Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 LAccepted-AOC BHAROTA NIWAS SANGTI SANJAULI SHIMLA HP 171006 | SHIMLA | HIMACHAL PRADESH | 171006 | L1 | Accepted-AOC lowest rate quoted | |
| 2 | L2₹1.6 L+₹4,726.90 (3.03%)Rejected-Finance C O ZAMA MASZID GALI NO 3 MIDDLE BAZAR SHIMLA 171001 H P | SHIMLA | HIMACHAL PRADESH | 171001 | L2 | Rejected-Finance Highest Rate quoted | |
| 3 | L3₹1.7 L+₹15,756.32 (10.1%)Rejected-Finance C O ZAMA MASZID MIDDLE BAZAR SHIMLA H P | SHIMLA | HIMACHAL PRADESH | 170009 | L3 | Rejected-Finance Highest Rate quoted |
Tender Value
₹1.6 L
EMD Value
₹3,940
Closing Date
16 May 2023, 1:00 pmClosed
Er.Pratap Singh
ED.No.1 Kasumpti shimla171009
Estimate for Augmentation of 1Phase to 3Phase LT line from 100kVA,22/0.4kV Substation Jungle Mashobra ES mashobra under ESD,HPSEBL,Mashobra and for Re-organization of LT line from proposed 250KVA,11/0.4kV Substation BCS (near Mahunag) ES New Shimla
2023_HPSEB_72842_1
SED/SP-Limited Tender No-08/2023-24
Limited
Electrical Works
Percentage
90 days
Mashobra Khalini
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
₹3,940
27 May 2023
4 May 2023
17 May 2023
4 May 2023
16 May 2023
4 May 2023
eProcurement System Government of Himachal Pradesh Created By: pratap Singh Sidholi Created Date/Time: 17-May-2023 03:17 PM Tender Title: Estimate for Augmentation of 1Phase to 3Phase LT line from 100kVA,22/0.4kV Substation Jungle Mashobra ES mashobra under ESD,HPSEBL,Mashobra and for Re-organization of LT line from proposed 250KVA,11/0.4kV Substation BCS (near Mahunag) ES New Shimla Tender ID: 2023_HPSEB_72842_1
Tender Inviting Authority: Addl. Superintending Engineer, Shimla Elect. Division No.1,HPSEB Ltd., Shimla-171009.
Name of work: Estimate for Augmentation of 1Phase to 3Phase LT line from 100kVA , 22/0.4kV Substation Jungle Mashobra in ES mashobra under ESD, HPSEBL, Mashobra and for Re-organization of LT line from proposed 250KVA, 11/0.4kV Substation at BCS (near Mahunag) in ES New Shimla under ESD,HPSEBL khalini under Electrical Division No. 1
Contract No: SED/SP-limited Tender No-08/2023-24
SCHEDULE OF WORK / ITEM(S)
Sl.No Bidder Name Estimated Rate Quoted Percentage Quoted Rate in Figures and Words
1.00 Nishant Bharota(GSTN-02BERPB0382J1ZO) 157563.26 2.00 160714.53 One Lakh Sixty Thousand Seven Hundred and Fourteen
2.00 fayaz Ahmad(GSTN-NA) 157563.26 2.00 160714.53 One Lakh Sixty Thousand Seven Hundred and Fourteen
3.00 fayaz Ahmed Tantary(GSTN-NA) 157563.26 9.00 171743.95 One Lakh Seventy One Thousand Seven Hundred and Fourty Three
Lowest Amount Quoted BY: fayaz Ahmad,Nishant Bharota(160714.53)
BOQ Summary Details Tender Title: Estimate for Augmentation of 1Phase to 3Phase LT line from 100kVA,22/0.4kV Substation Jungle Mashobra ES mashobra under ESD,HPSEBL,Mashobra and for Re-organization of LT line from proposed 250KVA,11/0.4kV Substation BCS (near Mahunag) ES New Shimla Tender ID: 2023_HPSEB_72842_1
Sheet Name Sl.No Bidder Name Amount Bid Rank
BoQ1 1 fayaz Ahmad 160714.53 L1
2 Nishant Bharota 160714.53 L1
3 fayaz Ahmed Tantary 171743.95 L2
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_109529.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .