV M/s TAL make power transformer (ESD-482) such as radiators, conservator tank, bushings, cooling fans, motor drive mechanism of RTCC panel, oil pipe line etc. from site to stored place s/s Fatehpur including other associated works also if required for completion of job satisfactorily.
Shifting of main tank of new 63MVA, 132/33KV power transformer from stacking place to loading point, turning of tank if required, including all T&P, men and all other works required to complete the job satisfactorly at 220KV Substation Fatehpur, under ETD, Fatehpur
Upto 20 meter
additional shifting of T/F ( 01 job for every 5 meter)
Complete erection of 63MVA, 132/33KV power transformer by erection of its radiators, conservator tank, all bushings, their turrets connecting oil pipe lines, cooling fans, motor drive mechanism of tap changer, oil pumps and associated oil pipe lines etc. to complete the job satisfactorily including first filling of oil and topping up of transformer oil ( Not circulation )in tank, radiators, oil pipe lines, conservator tank etc. and attending the oil leakage, if any, and all other associated works for satisfactory completion of work at 220KV S/S Fatehpur. Contractor shall provide all assistance in getting the transformer successfully commissioned by providing qualified manpower till commissioning, including the cost of all men, T&P, and associated arrangements.
Centrifuging of complete transformer oil of New 63MVA, 132/33KV e power transformer in transformer tank or oil tanker by connecting centrifuging pipes, circulating the transformer oil through centrifuging machine, to be provided by the contractor and taking the BDV values of the oil periodically till the required value of the oil is achieved as per direction of supervising Engineer at 220KV substation Fatehpur, Fatehpur. All T&P, labor, centrifuging machine& other associated arrangements shall be provided by the contractor at his own cost.
Removal of RTCC panel /C&R of Damaged 63MVA, 132/33KV M/s T&R make power transformer (ESD-482) No.1 by opening cable connections and replacement of new RTCC panel of 63MVA , 132/33Kv Power transformer in control room at 220KV S/S Fatehpur, including its shifting of materail from store and vice versa, fixing , laying of control cable if required as per site and connections and other associated works also if required till commissioning of RTCC panel/C&R panel
Dismantling of 132 KV LA, cutting of earthing, opening of jumpers structures etc of 63MVA T/F-2.and re-erection of 132 KV LA, complete earthing and jumpering for new erected 63MVA T/F at 220KV substation Fatehpur.
Testing of centrifuge T/F oil (DGA, ppm, BDV)of new 63 MVA T/F at 220 KV S/S Fatehpur, from government approve laboratory after charging of transformer on load (preferbarly after 15 days)
Supply of 75x10sqmm MS flat approved by department for double earthing connection from HV &LV side of (2x160+2x40)MVA T/F at 220KV S/S Malwan.
Supply of 03meter length MS round bar of 40mm diameter electrode to be procured for strengthening of earthing system for protection of 2x63MVA T/F T/F installed at 220KV S/S Fatehpur.
Earthing of main tank of 63MVA, 132/33KV power transformer by using M.S.Flat of size 75x10mm, its jointing with already laid earth mat/deltas. Preparing neutral bushing support, excavation of trenches for earthing work , its back filling etc. M.S Flat will be provided by contractor at his own cost.
Doublle delta earthing from HV&LV neutral point of 63MVA T/F . the job includesformation of delta for HV&LV of T/F neutrals by fabrication of 3 Meter long Electrode with 40 mm / 36 dia M.S. Rod having 150 mm long conical shape and then its piercing vertically in the ground with top 500 mm below ground level, its welding with 75 x 10 mm size M.S. Flat for making of Shielding Mesh for HV/LV neutral and finally, connecting the Shielding with Main Earthmat at 2 Places, with due digging of Earth / trench, its back filling and painting etc. with all other associated works for satisfactory completion of the job as per technical specificatio
Erection of 36KV VCB (M/s Stel make) as per instruction manual at LV side of 63MVA T/F including shifting from store to erection site with all associated works. This work also include dismantaling damage VCB and shifting upto store.
Erection of 36KV CT for 63MVA T/F as per instruction manual at LV side of 63MVA T/F including shifting from store to erection site with all associated works. This work also include dismantaling damage CT and shifting upto store.
Earthing of all equipment’s and structure by using 75x10 sqmm MS flat below 800mm from ground level and connecting it with existing earthmat includes. Back filling of excavated earth, its leveling and proper ramming and all associated works including the cost of labor and T&P required to complete the job.
Erection of 132KV control& relay panel (conventional type) for 132kv solar bay including shifting from store to erection site and proper earthing of panel and all associated work to complete the job satisfactorily. This work also include dismantaling of old & damaged C&R panel at control room and shift to S/S store up to completion of all minor work at site.(cable gland & ferul will be provided by contractor om their own cast).Testing & commisioning of C&R panel including it' s configuration should be also done if required.
Laying and termination of following size of unarmored control cable from control room to equipment cable rack (CB,CT,C&R Panel etc) via cable trenches and fixing of it with the help of 25x3mm aluminium strip and 6mm dia GI nut and bolts on cable rack up to termination point by cable tray including tag wielding on equipments as per AE/JE direction and all associated works to complete the job satisfactorily
6Cx2.5 sqmm.
4Cx2.5 sqmm.
Carriage of M/s Siemens make transformer C&R panel from 132KV S/S Khaga to 220/132KV S/S Fatehpur through private carrier. . This work are including shifting,packing & loading on private carrier at 132KV S/S Khaga through hydaulic crane along with unloading and shifting at 220KV S/S Fatehpur. (Approx distance-135Km)
Carriage of 36KV, 1250Amp CT suitable for 63 MVA T/F from 220KV S/S Prayagraj cant under ETD-II Prayagraj to 220/132KV S/S Fatehpur through private carrier. . This work are including shifting,packing & loading of CT on private carrier at 132KV S/S Khaga through man power along with unloading and shifting at 220KV S/S Fatehpur.(approx distance-55Km)
Katyani Construction Co.
HARE KRISHNA ENERGY PROJECTS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .