| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹20.5 LAccepted-AOC | ₹20.5 L Quoted ₹22.2 L | L1 | Accepted-AOC Work was Awarded |
| 2 | L2₹23.3 LRejected-AOC 4 A 39 2 MACHADO NAGAR OPP APC COLLEGE TUTICORIN 2 | TUTICORIN | TAMIL NADU | 626202 | ₹23.3 L | L2 | Rejected-AOC Work was Not Awarded |
| Sl No | Description | Qty | Unit | Phoenix Engineering Enterprises L1 | ABR ENGINEERS L2 |
|---|---|---|---|---|---|
| 1.00 | Charges for rack out the L.T modules from the panel –Removing from its position –Removal of coal dust deposited over all electrical components such as power contactors, auxiliary contactors , fuse switch , control fuse holders, CT ammeter, selector switch , indicating lamp holders control transformer , power and control wiring and etc., by using blower / vacuum cleaner / cleaning brush. Removing the power contactors arc chute, auxiliary contactor top cover and cleaning the carbon deposition over the fixed and moving contacts by using good quality electrical contact cleaner (molykote) Tightness checking of all bolts and nuts, of power and control wiring with components. Reassembling the contactor arc chute and top covers in the respective places – After completion of work check the IR values of wirings and racked in the L.T modules to the panel and put into service position and check the operating condition of the module. Including assistance for shift operator round the clock in shift duty in the locations 6.6kV Switch Gear of Unit III.. (Incl T&P and consumables)
a) Size 3modules 30KW and above (Total 34 nos.) | 34 | Nos | 85,000 ₹1.0 L | 88,400 ₹1.0 L |
| 2.00 | Charges for rack out the L.T modules from the panel –Removing from its position –Removal of coal dust deposited over all electrical components such as power contactors, auxiliary contactors , fuse switch , control fuse holders, CT ammeter, selector switch , indicating lamp holders control transformer , power and control wiring and etc., by using blower / vacuum cleaner / cleaning brush. Removing the power contactors arc chute, auxiliary contactor top cover and cleaning the carbon deposition over the fixed and moving contacts by using good quality electrical contact cleaner (molykote) Tightness checking of all bolts and nuts, of power and control wiring with components. Reassembling the contactor arc chute and top covers in the respective places – After completion of work check the IR values of wirings and racked in the L.T modules to the panel and put into service position and check the operating condition of the module. Including assistance for shift operator round the clock in shift duty in the locations 6.6kV Switch Gear of Unit III.. (Incl T&P and consumables)
b) Size 2 modules 10KW to 29KW (Total 227 nos.) | 227 | Nos | 2,83,750 ₹3.3 L | 3,00,775 ₹3.5 L |
| 3.00 | Charges for rack out the L.T modules from the panel –Removing from its position –Removal of coal dust deposited over all electrical components such as power contactors, auxiliary contactors , fuse switch , control fuse holders, CT ammeter, selector switch , indicating lamp holders control transformer , power and control wiring and etc., by using blower / vacuum cleaner / cleaning brush. Removing the power contactors arc chute, auxiliary contactor top cover and cleaning the carbon deposition over the fixed and moving contacts by using good quality electrical contact cleaner (molykote) Tightness checking of all bolts and nuts, of power and control wiring with components. Reassembling the contactor arc chute and top covers in the respective places – After completion of work check the IR values of wirings and racked in the L.T modules to the panel and put into service position and check the operating condition of the module. Including assistance for shift operator round the clock in shift duty in the locations 6.6kV Switch Gear of Unit III.. (Incl T&P and consumables)
c) Size 1 modules Switch fuse type (Total 121 nos.) | 121 | Nos | 86,515 ₹1.0 L | 91,960 ₹1.1 L |
| 4.00 | Charges for Recording the parameters of running LT/HT equipments like Voltage, Current, Watt, Oil level checking, recording the parameters & healthiness of stand by LT/HT equipments. | 600 | Nos | 9,39,600 ₹11.1 L | 9,81,000 ₹11.6 L |
| 5.00 | Complete Servicing of 6.6 KV Alind make MOCB in Uniit III | 24 | Nos | 8,20,800 ₹9.7 L | 8,71,200 ₹10.3 L |
Tender Value
Refer Docs
EMD Value
₹17,000
Closing Date
31 Dec 2025, 2:00 pmClosed
CE/TTPS
Chief Engineer Tuticorin Thermal Power Station-Tuticorin
TTPS ES Circle EM I Complete cleaning and tightness checking to enrich the healthiness of the modules and LT HT breakers Daily checking and Recording the parameters of LT modules at LT SWGR and Daily checking and Recording the parameters of HT breake
2025_EB_633140_1
CE/SE/ES/TTPS/43/2026-27
Open Tender
Electrical and Maintenance Works
365 days
TTPS
As per BQR conditions in NIT
7 documents required · 7 mandatory
₹0
₹17,000
Yes
23 Mar 2026
16 Dec 2025
2 Jan 2026
16 Dec 2025
31 Dec 2025
16 Dec 2025
Charges for Recording the parameters of running LT/HT equipments like Voltage, Current, Watt, Oil level checking, recording the parameters & healthiness of stand by LT/HT equipments.
Complete Servicing of 6.6 KV Alind make MOCB in Uniit III
ABR ENGINEERS (BID ID -1550071)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.27 MB
BOQ_757467.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid