| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.0 CrAccepted-AOC | ₹3.0 Cr | L1 | Accepted-AOC Lowest bidder |
| 2 | L2₹3.0 Cr+₹1.8 L (0.61%)Rejected-Finance | ₹3.0 Cr+₹1.8 L (0.61%) | L2 | Rejected-Finance Highest of L1 |
| 3 | L3₹3.1 Cr+₹14.3 L (4.76%)Rejected-Finance | ₹3.1 Cr+₹14.3 L (4.76%) | L3 | Rejected-Finance Highest of L1 |
| 4 | L4₹3.2 Cr+₹18.0 L (6.00%)Rejected-Finance | ₹3.2 Cr+₹18.0 L (6.00%) | L4 | Rejected-Finance Highest of L1 |
| 5 | L5₹3.6 Cr+₹58.2 L (19.4%)Rejected-Finance | ₹3.6 Cr+₹58.2 L (19.4%) | L5 | Rejected-Finance Highest of L1 |
Tender Value
₹4 Cr
EMD Value
₹8 L
Closing Date
15 Jan 2019, 3:00 pmClosed
SE ICC JHANSI
SE ICC JHANSI CIVIL LINE STATION ROAD JHANSI
Canal lining pitching and correcting section of Lakheri canal system
2019_UPIDC_290255_1
04/SE/2018-19
Open Tender
Civil Works
Item Rate
90 days
Revan Mauranipur Jhansi
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
Yes
EE ICD-5
₹8 L
Yes
24 Feb 2021
3 Jan 2019
16 Jan 2019
3 Jan 2019
15 Jan 2019
3 Jan 2019
Amount
Earth Work in Cutting M.K.R., Kankar Mixed soil with manual compaction & dressing with disposal such as spoil bank etc upto 50 M. including all cost of labour, T&P etc .
Earth Work in Cutting/Filling in M.K.R. in Kankar Mixed soil with manual compaction & dressing with lead up 100 M including all cost of labour, T&P etc .
Earth Work in Cutting/Filling in M.K.R. in Kankar Mixed soil with manual compaction & dressing with lead 195 M. including all cost of labour, T&P etc .
Earth Work in Cutting/Filling in M.K.R. in Kankar Mixed soil with manual compaction & dressing with lead 595M. including all cost of labour, T&P etc .
Earth Work in Filling in M.K.R. in Kankar Mixed soil with manual compaction & dressing with carriage up to 2 Km. including all cost of labour, T&P etc .
Earth Work in Filling in M.K.R. in Kankar Mixed soil with manual compaction & dressing with carriage up to 2 Km. including all cost of private earth, labour, T&P etc .
Dismantling of Stone Masonary in Cement Mortar including all cost of labour, material, T&P etc .
Earth in excavation in M.K.R. & Kankar Mixed soil, dry & mixed with soft rock with manual compaction & dressing with in Av. Lead of 30m & lift upto 1.5m. including all cost of labour, material, T&P etc .
Filling sand under foundation including all cost of labour, material, T&P etc .
Providing & Laying 1:3:6 lean concrete in foundation base with grit 20-40 mm size including supply of all cost of labour, material, T&P etc. required for proper completion of work.
RCR Khanda stone masonary with cement mortar 1:4(1cement : 4 coarse sand). including cost of all material, labour and T&P etc.
Centering & Shuttering R.C.C work including all rates of material, labour, T&P complete etc.
Mild steeel or Iron Work in plain work such as reinforced concrete /brick workwrought to required shape as necessary including bending for proper completion of work &including supply of all steel &wastage & overlapping & hooks.
Providing & Laying 1:1.5:3 Reinforced cement concret with grit 10-20 mm size including supply of all materials labour,T&P etc.required for proper completion of work.
Providing & Laying 1:2:4 Plain cement concret with grit 10-20 mm size including supply of all materials labour, T&P etc.required for proper completion of work.
Providing & Laying 1:2:4 Plain cement concret with grit 10-20 mm size including supply of all materials labour,T&P etc. required for proper completion of work for c.c.lining with Paver charges.
Raised Cement Pointing in R.C.R 1:2 cement sand mortar including all cost of labour material T&P etc .
Dewatrening by pump including hiring charge of pump and its accessories with fule, lubricant etc complete.
Dry stone boulder pitching including all cost of labour material T&P etc .
Making sub grade for lining including scraping ( kankar or black cotton ) soil from canal section and replaced it by non-expansive soil in 30 cm depth below lining with proper slope and compaction, dressing complete Work.
Centering & Shuttering for plain CC work. including all rates of Material, labour, T&P, complete work etc.
Moorum plaster 50 mm thick. including cost of all material, labour and T&P etc.
One Coat of hot coal taron new surface & one coat of hot coaltar after previously painted surface including supply of allmaterials, labour & T&P etc. required for complition of work.
Providing & Laying of 200 micron thick polithine sheet including supply of all materials labour,T&P etc.
Providing & filling position bitumen mix filler of proportion 80 kg. of hot bitumen, 1 kg of cement & 0.25 Cum of coarse sand in expansion joint in width up to 2.5 cm & Depth upto 1.5 cm. Excluding cost of fuel.
M/s Kailash Narayan Thekedar
MS YADAV AND SONS
M/S SINGH BROTHER
BHAWANA CONSTRUCTION
Hari Construction
JC Company
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .