| Sl No | Description | Qty | Unit | ANBUMANI L1 | MPANDCO L2 |
|---|---|---|---|---|---|
| 1.00Providing For CC Pavement at Sri Ram Nagar in Puliyamangalam Panchayat (70m) | |||||
| 2.00 | Plain Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials and all labour charges for mixing laying and compacting etc. complete | 23.47 | cum | 5,840 ₹1,37,065 Lowest | 6,000 ₹1,40,820 |
| 3.00 | Supply and erecting of centering including cost and conveyance of all materials to work site and all labaour charges etc complete | 24.5 | m2 | 180 ₹4,410 Lowest | 210 ₹5,145 |
| 4.00 | Cement Concrete 1:2:4 mix using 20mm metal including cost and conveyanceof all materials to work site and all labour charges etc. | 17.6 | cum | 7,140 ₹1,25,664 Lowest | 7,147.28 ₹1,25,792 |
| 5.00 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) | 1 | GST Amount | 48,085.02 ₹48,085.02 Lowest | 48,916.26 ₹48,916.26 |
Tender Value
₹3.2 L
EMD Value
₹3,240
Closing Date
26 Feb 2026, 3:00 pmClosed
BDO VP AKM
Panchayat Union Arakkonam
Providing For CC Pavement at Sri Ram Nagar in Puliyamangalam Panchayat (70m)
2026_RDTN_666373_1
AA1/2826/2025
Open Tender
Civil Works
Item Rate
180 days
Panchayat Union Arakkonam
Please refer Tender documents.
1 document required · 1 mandatory
₹0
₹3,240
Yes
16 Aug 2026
25 Feb 2026
26 Feb 2026
25 Feb 2026
26 Feb 2026
25 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing For CC Pavement at Sri Ram Nagar in Puliyamangalam Panchayat (70m) | - | - | - | - |
| 2 | Plain Cement Concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials and all labour charges for mixing laying and compacting etc. complete | 23.47 | cum | 5,851.46 | ₹1,37,333.77 |
| 3 | Supply and erecting of centering including cost and conveyance of all materials to work site and all labaour charges etc complete | 24.5 | m2 | 182.5 | ₹4,471.25 |
| 4 | Cement Concrete 1:2:4 mix using 20mm metal including cost and conveyanceof all materials to work site and all labour charges etc. | 17.6 | cum | 7,147.28 | ₹1,25,792.13 |
| 5 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) | - | GST Amount | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.25 MB
BOQ_800441.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .