| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹12.1 LAccepted-AOC | L-1 | Accepted-AOC Lowest Bidder | |
| 2 | L-2₹15.5 L+₹3.5 L (28.6%)Rejected-Finance 1ST FLOOR SHOP NO 11 MORI GATE RAJINDER MARKET NEW DELHI DELHI 110006 INDIA | NORTH | DELHI | 110006 | L-2 | Rejected-Finance Lowest-2 |
| Sl No | Description | Qty | Unit | R.V. ELECTRICAL ENTERPRISES PVT. LTD. L2 | OM TRADERS L1 |
|---|---|---|---|---|---|
| 1.00 | Operator for operation and Maintenance
Operator/Electrican (Specially for HT equipment and HT Line Expert)-01 Number per month
(Electrician/Mechanic) for one shift (9am -5pm ) or as per direction of Engineer-in-charge. | 12 | for one year | 42,755 ₹5,13,060 | 20,800 ₹2,49,600 Lowest |
| 2.00 | HT Panel-1 (Existing HT Panel of Sub-station-1)
H.T. PANEL & H.T. LINE: 03 Numbers per month
i) The panel shall be maintained as per the frequency indicated below. Shut down in prescribed proforma must be taken before attending to this panel. Solid earthing must be done after making the busbars dead. Only licensed and registered Technician / Supervisor will be allowed to attend to H.T. System.
ii) For panel, insulation test for phase to phase and phase to earth with 5000 v meggar are to be carried out once in a year and to furnish certificate.
ii) To check overheating & Temperature rise once in month. | 36 | for one year | 8,859 ₹3,18,924 | 3,500 ₹1,26,000 Lowest |
| 3.00 | TRANSFORMER 750 to 1600 KVA DRY TYPE CAST RESIN TRANSFORMERS 11KV /433V: 10 Numbders per month
i) Dehydration and filtration of dirty transformer oil for transformer with dehydration filter machine.
ii) Supply and topping of transformer oil in conservator tank and including replacement of dirty silica gel in 5 transformers.
iii) Various connections of the transformer e.g. L.T. Connection neutral & Body – earthing are to be checked once in three months and if found loose is to be tightened.
iv) Bushings are to be examined for crack and dirt deposit and are to be cleaned or replaced as necessary once in three months.
v) Checking of neutral earth and equipment body earth once in a year.
vi) Insulation testing of the following once in three months.
a) Between L.T. and Earth with 1000 v meggar
b) Between H.T. and Earth with 5000 v meggar
c) Between H.T. and L.T winding with 5000 v meggar
vii) To check noise /humming sound & temperature rise (over heating) once in three month.
vii) General cleaning of transformer to keep if free from dust and soot’s once in three month.
ix) The Agency is liable to furnish certificate regarding c & d above. | 120 | for one year | 2,395 ₹2,87,400 Lowest | 3,050 ₹3,66,000 |
| 4.00 | L.T. PANEL & L.T. LINE: 03 Numbers per month
Main LT panel, cubicle type, made out of 14 swg CRCA sheet steel, totally enclosed, IP 54 protection, free standing, floor mounting, dust and vermin proof, indoor, compartmentalised in type 4B execution; powder coated painting suitable for operation on 3 Phase and neutral, 415V, 50 Hz AC supply system with busbars extensible on both sides, interconnections with suitable size of copper lead/ solid aluminium strips, control circuit with breaker control switch & auto/ manual selector switch, ammeter, ammeter selector switches voltmeter, voltmeter selector switches, indicating lamps CT's, all incoming & outgoing feeders with true rms value sensing class 0.5 multifunction power cum energy meters with ports & wired out, interlocking and having following incomer & Bus coupler Air circuit breakers and outgoing Air circuit breaker/ Moulded case circuit breaker complete with releases for protection of all supply & installation complete with 3 Sets (1 Sets included incommer, bus-coupler & Outgoing ACB&MCCB) of Inating lamps LED type, for breaker RYB "ON", "OFF", "TRIP" indication with HRC control fuses. 1 Lot of control wiring.1 Set of designation plates. | 36 | for one year | 5,300 ₹1,90,800 | 2,850 ₹1,02,600 Lowest |
| 5.00 | Automatic control panel with capacitor : 03 Numbers per month
i) Supplying, fixing and Replacement of defective shunt capacitor 25 kvar/5kvar installed in 200 kvar shunt capacitor bank
ii) Repair & maintenance of 180 KVAR 3 phase LT power factor control capacitor panel of 500KVA 11KV/415Volt distribution transformer including the cost of following items:-
iii) Repair & maintenance of 180 KVAR 3 phase LT power factor control capacitor panel of 500KVA 11KV/415Volt distribution transformer including the cost of following items:-
iv) Power factor digital meter of AE/L&T make.
v) A set of LED lamps (3 Nos.) phase indicating lamp of L & T make
vi) 3 phase dry capacitor of simens /Naptune make (totaled 180 KVAR) matching from 1 KVAR to 20 KVAR
vii) Required capacity 3 phase. Contactor independent for each capacitor of L&T /Siemen / INDO-ASIAN make.
viii) Required capacity 3 Pole MCB independent for each contactor Make- L&T/Schneider / INDO -ASIAN
ix) AVF digital meter 3 phase Make-L&T
x) 1 number of CT VA 5 burden and accuracy class -1 having rating of 500/5-5 amp. For M meter and relay Make- AE & Concord Page 3 of 7 Sign of Contractor with stamp Director indication LED Lamps 220 volts for ON indicator of respective capacitor of L&T make.
xi) Automatic / manual off operation selector switch of respective capacitor Make- L&T.
xii) The panel should be complete with all internal wiring with PVC copper conductor wire, internal connection etc., with all labour and material required to complete the job in all respect. | 36 | for one year | 5,241 ₹1,88,676 | 3,000 ₹1,08,000 Lowest |
| 6.00 | Distribution PANEL : 02 Numbers per month
distribution panel, cubicle type, made out of 14 swg CRCA sheet steel, totally enclosed, IP 54 protection, free standing, floor mounting, dust and vermin proof, indoor, compartmentalised in type 4B execution; powder coated painting suitable for operation on 3 Phase and neutral, 415V, 50 Hz AC supply system with busbars extensible on both sides, interconnections with suitable size of copper lead/ solid aluminium strips, control circuit with breaker control switch & auto/ manual selector switch, ammeter, ammeter selector switches voltmeter, voltmeter selector switches, indicating lamps CT's, all incoming & outgoing feeders with true rms value sensing class 0.5 multifunction power cum energy meters with ports & wired out, interlocking and having following incomer & Bus coupler Air circuit breakers and outgoing Air circuit breaker/ Moulded case circuit breaker complete with releases for protection of all supply & installation complete with 3 Sets (1 Sets included incommer, bus-coupler & Outgoing ACB&MCCB) of Indicating lamps LED type, for breaker RYB "ON", "OFF", "TRIP" indication with HRC control fuses. 1 Lot of control wiring.1 Set of designation plates. | 24 | for one year | 1,057 ₹25,368 Lowest | 1,500 ₹36,000 |
| 7.00 | Feeder Pillar : 12 Numbers per month
Feeder pillar, cubicle type, made out of 14 swg CRCA sheet steel, totally enclosed, IP 54 protection, free standing, floor mounting, dust and vermin proof, indoor, compartmentalised in type 4B execution; powder coated painting suitable for operation on 3 Phase and neutral, 415V, 50 Hz AC supply system with busbars extensible on both sides, interconnections with suitable size of copper lead/ solid aluminium strips, control circuit with breaker control switch & auto/ manual selector switch, ammeter, ammeter selector switches voltmeter, voltmeter selector switches, indicating lamps CT's, all incoming & outgoing feeders with true rms value sensing class 0.5 multifunction power cum energy meters with ports & wired out, interlocking and having following incomer & Bus coupler of all supply & installation complete with 3 Sets (1 Sets included incommer, bus-coupler & Outgoing ACB&MCCB) of Indicating lamps LED type, for breaker RYB "ON", "OFF", "TRIP" indication with HRC control fuses. 1 Lot of control wiring.1 Set of designation plates. | 144 | for one year | 211 ₹30,384 Lowest | 1,535 ₹2,21,040 |
| 8.00NOTE:- A) Bidder may quote the rate for item. L1 will be decided based on the lowest rates quoted by bidders for total items. B) AMC charges shall be inclusive of all taxes, duties, charges etc. C) The contractor shall pay the personnel deployed in USER/CLIENT premises, their wages in accordance with the Minimum Wages Act, 1948 (amended time to time). D) All items to be used in this work should be genuine spare parts of OEM. In case of any discrepancy decision of Engineer-in-charge shall be final and abiding. | |||||
Tender Value
Refer Docs
EMD Value
₹33,420
Closing Date
8 Jul 2025, 4:00 pmClosed
DIG (Engineer) Dte. CRPF
Works Directorate, CRPF, Level-III, East Block-7, RK Puram, Sector-1, New Delhi-110066
Annual Maintenance Contract for High Tension Electrical Equipment (Electrical Substation-3 Nos Included HT and LT Panel Switches, Breakers, Command and Control System, Communication Network) installed at GC, CRPF Greater Noida (for One Year)
2025_CRPF_865973_1
B.V(GCNDA)25-WksDte-CCellNIT63
Open Tender
Electrical Works
Works
365 days
GC CRPF GREATER NOIDA DADRI ROAD, GB NAGAR -UP
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹33,420
28 Aug 2025
25 Jun 2025
9 Jul 2025
25 Jun 2025
8 Jul 2025
25 Jun 2025
25 Jun 2025 - 30 Jun 2025
Amount
Operator for operation and Maintenance Operator/Electrican (Specially for HT equipment and HT Line Expert)-01 Number per month (Electrician/Mechanic) for one shift (9am -5pm ) or as per direction of Engineer-in-charge.
HT Panel-1 (Existing HT Panel of Sub-station-1) H.T. PANEL & H.T. LINE: 03 Numbers per month i) The panel shall be maintained as per the frequency indicated below. Shut down in prescribed proforma must be taken before attending to this panel. Solid earthing must be done after making the busbars dead. Only licensed and registered Technician / Supervisor will be allowed to attend to H.T. System. ii) For panel, insulation test for phase to phase and phase to earth with 5000 v meggar are to be carried out once in a year and to furnish certificate. ii) To check overheating & Temperature rise once in month.
TRANSFORMER 750 to 1600 KVA DRY TYPE CAST RESIN TRANSFORMERS 11KV /433V: 10 Numbders per month i) Dehydration and filtration of dirty transformer oil for transformer with dehydration filter machine. ii) Supply and topping of transformer oil in conservator tank and including replacement of dirty silica gel in 5 transformers. iii) Various connections of the transformer e.g. L.T. Connection neutral & Body – earthing are to be checked once in three months and if found loose is to be tightened. iv) Bushings are to be examined for crack and dirt deposit and are to be cleaned or replaced as necessary once in three months. v) Checking of neutral earth and equipment body earth once in a year. vi) Insulation testing of the following once in three months. a) Between L.T. and Earth with 1000 v meggar b) Between H.T. and Earth with 5000 v meggar c) Between H.T. and L.T winding with 5000 v meggar vii) To check noise /humming sound & temperature rise (over heating) once in three month. vii) General cleaning of transformer to keep if free from dust and soot’s once in three month. ix) The Agency is liable to furnish certificate regarding c & d above.
NOTE:- A) Bidder may quote the rate for item. L1 will be decided based on the lowest rates quoted by bidders for total items. B) AMC charges shall be inclusive of all taxes, duties, charges etc. C) The contractor shall pay the personnel deployed in USER/CLIENT premises, their wages in accordance with the Minimum Wages Act, 1948 (amended time to time). D) All items to be used in this work should be genuine spare parts of OEM. In case of any discrepancy decision of Engineer-in-charge shall be final and abiding.
R.V. ELECTRICAL ENTERPRISES PVT. LTD. (BID ID -3245232)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .