| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹59.1 CrAccepted-AOC 121 THIRUMURUGAN NAGAR VEERIYAMPALAYAM ROAD KALAPATTY POST COIMBATORE 641048 | COIMBATORE | TAMIL NADU | 641048 | L1 | Accepted-AOC L1 | |
| 2 | L2₹63.6 Cr+₹1.2 Cr (1.91%)Rejected-AOC 11 RAMASAMY COLONY NORTH THALLAKULAM MADURAI 625002 | MADURAI | TAMIL NADU | 625002 | L2 | Rejected-AOC L2 | |
| 3 | Rejected-Technical 4 91C BYPASS ROAD PUDUKOTTAI THOOTHUKUDI THOOTHUKUDI TUTICORIN THOOTHUKUDI TAMIL NADU 628103 | TUTICORIN | TAMIL NADU | 628103 | - | Rejected-Technical Not Responsive |
Tender Value
₹59.1 Cr
EMD Value
₹29.7 L
Closing Date
16 Jun 2023, 3:30 pmClosed
Managing Director
SIPCOT Head office Egmore Chennai
Formation of Internal Roads (Road No 8, 9, 10, 11, 12 and 13) in Furniture Park at SIPCOT Industrial Park, Thoothukudi
2023_SIPCT_315365_1
NIT.No.11/CD/T.No.11/2023-24
Open Tender
Civil Works
Lump-sum
330 days
SIPCOT Industrial Park Thoothukudi
Please refer Tender documents.
15 documents required · 15 mandatory
₹0
₹29.7 L
SIPCOT Head office Egmore
21 Sept 2023
15 May 2023
19 Jun 2023
15 May 2023
16 Jun 2023
15 May 2023
29 May 2023
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1(Part A) Formation of Internal Roads | |||||
| 1.01 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness etc. complete as directed by the SIPCOT Officers. | - | Sqm | - | - |
| 1.02 | Earth work excavation for cutting work in all class of soils such as hard stiff clay, stiff black cotton soil, etc., as per SS20-B ( HGS SS.20B) and deposting the same to the road side as directed by the SIPCOT Officers etc., as per standard specification. | - | Cum | - | - |
| 1.03 | Forming embankment using excavated earth (20 Km lead) having CBR value not less then 8% which has to compacted properly and form a stable embankment including cost , loading and unloading and labour for proper setting out, stripping and storing the top soil, if necessary compacting the original ground by vibratory roller to have a relative compaction of required proctor density, spreading the materials uniformly over the entire width of embankment in layers of not exceeding 250 mm compacted thickness, breaking clods, watering with all leads for water, compacting to 95% proctor density for the soil below the top of 0.5 meter height of subgrade under optimum moisture content with moisture content adjusted in the range of one per cent (1 %) above and two percent (2%) below the optimum moisture content determined as per IS. 2720 (Part VII) with power roller rolling and other construction equipments approved by engineer-in-charge and finishing the embankment at 95% proctor density including compaction to specified requirement, working in narrow width of embankment including hire and fuel charges for all tools and plants and all other incidental charges etc. Complete as per MORTH standard specification . (Forming Embankment at 95% Compaction) etc. complete as directed by the SIPCOT Officers. | - | Cum | - | - |
| 1.04 | Forming Subgrade using carted earth with a conveyance of 20 Km having CBR value not less then 8% which has to compacted properly and form a stable embankment including cost , loading and unloading and labour for proper setting out, stripping and storing the top soil, if necessary compacting the original ground by vibratory roller to have a relative compaction of required proctor density, spreading the materials uniformly over the entire width of embankment in layers of not exceeding 500 mm compacted thickness, breaking clods, watering with all leads for water, compacting to 97% proctor density for the soil 0.5 meter height of sub grade under optimum moisture content with moisture content adjusted in the range of one per cent (1 %) above and two percent (2%) below the optimum moisture content determined as per IS. 2720 (Part VII) with power roller rolling and other construction equipments approved by engineer-in-charge and finishing the embankment at 97% proctor density including compaction to specified requirement, working in narrow width of embankment including hire and fuel charges for all tools and plants and all other incidental charges etc. Complete as per MORTH standard specification. (Forming Subgrade at 97% Compaction) etc. complete as directed by the SIPCOT Officers. | - | Cum | - | - |
| 1.05 | Construction of Granular Sub - Base (GSB) to the required compacted thickness (Drainage layer) by providing approved Coarse graded material conforming to Grading- V of Table 400 - 1 and satisfying the physical requirement for material for GSB as per Table 400 - 2 of MORTH Rev.-5 including screening, spreading in uniform layers with motor grader on prepared surface, watering and premixing by mix in place method with rotavator at OMC, and compacting with Vibratory roller 80 to 100 KN static weight to achieve the desired density and fine dressing to required grade and cross slope as directed by the SIPCOT officers etc., complete including obtaining and transporting all materials from approved quarry site to work site with all lift and lead by mechanical transport, head load or any other mode of transporation including cost and conveyance of all materials, labour charges,hire charges and fuel charges for loader, water tanker with sprinkler,motor grader, vibratory road rollers and all other equipments, tools and plants, safety measures, testing required including all other incidental charges, etc., complete as per the standard specification as per clause 401 of MORTH Rev.-5 and as directed by the SIPCOT officers. | - | Cum | - | - |
| 1.06 | Construction of Granular Sub - Base (GSB) to the required compacted thickness (Drainage layer) by providing approved Coarse graded material conforming to Grading- III of Table 400 - 1 and satisfying the physical requirement for material for GSB as per Table 400 - 2 of MORTH Rev.-5 including screening, spreading in uniform layers with motor grader on prepared surface, watering and premixing by mix in place method with rotavator at OMC, and compacting with Vibratory roller 80 to 100 KN static weight to achieve the desired density and fine dressing to required grade and cross slope as directed by the SIPCOT officers etc., complete including obtaining and transporting all materials from approved quarry site to work site with all lift and lead by mechanical transport, head load or any other mode of transporation including cost and conveyance of all materials, labour charges,hire charges and fuel charges for loader, water tanker with sprinkler,motor grader, vibratory road rollers and all other equipments, tools and plants, safety measures, testing required including all other incidental charges, etc., complete as per the standard specification as per clause 401 of MORTH Rev.-5 and as directed by the SIPCOT officers. | - | Cum | - | - |
| 1.07 | Providing and laying, spreading and compacting graded stone aggreates to Wet Mix Macadam Base Course of 250mm compacted thickness specification in two layers of 150mm thick each or else as specified on the prepared sub base by providing approved Coarse graded material conforming to Table 400 - 13 and satisfying the physical requirement for material for WMM as per Table 400 - 12 of MORTH Rev.-5, including pre-mixing the materials with water at OMC in mechanical mix plant carriage of mixed matrerial by tipper to site laying in uniform layers with favours in subbase/ base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges, rental for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev.-5 and as directed by SIPCOT Officers. | - | Cum | - | - |
| 1.08 | Providing and laying Prime coat over wet mix macadam surface using 7.00 Kg bitumen for 10 sqm area including cost and conveyance of bitumen binder including labour charges for preparing the surface and applying the required quantity as tack coat by bitumen sprayer etc.complete as per clause 502 of MORT & H specifications. etc. complete as directed by the SIPCOT Officers. | - | Sqm | - | - |
| 1.09 | Providing and laying Tack coat over treated wet mix macadam surface using 2.50 Kg bitumen to cut back for 10 sqm area including cost and conveyance of bitumen binder including labour charges for preparing the surface and applying the required quantity as tack coat by bitumen sprayer etc.complete as per clause 503 of MORT & H specifications. etc. complete as directed by the SIPCOT Officers. | - | Sqm | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
BOQ_374327.xls
BOQ Document • 0.34 MB
120913369.pdf
Tender Document • 0.39 MB
tenderdocumentII.pdf
Tender Document • 1.02 MB
TechnicalAnnexureI.pdf
Tender Document • 0.81 MB
120913371.html
Tender Document • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .