Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-AOC | ₹1.2 Cr | L1 | Accepted-AOC Work Order Issued |
| 2 | L2₹1.4 Cr+₹15.4 L (12.7%)Rejected-Finance RNB ROAD KOKRAJHAR ASSAM | KOKRAJHAR | ASSAM | 783331 | ₹1.4 Cr+₹15.4 L (12.7%) | L2 | Rejected-Finance L2 Rate Rejected |
| 3 | Rejected-Technical CHATRIBARI ROAD KRISHNA NAGAR GUWAHATI 1 ASSAM | KAMRUP METRO | ASSAM | 781001 | - | - | Rejected-Technical Not Qualified |
Tender Value
₹1.4 Cr
EMD Value
₹2.7 L
Closing Date
18 Feb 2021, 3:00 pmClosed
Addl. CE., PWD (Elect), Assam, Chandmari, Ghy-3
O/O The CE, PWD (Bldg), Assam, Chandmari, Ghy-3
Establishment of New Medical College attached with existing District/Referral Hospital at Dhubri , Assam (Solar Power System)
2021_PWBNH_20719_1
CE/BLD/ELECT/ 17/2015/135 Dhubri Solar Power
Open Tender
Electrical Works
Item Rate
180 days
Dhubri
Please refer Tender documents.
6 documents required · 6 mandatory
₹4,000
Assam State Road Board Maintenance (Road) Fund
₹2.7 L
Yes
O/O The CE, PWD (Bldg), Assam, Chandmari, Ghy-3
10 Aug 2021
1 Feb 2021
18 Feb 2021
1 Feb 2021
18 Feb 2021
1 Feb 2021
5 Feb 2021
Amount
Supplying , installation, testing and Commissioning of ON-Grid Roof Top Solar PV System as per the MNRE norms and conforming to all rules, regulations, codes, procedures as specified by Central Electricity Authority (CEA),Central Electricity Regulatory Commission(CERC),Assam Electricity Regulatory Commission (AERC) and any other authority related in this regard and all components should conform to the BIS or IEC or international specifications consisting of the following specifications- >Solar PV modules consisting of required number of crystalline PV modules conforming IEC:61215/IS:14286 & IEC:61730 Part-2. >Grid interactive Power Conditioning Unit with Remote Monitoring System.( DC Distribution Board & AC Distribution Board designed for min. ambient temperature of 45 deg C). >Mounting structure Hot Dip Galvanized to withstand wind pressure 180 Km/hr and total load should be less than 60 Kg /sqm and minimum clearance of structure from roof level should be 300mm. >Junction Boxes made of GRP / FRP / Power Coated Aluminium with full dust,water & vermin proof . >IR / UV Protected PVC Cables, Pipes and Accessories shall meet IEC 60227 / IS 694, IEC 60502 / IS 1554 standards, Temp. range-10 deg C to +80 deg C . >Cables to be routed in GI cable tray..System Voltage -230 V / 415 V, 50 Hz. >Solar PV array- Min. 250 Wp. >Protective device against Surge. > Rated Out Put Power tolerance +/_ 3%. >Earthing and Lightening protections. HOSPITAL BUILDING
Supplying , installation, testing and Commissioning of ON-Grid Roof Top Solar PV System as per the MNRE norms and conforming to all rules, regulations, codes, procedures as specified by Central Electricity Authority (CEA),Central Electricity Regulatory Commission(CERC),Assam Electricity Regulatory Commission (AERC) and any other authority related in this regard and all components should conform to the BIS or IEC or international specifications consisting of the following specifications- >Solar PV modules consisting of required number of crystalline PV modules conforming IEC:61215/IS:14286 & IEC:61730 Part-2. >Grid interactive Power Conditioning Unit with Remote Monitoring System.( DC Distribution Board & AC Distribution Board designed for min. ambient temperature of 45 deg C). >Mounting structure Hot Dip Galvanized to withstand wind pressure 180 Km/hr and total load should be less than 60 Kg /sqm and minimum clearance of structure from roof level should be 300mm. >Junction Boxes made of GRP / FRP / Power Coated Aluminium with full dust,water & vermin proof . >IR / UV Protected PVC Cables, Pipes and Accessories shall meet IEC 60227 / IS 694, IEC 60502 / IS 1554 standards, Temp. range-10 deg C to +80 deg C . >Cables to be routed in GI cable tray..System Voltage -230 V / 415 V, 50 Hz. >Solar PV array- Min. 250 Wp. >Protective device against Surge. > Rated Out Put Power tolerance +/_ 3%. >Earthing and Lightening protections. MEDICAL COLLEGE BUILDING
Supplying , installation, testing and Commissioning of OFF-Grid Roof Top Solar PV System as per the MNRE norms and conforming to all rules, regulations, codes, procedures as specified by Central Electricity Authority (CEA),Central Electricity Regulatory Commission(CERC),Assam Electricity Regulatory Commission (AERC) and any other authority related in this regard and all components should conform to the BIS or IEC or international specifications consisting of the following specifications- >Solar PV modules consisting of required number of crystalline PV modules conforming IEC:61215/IS:14286 & IEC:61730 Part-2. >Grid interactive Power Conditioning Unit with Remote Monitoring System.( DC Distribution Board & AC Distribution Board designed for min. ambient Temperature of 45 deg C). >Mounting structure Hot Dip Galvanized to withstand wind pressure 180 Km/hr and total load should be less than 60 Kg /sqm and minimum clearance of structure from roof level should be 300mm. >Junction Boxes made of GRP / FRP / Power Coated Aluminium with full dust,water & vermin proof . >IR / UV Protected PVC Cables, Pipes and Accessories shall meet IEC 60227 / IS 694, IEC 60502 / IS 1554 standards, Temp. range-10 deg C to +80 deg C . >Cables to be routed in GI cable tray..System Voltage -230 V / 415 V, 50 Hz. >Solar PV array- Min. 250 Wp. >Protective device against Surge. > Rated Out Put Power tolerance +/_ 3%. >Earthing and Lightening protections. >Storage Battery - 12 V , 150 AH. > Nos. of Battery- As per requirements. >Battery Backup-3 Hrs. HOSTEL BUILDING ( BOYS)
Supplying , installation, testing and Commissioning of OFF-Grid Roof Top Solar PV System as per the MNRE norms and conforming to all rules, regulations, codes, procedures as specified by Central Electricity Authority (CEA),Central Electricity Regulatory Commission(CERC),Assam Electricity Regulatory Commission (AERC) and any other authority related in this regard and all components should conform to the BIS or IEC or international specifications consisting of the following specifications- >Solar PV modules consisting of required number of crystalline PV modules conforming IEC:61215/IS:14286 & IEC:61730 Part-2. >Grid interactive Power Conditioning Unit with Remote Monitoring System.( DC Distribution Board & AC Distribution Board designed for min. ambient Temperature of 45 deg C). >Mounting structure Hot Dip Galvanized to withstand wind pressure 180 Km/hr and total load should be less than 60 Kg /sqm and minimum clearance of structure from roof level should be 300mm. >Junction Boxes made of GRP / FRP / Power Coated Aluminium with full dust,water & vermin proof . >IR / UV Protected PVC Cables, Pipes and Accessories shall meet IEC 60227 / IS 694, IEC 60502 / IS 1554 standards, Temp. range-10 deg C to +80 deg C . >Cables to be routed in GI cable tray..System Voltage -230 V / 415 V, 50 Hz. >Solar PV array- Min. 250 Wp. >Protective device against Surge. > Rated Out Put Power tolerance +/_ 3%. >Earthing and Lightening protections. >Storage Battery - 12 V , 150 AH. > Nos. of Battery- As per requirements. >Battery Backup-3 Hrs. HOSTEL BUILDING ( GIRLS)
Supplying , installation, testing and Commissioning of OFF-Grid Roof Top Solar PV System as per the MNRE norms and conforming to all rules, regulations, codes, procedures as specified by Central Electricity Authority (CEA),Central Electricity Regulatory Commission(CERC),Assam Electricity Regulatory Commission (AERC) and any other authority related in this regard and all components should conform to the BIS or IEC or international specifications consisting of the following specifications- >Solar PV modules consisting of required number of crystalline PV modules conforming IEC:61215/IS:14286 & IEC:61730 Part-2. >Grid interactive Power Conditioning Unit with Remote Monitoring System.( DC Distribution Board & AC Distribution Board designed for min. ambient Temperature of 45 deg C). >Mounting structure Hot Dip Galvanized to withstand wind pressure 180 Km/hr and total load should be less than 60 Kg /sqm and minimum clearance of structure from roof level should be 300mm. >Junction Boxes made of GRP / FRP / Power Coated Aluminium with full dust,water & vermin proof . >IR / UV Protected PVC Cables, Pipes and Accessories shall meet IEC 60227 / IS 694, IEC 60502 / IS 1554 standards, Temp. range-10 deg C to +80 deg C . >Cables to be routed in GI cable tray..System Voltage -230 V / 415 V, 50 Hz. >Solar PV array- Min. 250 Wp. >Protective device against Surge. > Rated Out Put Power tolerance +/_ 3%. >Earthing and Lightening protections. >Storage Battery - 12 V , 150 AH. > Nos. of Battery- As per requirements. >Battery Backup-3 Hrs. HOSTEL BUILDING ( BOYS INTERN)
Supplying , installation, testing and Commissioning of OFF-Grid Roof Top Solar PV System as per the MNRE norms and conforming to all rules, regulations, codes, procedures as specified by Central Electricity Authority (CEA),Central Electricity Regulatory Commission(CERC),Assam Electricity Regulatory Commission (AERC) and any other authority related in this regard and all components should conform to the BIS or IEC or international specifications consisting of the following specifications- >Solar PV modules consisting of required number of crystalline PV modules conforming IEC:61215/IS:14286 & IEC:61730 Part-2. >Grid interactive Power Conditioning Unit with Remote Monitoring System.( DC Distribution Board & AC Distribution Board designed for min. ambient Temperature of 45 deg C). >Mounting structure Hot Dip Galvanized to withstand wind pressure 180 Km/hr and total load should be less than 60 Kg /sqm and minimum clearance of structure from roof level should be 300mm. >Junction Boxes made of GRP / FRP / Power Coated Aluminium with full dust,water & vermin proof . >IR / UV Protected PVC Cables, Pipes and Accessories shall meet IEC 60227 / IS 694, IEC 60502 / IS 1554 standards, Temp. range-10 deg C to +80 deg C . >Cables to be routed in GI cable tray..System Voltage -230 V / 415 V, 50 Hz. >Solar PV array- Min. 250 Wp. >Protective device against Surge. > Rated Out Put Power tolerance +/_ 3%. >Earthing and Lightening protections. >Storage Battery - 12 V , 150 AH. > Nos. of Battery- As per requirements. >Battery Backup-3 Hrs. HOSTEL BUILDING ( GIRLS INTERN)
Supply, installation & testing of Copper Plate earth station with 600 mmx600 mmx3 mm copper earth plate with necessary 40 mm dia. G.I. medium duty watering pipe with G.I. Fittings such as Socket, Tee, elbow, nipple and 50 mmx40 mm G.I. reducing socket for funnel including locking arrangement with 300 mmx300 mmx6 mm C.I. hinged cover plate complete with digging of earth pit, construction of brick chamber and plastering of both inner & outer surface of wall as specified and directed by the deptt .
Extra for using salt (5 K and Charcoal (96 K in G.I./Copper plate Earth Station pit to provide low impedance ground in location of high soil resistivity as and when required and specified by the deptt .
Supplying & laying of following size G.I. strips drawn on surface from earth electrode to Electrical switch gears, machineries etc complete with supply of G.I. nuts & bolts, screws etc including riveting, soldering & making necessary connection as approved, specified and directed by the deptt.
Supply, fitting & fixing of Lighting Finial Arrestor made of 25 mm dia 300 mm long solid Copper tube having 85 mm dia. single prong at top and 3 mm thick base plate at bottom complete with fitting & fixing with Brass nuts & bolts on roof, RCC slab, top of column etc. as specified and directed by the deptt.
M/S Assam Electric Store
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .