Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹16.8 LAdmitted-Finance H NO 36 F SIMOLDA WADA REVORA BARDEZ GOA | SOUTH GOA | GOA | 403712 | -20.00% | ₹16.8 L | L1 | Admitted-Finance |
| 2 | L1₹16.8 LAdmitted-Finance H NO 198 A NAIK WADDO VERLA MAPUSA NORTH GOA | -20.00% | ₹16.8 L | L1 | Admitted-Finance |
Tender Value
₹21.0 L
EMD Value
₹41,911
Closing Date
6 Apr 2026, 3:00 pmClosed
EE XIII(R), PWD MAPUSA GOA
EE XIII(R), PWD MAPUSA GOA
Construction of collapsed retaining wall for a length of 50m for ground of St. Britto School in Mapusa Constituency of Bardez Taluka.
2026_PWD_28474_1
6/4/PWD-WD-XIII (R)/ASW/45/2025-26L3
Open Tender
Civil Works - Roads
90 days
MAPUSA
Please refer Tender documents.
3 documents required · 3 mandatory
₹5,000
₹41,911
7 Apr 2026
1 Apr 2026
7 Apr 2026
1 Apr 2026
6 Apr 2026
1 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Demolishing laterite stone masonry in cement mortar including stacking of serviceable material & disposal of unserviceable material within 50 mts lead. | - | cum | - | - | BI01010001010000000000000515BI0100001112 |
| 2 | Earthwork in excavation for roadway as per drawing and specification, in all types of strata comprising any of the material such as soil, silt, sand, clay, gravel, murrum of all varieties, shingles, pebbles all types of conglomerates, laterites rock, etc soft rock, ordinary rock or disintegrated rock fissured shattered/ decomposed rock or weathered rock all such material as described under appendix to those specification either in full or in parts as the case may be adopting mechanical means (hydraulic excavator) or any approved method or methods as the case may be convenient or permitted inclusive of chiseling and wedging etc in all conditions such as dry, moist,saturated, submerged, foul condition etc including setting out, construction of shoringand bracing, removal of stumps and other deleterious matter, dressing sides, ramming of bottoms,getting out the excavated soil/rock to be leveled and neatly dressed, pumping and bailing out of water, back filling the excavated earth to the extent required and utilizing the remaining earth locally for road work, barricading, danger lightening, guarding and disposal of excavated earth as directed by the engineer in charge all complete including all leads and lifts and upto depth of excavation as per MORT&H Specification 301. | - | m3 | - | - | BI01010001010000000000000515BI0100001113 |
| 3 | Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete. | - | cum | - | - | BI01010001010000000000000515BI0100001114 |
| 4 | Providing and laying in position cement concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded granitic or basaltic stone aggregate 40 mm nominal size) excluding cost of centering, shuttering and finishing :a)All works upto plinth level . | - | cum | - | - | BI01010001010000000000000515BI0100001115 |
| 5 | Providing and laying in position cement concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded granitic or basaltic stone aggregate 40 mm nominal size) excluding cost of centering, shuttering and finishing :In retaining walls , return walls(any thk) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing
courses, parapets, coping bed blocks, anchor blocks, plain window sills, fillets etc, upto floor five level. | - | cum | - | - | BI01010001010000000000000515BI0100001116 |
| 6 | Centering & shuttering including Strutting, Propping & removal of forms for : i)Foundations, Footings, Bases for columns. | - | sqm | - | - | BI01010001010000000000000515BI0100001117 |
| 7 | Centering & shuttering including Strutting, Propping & removal of forms for : vertical surfaces such as retaining walls , return walls, walls (any thk) including attached pilasters, buttresses, plinth and string courses, fillets, etc. | - | sqm | - | - | BI01010001010000000000000515BI0100001118 |
| 8 | Providing and fixing weepholes with rigid PVC make laid in position with a required slope and level while layingpipes of approved the concrete of retaining wall,wing wall and earth retainig structure complete as directed by the Engineer in charge | - | RM | - | - | BI01010001010000000000000515BI0100001119 |
| 9 | Construction of embankement with approved material obtained from borrowpits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting with Static roller to meet requirement of Table 300-2 as per MORTH specification 305 | - | m3 | - | - | BI01010001010000000000000515BI0100001120 |
| 10 | Providing and fixing G.I. chain link mesh 6.35cm x 6.35 cm x 10 gauge (2.5” x 2.5” x 10 gauge) fixed with angle iron posts and struts by G.I. or M.S. staples at 20cms apart with welding with the iron posts (placed at 3 meters centre to centre) including providing barbed wire stiffeners (shall weigh 9.33 kg. per 100 meters minimum) at top and bottom with barbed wire stiffers by binding wires at 50cms centre to centre complete as per the direction of the Engineer – in – charge (angle iron posts struts, earthwork and concrete for fencing posts and struts to be paid separately) | - | Metre | - | - | BI01010001010000000000000515BI0100001121 |
stage.html
html • 0.03 MB
technical_28914.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.49 MB
Tendernotice_2.pdf
PDF • 0.80 MB
BOQ_28914.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid