bdo
bdo Madurai east
Implementation of SFC(DP) - 1Nos of Work in Madurai East Block in Madurai District for the Year 2023-2024 Package No 1
2024_RDTN_425045_1
Madurai East (SFC-2023-2024) Construction of Dining hall at Community hall in Karupaiyurani Pt
Open Tender
Civil Works
Item Rate
madurai
refer tender document
2 documents required · 2 mandatory
₹0
₹20,000
Yes
28 Feb 2024
14 Feb 2024
23 Feb 2024
14 Feb 2024
23 Feb 2024
14 Feb 2024
Amount
Earth work excavation in all soils such as red earth ,hard stiff clay soil, stiff black cotton soil, hard redearth,shales, murrams, gravel,hard rock not requiring blasting ete complete.,SS 20 B
Supplying and filling in foundation, basement, etc with filling M.Sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers.
Cement concrete 1:4:8 mix usin 40 mm HBGS metal inculding cost and coveyance of all materials to site including labour for mixing , laying,curing etc complete.,
Supplying and filling well gravel including all charges
Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. (Contractor has to make his own arrangements for the supply of steel and binding wire)
Supplying and erection centering for sides and soffits inculding necessary supports and structing for plain surfaces such as RCC Slab,Lintel,Beam coloum,sunshade etc complete.,
R.Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three M.Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers
Brick work using country bricks of size 83/4"x41/4"x23/4" in cement mortar 1:5 (One cement and five M.Sand) including curing neat finishing, etc., complete complying with standard specifiction.
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Supplying and Doors and window
Door 1.50x 2.10m
window 1.50x1.20m
jolly 0.90x0.60m
Special ceiling plastering and finishing the exposed surface of all RCC items of work such as slabs, beams, sunshades, facia, canopy slab, staircase waist slab, landing slab etc., with Cement Mortar 1:3 (One Cement and Three M.Sand) 10mm thick including hacking the surfaces, providing cement mortar nosing, beading for sunshades, staircases, steps, landing slabs and curing, etc., in all floors complying with standard specification and as directed by the departmental officers
Paving the floor with kota stone slab of size 600 x 600 of 18 / 20mm (un-polished) in all floors laid in of cement mortor 1:3 (one cement three M.Sand), 20mm thick and pointed with colour cement neatly including polishing with polishing stone and oxalic acid etc., so as to perfectly smooth and glossy and including hire charges for polishing machine and power consumption charges etc. The kota stone slabs and other materials to be used shall be got approved by the Executive Engineer concerned before use on work, etc., complete as per standard speicification.
Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification.
Supply and fixing of PUF roof panels made up of minimum 0.5mm thick PPGI corrugated Sheet at the top and a plain sheet at the bottom with a layer of rigid CFC free polyurethane foam (PUF) of density 40kg + 2 Kg/cum as insulation in between .The polyurethane foam shall confirm to latest IS 12436. The minimum thickness of PU foam layer shall be 29mm for having 30mm (min) thick PUF panel. The PPGI Sheets shall be of minimum 240 MPA Steel Grade & shall have a Zinc coating of minimum 120 GSM as per IS 277/1992, 5-7 microns of epoxy primer on both sides of the sheet & polyester top coat of 18-20 microns on one side / outer side. The PPGI Sheets / PUF Panels shall have a protective guard film of minimum 20-25 microns to avoid scratches to finished panel during transportation. Providing ridges or hips ,encasing the ends of Panel with plain G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers etc complete excluding the cost of trusses, purlins and inclusive of cutting to size and shape wherever required.
Supplying and fixing G.I 'L' angle of size 100x100x6mm including cutting the angle to the required length drilling holes wherever necessary for fixing the pipe purlins, rafters and fixing the post etc., complete.
Supplying and fixing colour galvalume sheet roof of 0.47mm thickand steel tubular box section of 100x50x3mm of 1meter interval including priming coat fixing in position with all necessary accessories complete complying with standard specification and as directed by the departmental officers.
Provision for Name Board charges
Provision for Photo charges
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
M SAHADEVAN
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .