| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹23.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹29.4 L+₹5.0 L (20.7%)Rejected-Finance | L2 | Rejected-Finance Other than L1 | |
| 3 | L3₹29.7 L+₹5.4 L (22.1%)Rejected-Finance | L3 | Rejected-Finance Other than L1 | |
| 4 | L4₹32.2 L+₹7.9 L (32.4%)Rejected-Finance | L4 | Rejected-Finance Other than L1 | |
| 5 | L5₹32.6 L+₹8.3 L (34.0%)Rejected-Finance GROUND FLOOR TRACTOR MARKET KAITHAL ROAD ASSANDH KARNAL HARYANA 132039 | KARNAL | HARYANA | 132039 | L5 | Rejected-Finance Other than L1 |
| Sl No | Description | Qty | Unit | M/s Luxmi Constructions L6 | M/s Vee Kay Associates L8 | SARJIT SINGH AND CO. L3 | M/s BALDEV SINGH L4 | yogesh kumar contractor L9 | STELLAR PROJECTS L7 | GARG INFRA PROJECTS L2 | RAKESH KUMAR GARG & CO. L1 | SWARN SINGH AND CO. L5 | REYANSH GARG AND COMPANY L10 | GUPTA AND ENGINEERS L11 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00Cleaning of sewage line blockage by roding from manhole to manhole. Manhole to cleaning eye including that from first manhole to cleaning eye of down take pipe and removing all debris, sludge and solid material from sewage line and removal from site and well flushing with water after cleaning vertical/ horizontal pipe of following dia of pipes at any depth, complete all as specified and directed by Engineer in Charge. | ||||||||||||||
| 2.00 | (a) 200 mm internal dia | 120 | RUNNING METRE | 27 ₹3,240 | 100 ₹12,000 | 70 ₹8,400 | 75 ₹9,000 | 30 ₹3,600 | 50 ₹6,000 | 18 ₹2,160 Lowest | 30 ₹3,600 | 80 ₹9,600 | 100 ₹12,000 | 200 ₹24,000 |
| 3.00 | (b) 150 mm internal dia | 300 | RUNNING METRE | 27 ₹8,100 | 100 ₹30,000 | 65 ₹19,500 | 70 ₹21,000 | 35 ₹10,500 | 50 ₹15,000 | 18 ₹5,400 Lowest | 30 ₹9,000 | 70 ₹21,000 | 200 ₹60,000 | 25 ₹7,500 |
| 4.00 | (c) 100 mm internal dia | 350 | RUNNING METRE | 27 ₹9,450 | 100 ₹35,000 | 35 ₹12,250 | 37 ₹12,950 | 40 ₹14,000 | 50 ₹17,500 | 18 ₹6,300 Lowest | 30 ₹10,500 | 60 ₹21,000 | 100 ₹35,000 | 36 ₹12,600 |
| 5.00 | Cleaning of gully traps incl removal of blockage by rodding from gully trap to man hole and gully trap to cleaning eye of down take pipe and removing all debris sludge and solid material from waste pipe line and from the gully trap and removal from site and flushing with water after cleaning vertical pipe and spinking of bleaching powder, complete all as specified and directed by Engineer in Charge. | 150 | EACH | 162 ₹24,300 | 2,000 ₹3,00,000 | 160 ₹24,000 | 170 ₹25,500 | 200 ₹30,000 | 300 ₹45,000 | 100 ₹15,000 | 50 ₹7,500 | 90 ₹13,500 | 10 ₹1,500 Lowest | 20 ₹3,000 |
| 6.00 | Cleaning of manhole chamber of any shape/ size depth not exceeding 0.6 Mtr by removing sludge/ mud, silt, liquid etc (in foul condition to outside MD land premises) and spreading the bleaching powder to avoid the fly nuisance with all prescuation etc, complete all as specified and directed by Engineer in Charge. | 120 | EACH | 162 ₹19,440 | 2,000 ₹2,40,000 | 260 ₹31,200 | 300 ₹36,000 | 250 ₹30,000 | 350 ₹42,000 | 100 ₹12,000 | 50 ₹6,000 Lowest | 90 ₹10,800 | 200 ₹24,000 | 220 ₹26,400 |
| 7.00 | Cleaning of manhole chamber of any shape/size depth exceeding 0.6 Mtr but n exc 1.5Mtr by removing sludge/ mud, silt, liquid etc (in foul condition to outside MD land premises including testing of manholes by filling with water), complete all as specified and directed by Engineer in Charge. | 50 | EACH | 198 ₹9,900 | 2,000 ₹1,00,000 | 260 ₹13,000 | 300 ₹15,000 | 300 ₹15,000 | 350 ₹17,500 | 90 ₹4,500 | 50 ₹2,500 Lowest | 100 ₹5,000 | 200 ₹10,000 | 200 ₹10,000 |
| 8.00Note for ser item No 1 to 7:- (i) The rates quoted in the above item include the cost of T&P such as rods, bamboos, gumshoes, shovels, and hand gloves, etc, complete all as specified and directed by Engineer in Charge. (ii) The complaint has to be rectified within 24 hours as given in the complaint slip; failing which, a penalty of ₹250 per complaint per day will be imposed. (iii) Two labourers/sweepers report to the AGE BR-II office every working day at 9:30 AM and collect complaint slips for the tech area. They should complete all complaints on the same day and hand over the completed complaint slips to the concerned JE at 4:30 PM. | ||||||||||||||
| 9.00 | Taking out liquid/ solid content sludge etc from sump, septic tank, manhole and soak well either manually or by pumping cleaning thoroughly including disposal of liquid/solid content out side defence area, complete all as specified and directed by Engineer in Charge. | 35 | CUBIC METRE | 495 ₹17,325 | 1,000 ₹35,000 | 250 ₹8,750 | 300 ₹10,500 | 550 ₹19,250 | 600 ₹21,000 | 60 ₹2,100 | 50 ₹1,750 Lowest | 300 ₹10,500 | 500 ₹17,500 | 500 ₹17,500 |
| 10.00 | Demolition of RCC man hole covers and similar works etc, complete all as specified and directed by Engineer in Charge. | 5 | CUBIC METRE | 270 ₹1,350 | 700 ₹3,500 | 1,600 ₹8,000 | 1,700 ₹8,500 | 400 ₹2,000 | 300 ₹1,500 | 300 ₹1,500 | 200 ₹1,000 Lowest | 500 ₹2,500 | 200 ₹1,000 Lowest | 200 ₹1,000 Lowest |
Tender Value
Refer Docs
EMD Value
₹70,000
Closing Date
11 Jul 2025, 6:00 pmClosed
GE (AF) BHISIANA
GE (AF) BHISIANA PIN - 151201
PERIODICAL SERVICES TO CERTAIN OTM ACCN NORTH AND SOUTH SIDE OF RUNWAY AND REPAIR AND CLEANING OF SEWAGE LINES MAN HOLES INCLUDING DRAIN IN TECH AREA AT AF STN BHISIANA
2025_MES_715515_1
GE/BHI/T-21/2025-26
Open Tender
Civil Works
Item Rate
273 days
GE (AF) BHISIANA
Please refer Tender documents.
10 documents required · 10 mandatory
₹500
GE (AF) BHISIANA
₹70,000
Yes
11 Aug 2025
19 Jun 2025
14 Jul 2025
19 Jun 2025
11 Jul 2025
4 Jul 2025
19 Jun 2025 - 27 Jun 2025
stage.html
html • 0.07 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .