| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹1.3 CrAccepted-AOC | ₹1.3 Cr | L-1 | Accepted-AOC responsive |
| 2 | L-2₹1.3 CrRejected-Finance | ₹1.3 Cr | L-2 | Rejected-Finance non responsive |
Tender Value
₹1.3 Cr
EMD Value
₹8.7 L
Closing Date
24 Jun 2026, 12:00 pmClosed
SE MBD CIRCLE PWD MORADBAD
SE MBD CIRCLE PWD MORADBAD
Year 2025-26 Under New Construction of Pawansa Chandausi Aata mau Assu Pawansa road to Rahma Devi Singhpur link road
2026_CEMBD_1161343_1
3376/E-Nivida-MBD Circle/26-27 DT 05-06-2026
Open Tender
Civil Works - Roads
365 days
SAMBHAL
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹8.7 L
Yes
SE MBD CIRCLE PWD MORADBAD
2 Jul 2026
17 Jun 2026
24 Jun 2026
17 Jun 2026
24 Jun 2026
17 Jun 2026
20 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of subgrade and earthenshoulders with approved material obtained from road side with all lifts and leads trancporting to sites, spreading, grading to required slope and compected to meet requirement of table 300.2 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | 18,500 | cum | 80 | ₹14,80,000 |
| 2 | Providing, Laying & Spreading Material on a prepared sub grade, adding cement @ 2% by weight to the spread material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined, compressive strength and to form a layer of sub-base. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | 825 | cum | 4,300 | ₹35,47,500 |
| 3 | Providing, treated, Laying & spreading Material on a prepared sub grade, adding cement @4% by weight to the spread material (G-3 with 4% cement OPC) manually, mixing in place ith rotavator and compacting with the road roller at OMC to achived the desired unconfined, compressive strenght and to form a layer of sub-base. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | 825 | cum | 5,200 | ₹42,90,000 |
| 4 | Providing & applying tack coat with bitumen VG-10 using pressure distributor at the rate of 0.30 kg per sqm on the prepared bituminous/granular surface incliding supply of all meterial T&P and labour cess etc. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | 8,250 | Sqm | 15 | ₹1,23,750 |
| 5 | P/L of open graded premix carpeting of 20mm thick composed with 13.2 mm and 11.2mm grit aggregate or approved graded grit @ 0.27 cum/10Sqm. using 80/100 bitumen @ 146.00 Kg./100Sqm. as bearing course, including heating of bitumen to required temperature, and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | 8,250 | Sqm | 190 | ₹15,67,500 |
| 6 | Providing and applying seal coat type ‘C’ with 6.8 mm gauge stone grit @ 0.90 cum/100 Sqm & bitumen 65 kg/100 Sqm including heating of bitumen to required temperature, mixing of stone gri with suitable mixol, laying and rolling with a smooth wheeled roller including cost of all material, Labour, royalty, T&P and all taxes etc required for proper completion of work and roller charges and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | 8,250 | Sqm | 71 | ₹5,85,750 |
| 7 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | - | cum | 35 | - |
| 8 | providing concrete for plain/reinforced concrete P.C.C. Grade M-10 (1:3:6) in open foundations complete as per drawing and technical specifications. and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | 12 | cum | 7,100 | ₹85,200 |
| 9 | Laying and compacting dry O.B.B. 40mm. Gauge in foundation in layers of not more than 15cm. Thickness including local sand, in ratio 2:1 as per direction of the Engineer-in-Charge and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T.. Chp 1 2c | 40 | cum | 1,100 | ₹44,000 |
| 10 | Brick masonry work in cement mortar in foundation complete excepting pointing and plastering, as per drawing and technical specification Clauses 600, 1202 & 1203 and including all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. | 59 | cum | 6,200 | ₹3,65,800 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.93 MB
Tendernotice_2.pdf
PDF • 5.90 MB
BOQ_2176792.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid