Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.7 LAccepted-AOC | L1 | Accepted-AOC Found 1st Lowest | |
| 2 | L2₹2.7 L+₹43,385.94 (18.9%)Rejected-AOC | L2 | Rejected-AOC Found 2nd Higher | |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
Refer Docs
EMD Value
₹2,000
Closing Date
8 Aug 2022, 1:00 pmClosed
SUPERINTENDING ENGINEER, EDC, BANDA
CHILLA ROAD, INDIRA NAGAR, BANDA
Erection of 11 KV Lines and Sub-Stations for electrification work of primary and upper primary schools at various places/villages under full deposit scheme under EDD, Banda
2022_DVVNL_701334_5
EDCBNDA-13/2022-23
Open Tender
Electrical Works
Item Rate
180 days
BANDA
AS PER ANNEXURED
2 documents required · 2 mandatory
₹1,180
DVVNL
₹2,000
O/O SE, EDC, BANDA
29 Mar 2023
25 Jul 2022
8 Aug 2022
25 Jul 2022
8 Aug 2022
25 Jul 2022
6 Aug 2022
The work of ERECTION OF 11 KV HT LINES & 10 KVA Sub-Stations on 8.5 Mtr. PCC Poles with ACSR Weasel/ABC/PVC Conductors for giving connections to various PC/UPC as ANWAN, BAGHAILA, MIRJAPUR, INGUWARI, KACHHAR, BAIRAF (MARKA), KARHULI, PINDARAN (KANYA PATHASHALA), GAUTAMPUR, KAJITOLA (NAVEEN), BAHOLLA PURWA (NAVEEN), BAMHRAULA, PARAS, KORARI, BAIRAF, ARMAR (HARIJAN BASTI) IN BLOCK BABERUetc. under FULL DEPOSIT SCHEME YEAR 2021-22 for EDSD, BABERU (BANDA) under EDD, BANDA, including carriage of required material viz. poles, T/Fs & other line materials from E.S.C., BANDA to work site, alongwith its loading, unloading & dragging at the respective ends, details of the work as given below :-
Safe cartage of 8.5 Mtr. long PCC poles.
Safe cartage of line material viz. conductor, cable, GI earth wire, cross arm, angle, channel, insulator, clamps and other line material.
Erection of single support on 8.5 Mtr. PCC poles, including complete H.T./L.T. fittings as per direction of Engineer incharge/RESSPO manual, as per actual site requirement & direction of enginner incharge.
Concreting/grouting of supports as single/double poles with cement, sand and brick ballast/stone ballast in ratio 1:4:8 (0.285 Cu. Mtr. each), including the cost of arrangement of cement, sand, brick ballast/stone ballast, stone pad etc. as per actual site requirement & direction of enginner incharge.
Erection/Installation of 10 KVA Capacity Transformers on the newly erected single/double pole structure in proper alignment and as per direction of supervising engineer/RESSPO manual, along with carriage, loading & unloading.
Erection and grouting of stay set including the work of nozelling & binding etc. as per RESSPO manual and also including the cost of all grouting material.
Fixing of earthing rod with fitting of all accessories as per RESSPO manual.
Laying, sagging, stringing, binding and jumpering of new ACSR Weasel Conductor on the erected poles as per direction of supervising engineer/RESSPO manual.
Laying, stringing, binding and termination etc. of PVC Cable 4x35 mm2 on the newly erected D/P as per direction of supervising engineer/RESSPO manual.
Laying, stringing, binding and sagging etc. of ABC cable 3x50+1x35+1x16 mm2 on the newly erected poles as per direction of supervising engineer/RESSPO manual.
Fixing of MS T-Off Channel with fitting of all accessories as per RESSPO manual.
Fixing & erection of 11 KV distribution box on single pole as ABC Cable with fitting of all accessories as per RESSPO manual.
M/s. SHIV SHAKTI INTERPRISES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .