| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹32.4 LAdmitted-Finance | ₹32.4 L | L1 | Admitted-Finance |
| 2 | L2₹68.0 L+₹35.6 L (110.1%)Admitted-Finance | ₹68.0 L+₹35.6 L (110.1%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | S PERIYASAMY L1 | Thanusri Venture L2 |
|---|---|---|---|---|---|
| 1.00Earthwork excavation by mechanical means (Hydraulic excavator) for foundation, substructures, plinth beam, cess pits & trenches, all kinds of foundation etc., in all types of soil like hard gravelly soil, sandy soil for the following depth from average ground level upto the required founding level, line and grades in both dry and wet conditions including shoring, strutting, bailing out of water if necessary, levelling and ramming the bottom of trenches, dressing of sides, stacking the excavated materials away from the edge of trenches, refilling the sides of foundation as required with selected excavated earth and depositing / disposing the surplus excavated earth (Disposed soil to be leveled by breaking clods, if any and neatly dressed and leveled) within the lead specified below all complete as per specifications and as directed by the Engineer-in-Charge. | |||||
| 1.01 | All kinds of soil with depth upto 1.5m below average Ground level and disposing surplus excavated earth upto a lead of 50 metres. | 60 | Cu.m. | 450 ₹27,000 Lowest | 1,200 ₹72,000 |
| 2.00 | Providing and fixing double Tubular scaffolding system using H-Frames / APS system or (cup lock type) on the exterior side made with 40mm dia M.S. tube 1.5m centre to centre horizontal and vertical tubes joining with cup and lock system with M.S. tubes, M.S. tube challies, M.S clamps and M.S staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connection with building etc. wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and as approved by the Engineer -in-Charge. Note : 1. The elevation area of the scaffolding shall be measured for payment purposes. 2. The payment shall be made once irrespective of duration of scaffolding. 3. The scaffolding system drawing shall be got approved by Engineer-in-Charge. 4. The contractor has to observe all safety procedure while working on heights as per I.S. 3696 (Part-I) (Safety Code for scaffolds). 5. Screen of suitable material shall be provided to the full height of scaffolding and securely tied to protect falling objects coming out during the work is in progress. 6. Necessary aluminium / M.S. ladder shall be provided at the cost of the contractor, to the full height of scaffolding at required location around the building to enable Departmental Supervisor/Engineer climb up and closely watch the repair work of the building. | 1,500 | Sq.m. | 203 ₹3,04,500 Lowest | 500 ₹7,50,000 |
| 3.00 | Dismantling Plain Cement concrete by manually / by mechanical means at all levels, carefully without damaging adjacent structures including disposal of debris with 50m lead, labour, tools required etc. complete in all respects as per specifications and directed by the Engineer-in-charge. | 10 | Cu.m. | 900 ₹9,000 Lowest | 3,000 ₹30,000 |
| 4.00 | Dismantling of RCC works at all levels by manually / by mechanical means, including Cutting and stacking of steel reinforcement bars and disposal of unserviceable materials within 50m lead as per specifications and directed by the Engineer-in-charge. | 10 | Cu.m. | 2,500 ₹25,000 Lowest | 4,000 ₹40,000 |
| 5.00 | Dismantling brick work in cement mortar at all levels by manually / by mechanical means, carefully without damaging adjacent structures including stacking of serviceable materials and disposal of unserviceable materials within 50m lead all as per specifications and directed by the Engineer-in-charge. | 20 | Cu.m. | 800 ₹16,000 Lowest | 3,000 ₹60,000 |
| 6.00 | Dismantling weather proofing old bitumen felt or App membrane sheets at all levels and cleaning the surface including disposal of rubbish to the dumping yard within 50 metres lead all as per specifications and directed by the Engineer-in-charge. | 350 | Sq.m. | 90 ₹31,500 Lowest | 310 ₹1,08,500 |
| 7.00Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-in-Charge for the following. | |||||
| 7.01 | Upto 25mm average thickness | 225 | Sq.m. | 100 ₹22,500 Lowest | 380 ₹85,500 |
| 7.02 | Above 25mm and upto 50mm average thickness | 75 | Sq.m. | 125 ₹9,375 Lowest | 550 ₹41,250 |
Tender Value
₹31.2 L
EMD Value
₹62,340
Closing Date
17 Jun 2026, 11:25 amClosed
Chief Engineer, CEG
Room No. 222, CDO Building, Indira Gandhi Centre for Atomic Research, Kalpakkam - 603102.
Retrofitting works for VNAS building in IGCAR, Kalpakkam.
2026_IGCAR_903699_1
CEG/IGC/2166/2026
Open Tender
Construction Works
Item Rate
240 days
Kalpakkam
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹62,340
15 Jul 2026
25 Mar 2026
18 Jun 2026
26 Mar 2026
17 Jun 2026
27 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Earthwork excavation by mechanical means (Hydraulic excavator) for foundation, substructures, plinth beam, cess pits & trenches, all kinds of foundation etc., in all types of soil like hard gravelly soil, sandy soil for the following depth from average ground level upto the required founding level, line and grades in both dry and wet conditions including shoring, strutting, bailing out of water if necessary, levelling and ramming the bottom of trenches, dressing of sides, stacking the excavated materials away from the edge of trenches, refilling the sides of foundation as required with selected excavated earth and depositing / disposing the surplus excavated earth (Disposed soil to be leveled by breaking clods, if any and neatly dressed and leveled) within the lead specified below all complete as per specifications and as directed by the Engineer-in-Charge. | |||||
| 1.01 | All kinds of soil with depth upto 1.5m below average Ground level and disposing surplus excavated earth upto a lead of 50 metres. | 60 | Cu.m. | - | - |
| 2 | Providing and fixing double Tubular scaffolding system using H-Frames / APS system or (cup lock type) on the exterior side made with 40mm dia M.S. tube 1.5m centre to centre horizontal and vertical tubes joining with cup and lock system with M.S. tubes, M.S. tube challies, M.S clamps and M.S staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connection with building etc. wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and as approved by the Engineer -in-Charge. Note : 1. The elevation area of the scaffolding shall be measured for payment purposes. 2. The payment shall be made once irrespective of duration of scaffolding. 3. The scaffolding system drawing shall be got approved by Engineer-in-Charge. 4. The contractor has to observe all safety procedure while working on heights as per I.S. 3696 (Part-I) (Safety Code for scaffolds). 5. Screen of suitable material shall be provided to the full height of scaffolding and securely tied to protect falling objects coming out during the work is in progress. 6. Necessary aluminium / M.S. ladder shall be provided at the cost of the contractor, to the full height of scaffolding at required location around the building to enable Departmental Supervisor/Engineer climb up and closely watch the repair work of the building. | 1,500 | Sq.m. | - | - |
| 3 | Dismantling Plain Cement concrete by manually / by mechanical means at all levels, carefully without damaging adjacent structures including disposal of debris with 50m lead, labour, tools required etc. complete in all respects as per specifications and directed by the Engineer-in-charge. | 10 | Cu.m. | - | - |
| 4 | Dismantling of RCC works at all levels by manually / by mechanical means, including Cutting and stacking of steel reinforcement bars and disposal of unserviceable materials within 50m lead as per specifications and directed by the Engineer-in-charge. | 10 | Cu.m. | - | - |
| 5 | Dismantling brick work in cement mortar at all levels by manually / by mechanical means, carefully without damaging adjacent structures including stacking of serviceable materials and disposal of unserviceable materials within 50m lead all as per specifications and directed by the Engineer-in-charge. | 20 | Cu.m. | - | - |
| 6 | Dismantling weather proofing old bitumen felt or App membrane sheets at all levels and cleaning the surface including disposal of rubbish to the dumping yard within 50 metres lead all as per specifications and directed by the Engineer-in-charge. | 350 | Sq.m. | - | - |
| 7Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-in-Charge for the following. | |||||
| 7.01 | Upto 25mm average thickness | 225 | Sq.m. | - | - |
| 7.02 | Above 25mm and upto 50mm average thickness | 75 | Sq.m. | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.47 MB
2166technicalbid.pdf
Tender Documents • 2.63 MB
2166Undertakingsandformoftender.pdf
Tender Documents • 0.22 MB
2166FormsACDFGHforfillinganduploading.xls
Tender Documents • 0.08 MB
BOQ_949894.xls
BOQ • 0.33 MB
2166amt5.pdf
PDF • 0.48 MB
2166Amend05202026122709.pdf
PDF • 0.34 MB
2166amen3.pdf
PDF • 0.36 MB
2166amt2.pdf
PDF • 0.36 MB
2166ament1.pdf
PDF • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .