Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹5.6 LAccepted-Finance | L-1 | Accepted-Finance Admitted | |
| 2 | L-2₹6.0 L+₹34,700 (6.15%)Accepted-Finance | L-2 | Accepted-Finance Admitted | |
| 3 | L-3₹6.2 L+₹51,886 (9.20%)Accepted-Finance | L-3 | Accepted-Finance Admitted | |
| 4 | L-4₹6.5 L+₹87,800 (15.6%)Accepted-Finance | L-4 | Accepted-Finance Admitted | |
| 5 | L-5₹7.0 L+₹1.4 L (23.9%)Accepted-Finance 145 1 0 NEAR OLD LIC SHIV NAGAR VILLAGE TOWN MODIPURAM CITY MEERUT MEERUT UTTAR PRADESH 250110 INDIA | MEERUT | UTTAR PRADESH | 250110 | L-5 | Accepted-Finance Admitted |
Tender Value
₹8.7 L
EMD Value
₹9,000
Closing Date
27 Dec 2022, 4:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Superintending Engineer
Electricity Transmission Circle, 220 KV S/S Campus Natwa, Mirzapur
Installation of 63 MVA, 132/33 KV Transformer by replacing 10 MVA, 132/33 KV T/F Lepper make along with other associated works at 132 KV Rihand Power Station through ETD Robertsganj.
2022_UPTCL_759193_1
short term T. No. 52/2022-23/ETC/Mzp
Open Tender
Electrical Works
Fixed-rate
30 days
Robertsganj
As per tender specification
2 documents required · 2 mandatory
₹590
Executive Engineer, ETD, Mirzapur
₹9,000
15 Feb 2023
15 Dec 2022
28 Dec 2022
15 Dec 2022
27 Dec 2022
15 Dec 2022
Amount
Dismantling of 10 MVA, 132/33 KV Lepper make, after opening of jumpers and cable connections draining out T/F oil into 209 Ltrs capacity empty drums/rank , removal of all radiators, conservator tank, oil pipe lines, all bushing, turrets, marshaling box RTCC panel etc. blanking the radiators pipe lines, conservator tank, with proper gaskets along with nuts & bolts to complete the jobs satisfactorily including proper stacking. ( all labour, T&P shall be provided by contractor at his own cost.)
Removal of earthing for neutral and main tank of transformer by cutting of welding and removal of supports etc.
Shifting of main tank of 10 MVA, 132/33 KV, Lepper make transformer from plinth to stacking place distance approx,. 110 meter outside of switchyard including turning of to tank, if required , including all T&P and work required to complete the job satisfactorily one job equal to 05 MTR.
Dismantling of existing 33 KV T/F Bus bar (RYB) of ACSR panther conductor along with tension fitting and disc insulators including shifting & proper stacking of dismantled mterials in the store of 132 KV Rihand power station.
Stringing of new 33 KV T/F bus bar of ACSR panther conductor and tightening with gantry along with hoisting, Clamping and fixing of all hardware & fittings including all other associated works.
shifting of main tank of 63MVA, 132/33 KV transformer from unloading point to distance up to the plinth approx. 110 meter distance, including turning to tank, if required including all T&P and work required to complete the job satisfactorily at 132 KV S/S Rihand power house. One job equal to 05 Mtr.
Carriage of 20 KL transformer Oil tank from 220 KV S/S, Natwa, Mirzapur upto 132 KV S/S Robertsganj And shifting back of the same up to 220 KV S/S, Natwa after completion of the centrifuging work contractor will arrange truck/trailer for safe transportation Approx distance 165 Km.
Complete erection of 132/33 KV, 63 MVA T/F by erection of radiators, conservator tank all bushing with their turrets, connecting oil pipe, cooling fans, motor drive mechanism with tap changer. RTCC panel, and associated oil pipe line etc to complete the job satisfactorily, including first filling of T/F oil (already centrifuged transformer oil in 20 KL tank and topping up of T/F oil for circulation in transformer, Radiator pipe lines, conservator tank etc and attending oil leakage, if any and all other associated work so that transformer result are achieved to complete the erection including cost of labour T&P etc.
Centrifuging of T/F oil of 63 MVA transformer after erection at 132 KV Rihand power station in tank and circulation in conservator tank OLTC and radiator to achieve B.D.V. above 65 KV and all other parameter.
Earthing of neutral and main tank of transformer by way of cutting bending welding and concerned terminal of transformer.
Dismantling of old 33 KV, 200/100/1A current transformer by way of cutting bending, welding and connecting to concerned terminal of transformer.
Dismantling of 33 KV, old BSI by removal of earthing, jumpers and including all associated works.
Installation of 2000A Rating 36 KV BSI on its structures, Earthing, opening of jumpers and all associated works.
Installation of 1200/800/1A current transformer in place of old CT on its structures, earthing of the same, making connection of jumpers and control cable etc. including shifting from stacking place to erection place including all associated work.
Jumpering of transformer with HV side by way of cutting of conductor and on LV side with twin panther conductor from bushing to Bus. Bus to CT, CT to CB, CB to BSI etc including all associated work.
Laying and termination of control cable in DCDB, MB and RTCC panel and T/F C&R panel and its termination at transformer and control room both sides to complete the job in all respect (2x2.5 mm 24 Nos, 4x2.5 mm 230 nos., 6x2.5 mm 210 Nos, 10x2.5 mm 26 Nos.)
Dismantling of existing 40 MVA HV side LA for shifting of T/F.
Erection of existing 40 MVA HV side LA after shifting of T/F.
Fabrication & Erection of 120 KV LA, 145 KV CT & 145 KV PT for 63 MVA T/F.
Fabrication & Erection of 145 KV SF6 CB with all associated works.
Structure (column & Beam) erection for separation & strengthening of existing Bus bar.
Dismantling of existing old 33 KV Bus PT with all associated works.
Erection of new 36 KV Bus PT with all associated works.
Erection of section Isolator structure for separation of 40 MVA & 63 MVA Bus bar.
Dismantling of old 30 KV LA, 36 KV CT, 36 KV CB, 36 KV BSI with all associated works.
Fabrication & Erection of New 30 KV LA, 36 KV CT, 36 KV CB, 36 KV BSI with all associated works.
U K S ENTERPRISES
M/S ACCURATE ENGINEERING
SAI KRIPA LIFT SHIFT COMPANY
Hi-tech power transmission
M/s. ADITYA TRADING CO., KM-383, RAIDOPUR OFFICERS COLONY, AZAMGARH, U.P.-276001.
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .