| 1 | 1₹27.3 LAccepted-AOC NO 123 1ST STREET URC NAGAR CHINNA SENGODAMPALAYAM ERODE DISTRICT 638 012 | CHINNA SENGODAMPALAYAM | ERODE | TAMIL NADU | 638012 | 1 | Accepted-AOC ACCEPTED | |
| 2 | 2₹29.2 L+₹1.9 L (6.85%)Rejected-AOC 16 5 KUMARASAMY STREET KALAIMAGAL SCHOOL ROAD ERODE | 2 | Rejected-AOC REJECTED |
Tender Value
₹3.3 Cr
EMD Value
₹33,000
Closing Date
14 Dec 2023, 3:00 pmClosed
COMMISSIONER TIRUNELVELI CORPORATION
S.N.High road Main office Tirunelveli Corproration
Construction of Compound wall at Knowledge center in ward no30
2023_MAWS_394869_1
42/2023-24/7
Open Tender
Civil Works
Works
90 days
S.N.High road Main office Tirunelveli Corproration
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹33,000
20 Aug 2024
1 Dec 2023
15 Dec 2023
1 Dec 2023
14 Dec 2023
1 Dec 2023
Amount
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum
Supplying and filling in foundation and basement with filling sand in layers of not more than 15cm.thick well rammed watered and compacted etc., complete complying with standard specification.
Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification
Boring, Providing and installing Cast in situ single under Reamed Pile of specified diameter and length below the pile cap in cement concrete 1:1:2 (1 cement, 1 Coarse sand & 2 graded stone aggregate of 20 mm nominal size) to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including Bentonite solution machinery charges labour chargers etc., all complete.
Installation charges inclusive of transportation to site and the bored pile equipment employed for the works including setting of pile driving equipment with all accessories and tools at each of the pile location based on the sequence of operation approved by the departmental engineers irrespective of the location and distance involved in movement of pile driving equipment etc.
Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oak joists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid)
Suppling and fabricating and placing in position MS (or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors.
Supplying and erecting steel centering including necessary supports for plane surface
For Rectangular and square column
Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of sand, but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requiremnents of IS staandards. (No separate payment will be made by the Department for the excess usage of materials)
Foundation and Basement
Brick work in CM 1:5 (one cement & five sand) using II class ground moulded bricks of size 9"X43/8"X 2 3/4" including finishing, curing, etc., complete complying with standard specification.
ground Floor
Plastering with cement mortar (1:5) 12mm ,thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications (S.I.306)
Stucco Plastering 12 mm thick using blue granite chips of size 10 mm and below over a base plastering with cement mortar 1:5 (One part of Cement and Five part of Plastering Sand (P- Sand)), 12mm thick,including cost and conveyance of all materials to site etc,complete as per standard specification.
Supply and fixing of M.S Grills with Doors and Windows with one coat of Red oxide with Primer including all costs such as welding,grinding and fabrication charges, cost and conveyance of all materials to site etc,complete as per standard specification.
Painting two coats with Ready Mixed Enamel Paint over the new iron works of approved quality and colour without priming coat including the cost all materials etc.,complete, in all floors
Painting two coats with ready mixed Plastic Emulsion Paint approved quality and colour over a priming coat, including thorough scrapping, clean removal of dirt, etc complete and including necessary plaster of paris, putty, wherever required etc, complete as per standard specification.
vivek vijay and company
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .