Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹24.8 LAccepted-AOC | L1 | Accepted-AOC being L1 | |
| 2 | L2₹26.6 L+₹1.8 L (7.40%)Rejected-Finance | L2 | Rejected-Finance Being L2 | |
| 3 | Rejected-Technical | - | Rejected-Technical non responsive | |
| 4 | Rejected-Technical | - | Rejected-Technical Non Reponsive |
Tender Value
Refer Docs
EMD Value
₹60,320
Closing Date
26 Mar 2021, 10:30 amClosed
Executive Engineer, NH Division, HPPWD Solan
Executive Engineer, NH Division, HPPWD Solan
Construction of PCC retaining wall in gabion structure at RD 144/583 to 144/601 near old barrier Shimla against NHAI deposit
2021_PWD_45733_1
7366-95
Open Tender
Civil Works
Item Rate
180 days
Shimla
As per tender document
13 documents required · 13 mandatory
₹5,000
Executive Engineer, NH Division, HPPWD Solan
₹60,320
7 Aug 2023
18 Mar 2021
26 Mar 2021
18 Mar 2021
26 Mar 2021
18 Mar 2021
Amount
Cutting in earth work in all heights depths and trimming bottom, sides slopes in accordance with requirement of lines, grades and cross section in all kind of soil such as Pick work, Jumper work Soft and hard rock including chiseling wedging out of rock where blasting is prohibited and saturated soil and their intermediate classification of soil and stacking the surplus materials and disposed off the surplus excavated earth up to all leads and lifts by tippers / dumpers to the identified dumping place at Muncipal Committee on Tara Devi Air port road as in MC Shimla Limits or to the private dumping site out side MC Shimla area to be arranged by contractor and at his risk and cost as per technical specification clause 302.3.5 by mechanical means as per the direction of the Engineer-in-Charge. Any loss or damage of Govt. or private property during the cutting/ excavation operation shall have to be made good by the contractor .
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. M-15 as per MoRT&H Specification Clause 1500, 1700 and 2100 as per fifth revision including all lead lift and carriage of material by all mode of transportation to the entire satisfaction and direction of the Engineer-In Charge.
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. M-20 as per MoRT&H Specification Clause 1500, 1700 and 2100 as per fifth revision including all lead lift and carriage of material by all mode of transportation to the entire satisfaction and direction of the Engineer-In Charge.
Providing & making Gabion Structures with Mechanically woven double Twisted Hexagonal shaped Wire mesh Gabion Boxex as per IS 16014:2012, MoRT&H Clause 2500, of required size Mesh Type 10x12 (D=100mmm with tolerance of ± 2% ) Zinc +PVC coated, (MACCAFERRI or equivalent)Mesh wire diameter 2.7/3.7 mm,mechanicaly edged/salvaged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist , trying with lacing wire of diameter 2.2/3.2mm (ID/OD), supplied @ 3% by weight of Gabion boxex, filled with boulders with least dimension of 200mm, and cut stones in valley side front faces 15*15*18(cm) from approved Quarry as per MoRT&H specification clause 2503.3 (Latest revision) including all leads and lifts with all mode of transport and as per the direction of Engineer-in-charge
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2 and MORT&H specification clause 305 (latest revision) including all leads and lifts with all mode of transport and as per the direction of Engineer-in-charge.
Dismantling of existing structures like Prestressed / Reinforced cement concrete grade M-20 & above including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of all leads as per MoRT&H specification caluse 202 (Latest revision) including all leads and lifts with all mode of transport and as per the direction of Engineer-in-charge
Dismantling of existing structures like Dismantling Brick / Tile work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres as per MoRT&H specification caluse 202 (Latest revision) including all leads and lifts with all mode of transport and as per the direction of Engineer-in-charge
Devi Prakash Sharma
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .