| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹37.1 LAccepted-AOC 32 FATEH ENCLAVE OFFICERS ENCLAVE PHASE II PATIALA 147001 PB | PATIALA | PATIALA | PUNJAB | 147001 | L1 | Accepted-AOC BEING LOWEST | |
| 2 | L2₹42.3 L+₹3.9 L (10.3%)Rejected-Finance 205 PARSHAV VIHAR PLOT NO 50 1 P EXTN PATPARGANJ DELHI 110092 | DELHI | EAST DELHI | DELHI | 110092 | L2 | Rejected-Finance NOT BEING LOWEST | |
| 3 | L3₹43.8 L+₹5.5 L (14.4%)Rejected-Finance H NO 597 SEONA ROAD RANJIT NAGAR PATIALA PB 147001 | PATIALA | PATIALA | PUNJAB | 147001 | L3 | Rejected-Finance NOT BEING LOWEST | |
| 4 | L4₹48.4 L+₹10.1 L (26.3%)Rejected-Finance BOOTH NO 119 SECTOR 9 PANCHKULA 134109 HARYANA | PANCHKULA | PANCHKULA | HARYANA | 134109 | L4 | Rejected-Finance NOT BEING LOWEST | |
| 5 | L5₹49.9 L+₹11.6 L (30.3%)Rejected-Finance 300 PREM BASTI 10 SANGRUR SANGRUR PUNJAB 148001 | SANGRUR | PUNJAB | 148001 | L5 | Rejected-Finance NOT BEING LOWEST |
| Sl No | Description | Qty | Unit | Jawandha Enterprises L3 | Arneja Builders L6 | SWAMI ENGINEERS L1 | sanjeev enterprises L2 | AGGARWAL & CO L5 | SHARMA ELECTRICAL ENGINEERS L4 |
|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Surface excavation not exceeding 30 cm and averaging 15 cm deep and getting out in soft/loose soil including removing green vegetation, roots, bushes,etc from surrounding of LT feeder Boards/Poles/substations etc complete all as specified. | 850 | Sqm | 25 ₹21,250 | 20 ₹17,000 | 25 ₹21,250 | 10 ₹8,500 Lowest | 80 ₹68,000 | 32 ₹27,200 |
| 2.00 | Excavation in trenches not exceeding 1.5 mtr wide and not exceeding 3.0 mtr in depth for laying of cables errecting of pole including getting out in any kind of soil complete all as specified and directed. | 806.11 | Cum | 100 ₹80,611 | 175 ₹1,41,069.25 | 85 ₹68,519.35 Lowest | 100 ₹80,611 | 120 ₹96,733.2 | 90 ₹72,549.9 |
| 3.00 | All as per item no 2 above but exceeding more than 1.5 m in depth | 2 | Cum | 150 ₹300 | 150 ₹300 | 150 ₹300 | 150 ₹300 | 80 ₹160 Lowest | 200 ₹400 |
| 4.00 | Returning filling in including spreading, levelling, and well ramming, in layers not exceeding 25 cm each layer of any kind of soil. | 432.04 | Cum | 25 ₹10,801 | 110 ₹47,524.4 | 25 ₹10,801 | 30 ₹12,961.2 | 90 ₹38,883.6 | 10 ₹4,320.4 Lowest |
| 5.00 | Removing surplus excavated material from site not exceeding 50 mtrs from starting point and depositing where directed at a level not exceeding 1.5 mtr above the starting point. | 374.07 | Cum | 25 ₹9,351.75 | 50 ₹18,703.5 | 25 ₹9,351.75 | 30 ₹11,222.1 | 50 ₹18,703.5 | 10 ₹3,740.7 Lowest |
| 6.00 | Clean dry sand laid in trenches/ducts for bedding and cushioning to cable, including spreading and leveling complete, all as specified.
Note:-(i) Consolidated/punned sand shall be considered for purpose of payment.(ii) Sand shall be same as specified for plastering work. | 271.35 | Cum | 350 ₹94,972.5 | 600 ₹1,62,810 | 500 ₹1,35,675 | 350 ₹94,972.5 | 250 ₹67,837.5 Lowest | 350 ₹94,972.5 |
| 7.00 | Taking up or down 10 sqmm 2 core worn out/ damaged / partially serviceable/unserviceable PVC insulated underground cable, armoured, heavy duty with aluminium conductors 1100 volt grade from trench including taking out unserviceable bricks,pipes etc testing of cable in the presence of Engr-in-charge to ascertain seviceability,seggregating serviceable and unserviceable cable and keeping in safe custody the serviceable portion for reuse, stocking serviceable bricks for reuse complete all as specified and directed
(Note: Earth work shall be measured and paid separately under relevant item of BoQ ). | 150 | RM | 15 ₹2,250 | 25 ₹3,750 | 10 ₹1,500 | 10 ₹1,500 | 10 ₹1,500 | 5 ₹750 Lowest |
| 8.00 | All as per item No. 07 here-in before but for cable of size 4 core 10 sqmm. | 350 | RM | 17 ₹5,950 | 30 ₹10,500 | 10 ₹3,500 | 10 ₹3,500 | 10 ₹3,500 | 5 ₹1,750 Lowest |
| 9.00 | All as per item No. 07 here-in before but for cable of size 4 core 16 sqmm. | 200 | RM | 20 ₹4,000 | 30 ₹6,000 | 10 ₹2,000 | 10 ₹2,000 | 10 ₹2,000 | 5 ₹1,000 Lowest |
| 10.00 | All as per item No. 07 here-in before but for cable of size 4 core 25 sqmm. | 500 | RM | 25 ₹12,500 | 40 ₹20,000 | 10 ₹5,000 | 10 ₹5,000 | 10 ₹5,000 | 5 ₹2,500 Lowest |
Tender Value
Refer Docs
EMD Value
₹88,000
Closing Date
20 Jun 2026, 6:00 pmClosed
MAJ MOHAMMED AQIL AZEEM
GE NORTH PATIALA MILITARY ENGINEER SERVICES SANGRUR ROAD PATIALA CANTT
REPAIR/REPLACEMENT OF LT OVERHEAD LINES,LT CABLES,LT SWITCH GEARS AND LT PANELS, AND ASSOCIATED WORKS AT SECTOR C UNDER GE (N) PATIALA
2026_MES_767833_1
GE (N)/TOKEN-30/2026-2027
Open Tender
Electrical and Maintenance Works
Item Rate
180 days
PATIALA
AS PER TENDER DOCUMENTS
9 documents required · 9 mandatory
₹500
GE N PATIALA
₹88,000
Yes
13 Aug 2026
26 May 2026
22 Jun 2026
26 May 2026
20 Jun 2026
13 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Surface excavation not exceeding 30 cm and averaging 15 cm deep and getting out in soft/loose soil including removing green vegetation, roots, bushes,etc from surrounding of LT feeder Boards/Poles/substations etc complete all as specified. | 850 | Sqm | 10 | ₹8,500 |
| 2 | Excavation in trenches not exceeding 1.5 mtr wide and not exceeding 3.0 mtr in depth for laying of cables errecting of pole including getting out in any kind of soil complete all as specified and directed. | 806.11 | Cum | 22 | ₹17,734.42 |
| 3 | All as per item no 2 above but exceeding more than 1.5 m in depth | 2 | Cum | - | - |
| 4 | Returning filling in including spreading, levelling, and well ramming, in layers not exceeding 25 cm each layer of any kind of soil. | 432.04 | Cum | 1 | ₹432.04 |
| 5 | Removing surplus excavated material from site not exceeding 50 mtrs from starting point and depositing where directed at a level not exceeding 1.5 mtr above the starting point. | 374.07 | Cum | 10 | ₹3,740.7 |
| 6 | Clean dry sand laid in trenches/ducts for bedding and cushioning to cable, including spreading and leveling complete, all as specified.
Note:-(i) Consolidated/punned sand shall be considered for purpose of payment.(ii) Sand shall be same as specified for plastering work. | 271.35 | Cum | 22 | ₹5,969.7 |
| 7 | Taking up or down 10 sqmm 2 core worn out/ damaged / partially serviceable/unserviceable PVC insulated underground cable, armoured, heavy duty with aluminium conductors 1100 volt grade from trench including taking out unserviceable bricks,pipes etc testing of cable in the presence of Engr-in-charge to ascertain seviceability,seggregating serviceable and unserviceable cable and keeping in safe custody the serviceable portion for reuse, stocking serviceable bricks for reuse complete all as specified and directed
(Note: Earth work shall be measured and paid separately under relevant item of BoQ ). | 150 | RM | - | - |
| 8 | All as per item No. 07 here-in before but for cable of size 4 core 10 sqmm. | 350 | RM | 1 | ₹350 |
| 9 | All as per item No. 07 here-in before but for cable of size 4 core 16 sqmm. | 200 | RM | 10 | ₹2,000 |
| 10 | All as per item No. 07 here-in before but for cable of size 4 core 25 sqmm. | 500 | RM | 22 | ₹11,000 |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.42 MB
BOQ_859873.xls
BOQ • 0.49 MB
TENDERDOCUMENTS.pdf
Tender Documents • 2.10 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .