| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹55.4 CrAccepted-AOC KAMAT NAGAR JUNA BAZAR SAWANTWADI DIST SINDHUDURG 416510 | SAWANTWADI | SINDHUDURG | MAHARASHTRA | 416510 | L1 | Accepted-AOC L1 |
Tender Value
₹52.8 Cr
EMD Value
₹26.4 L
Closing Date
4 Sept 2024, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SUPERINTENDING ENGINEER
Superintending Engineer Pradhan Mantri Gram Sadak Yojana Konkan Region,PWD COMPOUND, Thane-WEST
RD-SIN-A270
2024_MMGSY_1077435_2
MMGSY/Sindhudurg/TWT/21/24-25 2nd call
Open Tender
Civil Works - Roads
Percentage
730 days
SAWANTWADI, DODAMARG, VENGURLA
Please refer Tender documents.
8 documents required · 8 mandatory
₹29,500
₹26.4 L
Yes
17 Oct 2024
29 Aug 2024
5 Sept 2024
29 Aug 2024
4 Sept 2024
29 Aug 2024
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | 1.00 Upgradation & Maintenance of Road From Banda To Wafoli Road. Km. 0.500 to 4.760 Km. Tal-Sawantwadi, Dist -Sindhudurg. | - | - | - | - |
| - | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Mord 2014 Clause 201. (A) In area of Non-thorny jungle | 1.02 | One Hectere | 29,183.9 | ₹29,837.62 |
| - | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Mord 2014 Clause 201. (B) In area of thorny jungle | 0.68 | One Hectere | 36,276.55 | ₹24,726.1 |
| - | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and croun-sections, and transporting to the embankment location with a lift upto 1.5 m and lead above 1000 m as per Technical Specification MORD 2014 Clause 302.3 | 8,113.2 | One Cubic meter | 81.35 | ₹6,60,008.82 |
| - | Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, transporting to embankment site with a lift upto 1.5 m and lead above 1000 m, trimming bottom and side slopes in accordance with requirements of lines, grades and croun-sections as per Technical Specification MORD 2014 Clause 302.3.5 | 1,427 | One Cubic meter | 119.55 | ₹1,70,597.85 |
| - | Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and croun-sections, loading and disposal of cut rock with a lift upto 1.5 m and with all leads as per Technical Specification MORD 2014 Clause 302.3.5 | 238 | One Cubic meter | 98.95 | ₹23,550.1 |
| - | Excavation in Hard Rock (blasting Prohibited) -Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal with a lift upto 1.5 metre and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross- sections as per Technical Specification Clause 302.3.5 | 1,031 | One Cubic meter | 512.25 | ₹5,28,129.75 |
| - | Excavation in Hard Rock (Controlled Blasting) -Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal with a lift upto 1.5 metre and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross- sections as per Technical Specification Clause 302.3.5 | 79 | One Cubic meter | 194 | ₹15,326 |
| - | Loosening, Levelling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Tables 300.1 and 300.2 for embankment construction as per Technical Specification Clause 301.4.1. | 135 | One Cubic meter | 36.2 | ₹4,887 |
| - | Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 | 4,091.3 | One Cubic meter | 92.25 | ₹3,77,422.43 |
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
BOQ_1880383.xls
BOQ • 0.77 MB
151175202.pdf
Tender Documents • 0.06 MB
151175204.html
Tender Documents • 0.06 MB
RD-SIN-A270.pdf
Tender Documents • 1.23 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .