| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.7 CrAccepted-AOC 1804 SECTOR 2 HUDA 124001 | ROHTAK | HARYANA | 124001 | ₹3.7 Cr | L1 | Accepted-AOC Ok |
| 2 | L2₹4.3 Cr+₹61.1 L (16.6%)Rejected-Finance | ₹4.3 Cr+₹61.1 L (16.6%) | L2 | Rejected-Finance ok |
Tender Value
₹3.6 Cr
EMD Value
₹7.3 L
Closing Date
12 Mar 2021, 5:00 pmClosed
Executive Engineer, Provincial Division No. 1
Executive Engineer, Provincial Division No. 1
Road cuts on various roads under the control of Provincial Division No. 1, PWD BnR, Rohtak. (1) Old DHS road from Km. 65.900 to 67.760 (2) Old DHS road from Km. 67.760 to 68.570 (3) Old DHS road from Km. 68.570 to 69.110 (4) Northern Bye Pass from Km
2021_HRY_160464_2
1018-1318
Open Tender
Civil Works - Roads
Item-rate/Agreement basic
180 days
Rohtak
Please refer Tender documents.
2 documents required · 2 mandatory
₹15,000
₹7.3 L
Yes
Rohtak
26 Jul 2021
19 Feb 2021
15 Mar 2021
19 Feb 2021
12 Mar 2021
19 Feb 2021
26 Feb 2021
Amount
Milling of distress bituminous layer upto 40mm depth in a single pass with suitable milling machine (capable of milling @ 200-300 sqm area per Hr.) fitted with loading conveyor for loading the milled material directly on the trucks i/c hauling and stock piling the reclaimed material near the central recycling plant or reclaiming to bring to required specification to reuse with the approval of Engineer-in-Charge for safe disposal with all leads and lifts complete in all respects. Note :- 1. The unutilized quantity of reclaimed bituminous mix material shall be a recovery item as mention in BOQ item No. 12. 2. The quantity of reclaimed material shall be considered minimum 80% of theoretical volume. The reclaimed material shall be used 30% of total quantity of DBM item No. 10 as per clause No. 519 of MoRT&H specifications.
Earth work excavation in ordinary soil exclusive of compensation of earth. Kassi work undressed involving an average horizontal throw upto 2 metres, and an average vertical lift upto 0.5 metre including breaking of clods. Excavated earth may be reused on berms and disposed off surplus earth with all lead and lift including dressing complete in territorial as per direction of Engineer-in-charge will be incidental to work and nothing will be paid. (NS)
Construction of embankment, for replace of sub grade upto 500 mm in Mastnath stadium road to IMT chowk at RD km. 65.900 to 67.760, Bohar Majra chowk to Mastnath stadium road at RD 67.760 to 68.570, Omex city gate to Bohar Majra chowk at RD 68.570 to 69.110 (city portion) & Khokhra Kot road crossing at RD 5.900 to 5.967 & 6.200 to 6.400 with soil of minimum CBR 8 % (4 days soaked) of obtained from borrow area with any lead and lift transporting to site, spreading, grading to required slope and compacted to meet requirement of table 300-2 of MoRT&H specification clause No. 305. The finished road surface will be as per X-section approved by engineer the quantity of earth work calculated with NSL and finished level found to be less than the actual quantity (less than 10101.35 cum) will be paid. In case quantity worked out is more than 10101.35 cum, then only 10101.35 cum will be paid. Excess quantity shall be incidental to work and nothing extra will be paid. Further it shall be ensured that atleast 500 mm of sub grade with earth of CBR 8% shall be constructed at each location. Wherever any cutting of existing subgrade is required on this account excavation as well as handling and disposal of earthwork to accommodate minimum 500mm thick subgrade of minimum 8% CBR shall be carried out by the agency at his own cost. Nothing extra will be paid on this account. Before start of work, L-section shall be got approved from the employer with respect to GTS. However, typical X-section attached section-9 of DNIT. Note:1.) If soil of CBR 8% is not available then the agency will do appropriate stabilization as per IRC –SP-89-2010 as approved by SE-in-Charge and nothing extra shall be paid on this account and it will be incidental to work. No earth work will be allowed from PWD land.
Disposal of surplus earth with all lead and lift as per direction of Engineer-in Charge. {HSR 5.2 (a) + 4.1 (a)}
Providing and laying 150mm thick granular sub base consisting of filter layer confirming to Table 400.1 Grading - III of MoRT&H 5th edition, mixing in a mechanical mix plant at OMC, carriage of mix material to the site of work, spreading in uniform layer with motor grader on prepared surface and compacting with vibratory power roller to achieve desired density complete as per clause No. 401 of MoRT&H specifications. Note: - 1.Only crushed metal material should be used. No local earth sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI).2. Materials to be used and operations of manufacturing shall be approved by engineer.
Providing and laying 150mm thick granular sub base consisting of drainage layer confirming to Table 400.1 Grading - VI of MoRT&H 5th edition, mixing in a mechanical mix plant at OMC, carriage of mix material to the site of work, spreading in uniform layer with motor grader on prepared surface and compacting with vibratory power roller to achieve desired density complete as per clause No. 401 of MoRT&H specifications. Note: - 1.Only crushed metal material should be used. No local earth sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations of manufacturing shall be approved by engineer.
Providing & laying 250mm thick (Compacted) stone metal (G-II) 53mm to 22.4mm gauge wearing coat to water bound macadam in layer of 75/100mm each using screening type ‘B’ compacting with 3 wheeled steel roller/vibratory roller to achieve the desire density including lighting, guarding barricading and maintenance of diversion etc. as per clause No.404 of MoRT&H specifications for road & bridge (5th Revision) of 2013 as per drawing and design directed by the Engineer complete in all respects.(N.S.) Note: - 1.Only crushed stone metal material should be used. No local earth/ natural occurring sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations of manufacturing shall be approved by engineer.
Providing and applying primer coat with bitumen emulsion (S.S grade - I) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 Kg/Sqm using mechanical means as per MoRT&H specification for road & bridge (5th Revision) of 2013 as per drawing and design directed by the Engineer complete in all respects as per clause No.502. (N.S.)
Providing and laying tack coat with bitumen VG-10 grade pressure distributor at the rate of 0.30 kg. per sqm. on the prepared bitumen/granular surface cleaned with mechanical broom including cost of bitumen as per clause No.503 (5th edition) 2013 as per MoRT&H specification (N.S.)
Providing & laying 50 mm DBM using the reclaimed material to the extent of 30% per cent of the required quantity after carrying out necessary checks and evaluation, adding fresh material including rejuvenation as required, grade, level and thickness, all as specified in clause 519. (5th revision) 2013 using bitumen VG-30 (minimum Bitumen's 4.50% i/c bitumen of retrieved material as per job mix formula ) using 100-120 TPH batch type hot mix plant with appropriate arrangement for use of R.A.P, appropriate rollers and with hydraulic paver finisher with sensor control to the required grade. The milled material to be used in DBM shall be minimum 80% of the theoretical quantity. Note: - If bitumen required more than 4.50% as per job mix formula no extra payment will be paid extra bitumen required will be considered as incidental to work. Note: - Before carrying out bituminous work, coating & stripping of bitumen aggregate mix is to be performed in accordance with IS – 6241. If coating and stripping of bitumen aggregate mix is less than 95%, anti-stripping agent will be used by contractor. The anti – stripping agent should conform to the requirement as stipulated in IS 14982:2017. The cost so incurred will be considered as incidental to work and nothing extra shall be payable. The type and brand of anti-stripping agent along with procedure shall be approved by SE-in-charge in writing before start of work. A proper record of results be maintained and same shall be submitted along with bills by the contractor. 3). Where there is DBM on existing black top , cracks shall be sealed as MoRT&H specification 5th revision clause No. 3004.3, which may consists of (i) Fog seal/ or (ii) crack filling and or (iii) patch work repair as required at site in accordance with clause No. 3004.3.2, 3004.3.3 and 3004.2 of MoRT&H specification 5th revision respectively. Proper measurement and consumption shall be entered in MB for cracks sealed but no payment on this account shall be made as crack filling is incidental to work.
Providing and laying 40 mm compacted thickness of Bituminous Concrete (BC) in one layer with 100 - 120 TPH Batch Type Hot Mix Plant with bituminous binder VG-30 @ 5.4% (minimum) and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher having sufficient screed width so that the BC in full width of the carriage way is laid in single operation without any longititutinal joint with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and with pneumatic tyred roller (PTR) of 12 to 15 tonne weight with a tyre pressure of at least 0.56 MPa and tandem rollers to achieve the desired compaction as per MORT&H specification (Vth revision)-2013 Clause No. 507 complete in all respect. If bitumen required is more than 5.4% as per job mix including waste plastic material no extra payment will be made, Extra bitumen required will be considered as incidental to work. If bitumen required more than 5.4% as per job mix formula no extra payment will be made, extra bitumen required will be considered as incidental to work. Note: - Before carrying out bituminous work, coating & stripping of bitumen aggregate mix is to be performed in accordance with IS – 6241. If coating and stripping of bitumen aggregate mix is less than 95%, anti-stripping agent will be used by contractor. The anti – stripping agent should conform to the requirement as stipulated in IS 14982:2017. The cost so incurred will be considered as incidental to work and nothing extra shall be payable. The type and brand of anti-stripping agent along with procedure shall be approved by SE-in-charge in writing before start of work. A proper record of results be maintained and same shall be submitted along with bills by the contractor. Note: - Where there is only BC on existing black top, cracks shall be sealed as MoRT&H specification 5th revision clause No. 3004.3, which may consists of (i) Fog seal/ or (ii) crack filling and or (iii) patch work repair as required at site in accordance with clause No. 3004.3.2, 3004.3.3 and 3004.2 of MoRT&H specification 5th revision respectively. Proper measurement and consumption shall be entered in MB for cracks sealed but no payment on this account shall be made as crack filling is incidental to work.
Recovery items: The rates quoted against recovery items will not be included in the total amount rather it will be deducted while calculating financial statement of the agency. Material obtained from dismantling of existing bituminous layer have been calculated taking assumption that 80% of theoretical material will be retrieved. The dismantled material can used in any of the item for the work after modification (bringing it to required specifications) after approval from employer. In case it is not possible to use this material on the work, the agency can take away this material. This material can be taken away by the agency at the price quoted by the agency but minimum price to be quoted is limited to reserve price as fixed and mentioned as under :- (i) Bituminous mix material @ Rs.1334.60/- P. Cum. Note: - All quantities of the above materials have been worked out on the basis of theoretical quantities laid on this road. However, agency may visit site before quoting rates and assess the extent of retrieved material. There shall be no measurement after actual dismantling and if material after dismantling is found on lesser side, no claim of agency on this score will be entertained and full recovery on the basis of quoted rate and quantity exhibited in the BOQ shall be made. The reserve rates are minimum rates to be used as base for quoting purchase rate by the agency. No rates below the reserve price will be entertained and reserve price will be considered for all purposes in case the agency quotes lesser than reserve price.
SHIV SHAKTI CONSTRUCTION CO.
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .