Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
Refer Docs
EMD Value
₹7,600
Closing Date
26 Oct 2026, 2:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
CE/MTPS-II
O/o CE MTPS II
Cleaning of accumulated Ash inside pent house and water washing inside boiler 2nd pass an slope area removing of Ash at Economizer slope duct patch welding in eroded portion Economizer slope applying new refractory in required area
2026_EB_712871_1
OT 17 Cleaning of accumulated Ash inside pent house
Open Tender
Maintenance Works
Works
30 days
SE/M-I/MTPS-II
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹7,600
Yes
12 Oct 2026
12 Oct 2026
27 Oct 2026
12 Oct 2026
26 Oct 2026
12 Oct 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Removal of accumulated ash inside pent house through manhole door and scrapping of sticking ash from boiler tube top surfaces of skin casing, boiler tube header surfaces using scrapping plates and wire brushes, etc, inside the highly ash polluted and unapproachable in pent house area and the ash transporting to ‘0’m from respective elevations by using pulley arrangements including cost of consumables, hire charges for T&P’s, etc., | 10 | MT | - | - |
| 2 | Transportation of ash & dumping the ash into MTPS Ash dyke. | 10 | MT | - | - |
| 3 | Cleaning of boiler in 2nd pass & inter pass area such that LTSH, LTRH, Economizer tubes of upper & lower bank each sides, Final Reheater and inter pass slope area by water washing, including of transportation of fire fighting hoses, nozzles, valves and other materials from Fire fighting office to site at various location and fitting to the site hydrant points at various elevations and returning back to Fire fighting office after completion of work | 1 | Operation | - | - |
| 4 | Removal of Ash in Economizer slope duct (21m x 12m) at boiler second pass with highest level of Safety provision like life line safety belt, tools etc | 1 | Time | - | - |
| 5 | Arrangement of platform and scaffolding materials and erection of the same wherever required in Economizer slope area for inspection of eroded portion, patch welding to avoid air-ingress & accumulation ash into insulation. | 20 | Nos | - | - |
| 6 | Patch welding works in the worn out portion economizer slope area to aviod air-ingress & accumulation of ash into insulation.(Reheater & Superheater side) | 200 | RM | - | - |
| 7 | Removal of insulation double layer (60mm + 60mm = 120mm thick) for replace the defective thermocouples inside pent house and refixing after completion of rectification works & insulation if required bringing from stores. | 50 | m2 | - | - |
| 8 | Transporting the refractory from MTPS-II central store to boiler "0" mtr, leading and lifting to the required area of pent house by providing chain block, pulley and rope. | 3,000 | kg | - | - |
| 9 | Removing of old refractory inside pent house area and bringing to ‘0’m, including cost of all consumables, tools and plants etc., | 3,000 | kg | - | - |
| 10 | Providing shuttering for refractory and applying new refractory in the required area of platen header room including consumables and hire charges for T&Ps. | 3,000 | kg | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.73 MB
BOQ_856283.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .