Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.9 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹4.1 L+₹13,200 (3.35%)Rejected-Finance | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | V.BASKARAN L1 | S GIRIJA L2 |
|---|---|---|---|---|---|
| 1.00 | Labour charges for Removal of 10 H.P to 20 H.P submersible pump set and its accessories from bore well for attending repair including disjointing of submersible cable with proper clamps up to the starter and riser pipes to the required depth etc. complete | 7 | No | 7,000 ₹49,000 Lowest | 7,500 ₹52,500 |
| 2.00 | Labour charges for the Re-erection 10 H.P to 20 H.P submersible pump set in bore well including fixing and jointing and submersible cable with proper clamps up to the starter to the required depth and also fixing of riser pipes to the required depth valves erection clamps etc. complete and testing pump sets and trial run for 7 days. | 7 | No | 7,000 ₹49,000 Lowest | 7,500 ₹52,500 |
| 3.00 | Rewinding of above 10HP to 20 HP Submersible motor of 3 phase 440v 50Hz with including removal of materials to be deducted including cost of winding wire, sleeves and rotor reconditioning, motor and rotor core resetting,motor copper cable 3mts,servicing commissioning and testing of submersible motor etc., complete as per directed by the departmental officers.(guarantee period for 3months) | 7 | No | 10,600 ₹74,200 Lowest | 10,800 ₹75,600 |
| 4.00 | Labour charges for Removal of 20 H.P to 30 H.P submersible pump set and its accessories from bore well for attending repair including disjointing of submersible cable with proper clamps up to the starter and riser pipes to the required depth etc. complete | 8 | No | 7,600 ₹60,800 Lowest | 7,800 ₹62,400 |
| 5.00 | Labour charges for the Re-erection 20 H.P to 30 H.P submersible pump set in bore well including fixing and jointing and submersible cable with proper clamps up to the starter to the required depth and also fixing of riser pipes to the required depth valves erection clamps etc. complete and testing pump sets and trial run for 7 days. | 8 | No | 7,600 ₹60,800 Lowest | 7,800 ₹62,400 |
| 6.00 | Rewinding of above 20HP to 30 HP Submersible motor of 3 phase 440v 50Hz with including removalof materials to be deducted including cost of winding wire, sleeves and rotor reconditioning, motor and rotor core resetting,motor copper cable 3mts,servicing commissioning and testing of submersible motor etc., complete as per directed by the departmental officers.(guarantee period for 3months) | 8 | No | 12,500 ₹1,00,000 Lowest | 12,700 ₹1,01,600 |
Tender Value
₹5.0 L
EMD Value
₹4,950
Closing Date
16 Feb 2026, 3:00 pmClosed
COMMISSIONER VADALUR MUNICIPALITY
MUNICIPALITY OFFICE VADALUR
MAINTENANCE OF ELECTRICAL MOTORS IN VADALUR MUNICIPAL WARD 01 TO 14 LIMITS .
2026_MAWS_656315_5
2521/2025/E1
Open Tender
Electrical and Maintenance Works
Works
180 days
VADALUR MUNICIPALITY
Please refer Tender documents.
1 document required · 1 mandatory
₹0
₹4,950
12 Oct 2026
13 Feb 2026
16 Feb 2026
13 Feb 2026
16 Feb 2026
13 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Labour charges for Removal of 10 H.P to 20 H.P submersible pump set and its accessories from bore well for attending repair including disjointing of submersible cable with proper clamps up to the starter and riser pipes to the required depth etc. complete | 7 | No | - | - |
| 2 | Labour charges for the Re-erection 10 H.P to 20 H.P submersible pump set in bore well including fixing and jointing and submersible cable with proper clamps up to the starter to the required depth and also fixing of riser pipes to the required depth valves erection clamps etc. complete and testing pump sets and trial run for 7 days. | 7 | No | - | - |
| 3 | Rewinding of above 10HP to 20 HP Submersible motor of 3 phase 440v 50Hz with including removal of materials to be deducted including cost of winding wire, sleeves and rotor reconditioning, motor and rotor core resetting,motor copper cable 3mts,servicing commissioning and testing of submersible motor etc., complete as per directed by the departmental officers.(guarantee period for 3months) | 7 | No | - | - |
| 4 | Labour charges for Removal of 20 H.P to 30 H.P submersible pump set and its accessories from bore well for attending repair including disjointing of submersible cable with proper clamps up to the starter and riser pipes to the required depth etc. complete | 8 | No | - | - |
| 5 | Labour charges for the Re-erection 20 H.P to 30 H.P submersible pump set in bore well including fixing and jointing and submersible cable with proper clamps up to the starter to the required depth and also fixing of riser pipes to the required depth valves erection clamps etc. complete and testing pump sets and trial run for 7 days. | 8 | No | - | - |
| 6 | Rewinding of above 20HP to 30 HP Submersible motor of 3 phase 440v 50Hz with including removalof materials to be deducted including cost of winding wire, sleeves and rotor reconditioning, motor and rotor core resetting,motor copper cable 3mts,servicing commissioning and testing of submersible motor etc., complete as per directed by the departmental officers.(guarantee period for 3months) | 8 | No | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.08 MB
BOQ_787353.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .