| # | Company | Status |
|---|---|---|
| 1 | Accepted-Technical | Accepted-Technical ac |
| 2 | Accepted-Technical | Accepted-Technical ac |
| 3 | Accepted-Technical | Accepted-Technical ac |
| 4 | Not Admitted-Fee/PreQual/Technical | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 5 | Not Admitted-Fee/PreQual/Technical | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹22.9 L
Closing Date
17 Jul 2026, 6:00 pmClosed
DWCOZPMI SOLAPUR
ZP SOLAPUR
Name of Work Special Repairs To Percolation Tank At Chopadi (Balasaheb Babar) Taluka Sangola Dist Solapur
2026_SOLAP_1316461_1
DWCOMIZP/27/2025-26
Open Tender
Civil Works
Percentage
90 days
Name of Work Special Repairs To Percolation Tank
Please refer Tender documents.
5 documents required · 5 mandatory
₹1,000
Exempted
21 Aug 2026
10 Jul 2026
20 Jul 2026
10 Jul 2026
17 Jul 2026
10 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Item No. 1 : Cleaning grass and removal of rubbish , including all lead and depositing outside the periphery of the area as directed, including 1 % Cess for labour welfare etc. complete | 5,904 | Sq m | 4.2 | ₹24,796.8 |
| 2 | Item No. 2 : Dismentalling dry rubble stone pitching including stacking them neatly including all lead & lift , including 1 % Cess for labour welfare etc. complete | 4,192 | Sq m | 37.75 | ₹1,58,248 |
| 3 | Item No.3 : Stripping Up to 10 cm depth in all kind of soil, Soft Murum hard murum, with all lead & Lift and depositing as directed by Engineer in charge including 1 % Cess for labour welfare etc. complete | 461 | Cum | 38.15 | ₹17,587.15 |
| 4 | Item No.4 : Excavation in all kinds of Soils & Soft murum including boulders up to 0.6 m diameter (0.113cum) for COT / WW Bar & Flank Wall / Tail & Approach Channel and placing the excavated stuff neatly in dump area or for formation of service road / embankment as directed including cost of all materials, machinery, labour, dressing bed and sides to required level and profile with all lead and lift. including 1 % Cess for labour welfare etc. complete . | 527 | Cum | 38.15 | ₹20,105.05 |
| 5 | Item No.5 : Excavation in Hard Murum including boulders up to 0.6 m diameter (0.113 cum) for COT / WW Bar & Flank Wall / Tail & Approach Channel and placing the excavated stuff neatly in dump area or for formation of service road / embankment as directed including cost of all materials, machinery, labour, dressing bed and sides to required level and profile with all lead and lift. including 1 % Cess for labour welfare etc. complete . | 527 | Cum | 49.35 | ₹26,007.45 |
| 6 | Item No.6 : Excavation in Soft Rock without blasting including boulders up to 0.6 m diameter (0.113 cum) for COT / WW Bar & Flank Wall / Tail & Approach Channel and placing the excavated stuff neatly in dump area or for formation of service road / embankment as directed including cost of all materials, machinery, labour, dressing bed and sides to required level and profile with all lead and lift. including 1 % Cess for labour welfare etc. complete . | 1,260 | Cum | 64.2 | ₹80,892 |
| 9Item No.9 : Providing cut off trench filling using selected impervious soil from approved borrow areas ( Government acquired land ) including cost of all materials, machinery, labour, all other operations such as collection of soil, spreading soil in layer of specified thickness, sorting out, breaking clods, leveling, sectioning edges / sides, watering, compacting each layer to density control of not less than 95 percent or as stipulated using vibratory compacter including cost of water with all lead and lift excluding royalty charges including 1 % Cess for labour welfare etc. complete . | |||||
| 9.01 | A ) With Borrow Material From Submergence | 2,314 | Cum | 166.5 | ₹3,85,281 |
| 11Item No.11 : Providing hearting embankment using selected impervious soil from approved borrow areas ( Government acquired land ) in layers including cost of all materials, machinery, labour, all other operations such as collection of soil, spreading soil in layer of specified thickness, sorting out, breaking clods, leveling, sectioning edges / sides, watering, compacting each layer to density control of not less than 95 percent or as stipulated using vibratory compactor including cost of water with all lead and lift excluding royalty charges including 1 % Cess for labour welfare etc. complete . | |||||
| 11.01 | A ) With Borrow Material From Submergence | - | - | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.65 MB
Tendernotice_2.pdf
PDF • 0.81 MB
BOQ_2257159.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .