| 1 | L1₹1.0 CrAccepted-AOC | ₹1.0 Cr Quoted ₹85.9 L | L1 | Accepted-AOC As per approval of competent authority for award tender to L1 bidder |
| 2 | L2₹97.7 L+₹11.8 L (13.8%)Rejected-Finance | ₹97.7 L+₹11.8 L (13.8%) | L2 | Rejected-Finance The reasons mentioned in report attached along |
| 3 | L3₹1.0 Cr+₹16.0 L (18.7%)Rejected-Finance | ₹1.0 Cr+₹16.0 L (18.7%) | L3 | Rejected-Finance The reasons mentioned in report attached along |
| 4 | L4₹1.1 Cr+₹27.4 L (31.9%)Rejected-Finance | ₹1.1 Cr+₹27.4 L (31.9%) | L4 | Rejected-Finance The reasons mentioned in report attached along |
| 5 | L5₹1.2 Cr+₹30.1 L (35.1%)Rejected-Finance | ₹1.2 Cr+₹30.1 L (35.1%) | L5 | Rejected-Finance The reasons mentioned in report attached along |
| Sl No | Description | Qty | Unit | R.K GUPTA AND CO. L4 | S KUMAR CREATION PRIVATE LIMITED L7 | DEVESH CONSTRUCTIONS L1 | ALHADIN CONSTRUCTION L5 | M/S VIKAS DUGGAL L3 | ASHOK KUMAR GARG CONTRACTOR L6 | Cee Kay EPC Projects Pvt Ltd L2 |
|---|---|---|---|---|---|---|---|---|---|---|
| 1.00Material Required | ||||||||||
| 1.01 | Galvanized steel poles of tubular in design and swaged of the length 7 meters, with top cap welded and lightning spike and including MUFF | 464 | Nos | 10,200 ₹47,32,800 | 11,201 ₹51,97,264 | 7,700 ₹35,72,800 Lowest | 8,000 ₹37,12,000 | 10,000 ₹46,40,000 | 8,850 ₹41,06,400 | 8,460 ₹39,25,440 |
| 1.02 | Galvanized steel poles of tubular in design and swaged of the length 8 meters, with top cap welded and lightning spike and including MUFF | 116 | Nos | 11,200 ₹12,99,200 | 13,551 ₹15,71,916 | 9,200 ₹10,67,200 Lowest | 9,500 ₹11,02,000 | 16,000 ₹18,56,000 | 11,047 ₹12,81,452 | 9,500 ₹11,02,000 |
| 1.03 | Stay arrangement for 7M/8M steel poles of Galvanised Steel | 116 | Nos | 3,990 ₹4,62,840 | 3,501 ₹4,06,116 | 2,900 ₹3,36,400 | 2,900 ₹3,36,400 | 5,000 ₹5,80,000 | 2,500 ₹2,90,000 Lowest | - |
| 1.04 | Formed OFC Dead End and Termination Fittings including all supporting items. | 203 | Nos | 1,200 ₹2,43,600 Lowest | 1,501 ₹3,04,703 | 1,270 ₹2,57,810 | 2,500 ₹5,07,500 | 4,500 ₹9,13,500 | 1,600 ₹3,24,800 | - |
| 1.05 | OFC suspension fittings including all supporting items. | 522 | Nos | 850 ₹4,43,700 Lowest | 1,001 ₹5,22,522 | 1,000 ₹5,22,000 | 2,000 ₹10,44,000 | 1,000 ₹5,22,000 | 1,600 ₹8,35,200 | - |
| 1.06 | Adjustable Cable Storage Bracket. | 145 | Nos | 550 ₹79,750 Lowest | 902 ₹1,30,790 | 600 ₹87,000 | 1,700 ₹2,46,500 | 4,000 ₹5,80,000 | 1,000 ₹1,45,000 | - |
| 2.00SERVICES REQUIRED | ||||||||||
| 2.01 | Erection of 7 m / 8m poles including excavation, fixing of MUFF, concreting, curing, Backfilling, Reinstatement, Compaction of earth, Stay arrangements etc. and sign writing on poles with paint | 580 | Nos | 3,998 ₹23,18,840 | 3,851 ₹22,33,580 | 2,900 ₹16,82,000 | 3,150 ₹18,27,000 | 1,200 ₹6,96,000 Lowest | 4,000 ₹23,20,000 | 3,860 ₹22,38,800 |
| 2.02 | Slinging / Laying of ADSS / AOF including fixing of installation accessories and fixtures etc. splicing & jointing of OF cable, Link Testing & Acceptance Testing and makeover of route with As Built Diagram (ABD) of installed cost towards collection of ADSS Cable / AOF Cable from BSNL’s Store Depot. | 29 | Km | 50,500 ₹14,64,500 | 55,000 ₹15,95,000 | 29,000 ₹8,41,000 | 90,000 ₹26,10,000 | 7,000 ₹2,03,000 Lowest | 85,000 ₹24,65,000 | 48,000 ₹13,92,000 |
Tender Value
₹1.2 Cr
EMD Value
₹2.5 L
Closing Date
26 Jan 2026, 11:00 amClosed
Chief General Manager BSNL Himachal Pradesh Circle
O/o CGMT BSNL HP, Block no. 11, SDA Complex, Kasumpti, Shimla
Tender for comprehensive construction of ADSS OFC, including Supply and installation of related ADSS OFC accessories, supply and erection of 7m/8m tubular poles along with associated accessories, slinging of ADSS Cable, testing and commissioning
2025_BSNL_260890_1
HPCO-23/11/25/2025-CFA-HPCO
Open Tender
OFC Laying Works
Works
1095 days
Hamirpur BA
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,360
Yes
AO(Claim), O/o CGMT, BSNL HP
₹2.5 L
Yes
24 Jun 2026
30 Dec 2025
27 Jan 2026
5 Jan 2026
26 Jan 2026
5 Jan 2026
5 Jan 2026 - 16 Jan 2026
Material Required
Galvanized steel poles of tubular in design and swaged of the length 7 meters, with top cap welded and lightning spike and including MUFF
Galvanized steel poles of tubular in design and swaged of the length 8 meters, with top cap welded and lightning spike and including MUFF
Stay arrangement for 7M/8M steel poles of Galvanised Steel
Formed OFC Dead End and Termination Fittings including all supporting items.
OFC suspension fittings including all supporting items.
Adjustable Cable Storage Bracket.
SERVICES REQUIRED
Erection of 7 m / 8m poles including excavation, fixing of MUFF, concreting, curing, Backfilling, Reinstatement, Compaction of earth, Stay arrangements etc. and sign writing on poles with paint
Slinging / Laying of ADSS / AOF including fixing of installation accessories and fixtures etc. splicing & jointing of OF cable, Link Testing & Acceptance Testing and makeover of route with As Built Diagram (ABD) of installed cost towards collection of ADSS Cable / AOF Cable from BSNL’s Store Depot.
Construction of Joint Chamber as per EI supply & fixing of G.I. Pipe & PLB pipe for bringing down the of cable, supply of stone slab for covering the chamber and sand for filling the chamber
Installation of FDF and WSC/FTB, leading-in arrangement, jointing of pigtails and other related activity for construction of ADSS/Aerial OFC routes
Quoted Price iro Estimated Cost @
stage.html
html • 0.07 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 12.57 MB
approvedtender29kmHMRrehab.pdf
Tender Documents • 12.55 MB
BOQ_301763.xls
BOQ • 0.28 MB
taxdetailsADSSlaying.pdf
Additional Documents • 0.76 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .