Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹15.3 LAdmitted-Finance | ₹15.3 L | L1 | Admitted-Finance |
| 2 | L2₹32.3 L+₹17.0 L (111.4%)Admitted-Finance F 33 3 OKHLA INDUSTRIAL AREA PHASE 2 DELHI 110020 | SOUTH | DELHI | 110020 | ₹32.3 L+₹17.0 L (111.4%) | L2 | Admitted-Finance |
| 3 | L3₹58.1 L+₹42.8 L (280.1%)Admitted-Finance | ₹58.1 L+₹42.8 L (280.1%) | L3 | Admitted-Finance |
| 4 | L4₹1.1 Cr+₹97.1 L (634.7%)Admitted-Finance | ₹1.1 Cr+₹97.1 L (634.7%) | L4 | Admitted-Finance |
| 5 | L5₹1.6 Cr+₹1.4 Cr (921.8%)Admitted-Finance | ₹1.6 Cr+₹1.4 Cr (921.8%) | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | DSD INFRATECH MANAGEMENT PVT.LTD L1 | Spectrum Techno Consultants Pvt Ltd L5 | Almondz Global Infra Consultant Limited L2 | Infra Design Studio Pvt Ltd L3 | Dalwankar Projects OPC Pvt Ltd L4 |
|---|---|---|---|---|---|---|---|---|
| 1.10Key Personnel | ||||||||
| 1.11 | Team Leader cum Senior Highway Engineer | 10 | Month | 30,000 ₹3,00,000 | 1,20,000 ₹12,00,000 | 20,000 ₹2,00,000 Lowest | 35,000 ₹3,50,000 | 30,000 ₹3,00,000 |
| 1.12 | Senior Bridge Engineer | 10 | Month | 9,000 ₹90,000 Lowest | 1,20,000 ₹12,00,000 | 20,000 ₹2,00,000 | 30,000 ₹3,00,000 | 25,000 ₹2,50,000 |
| 1.13 | Highway cum Pavement Engineer | 10 | Month | 8,000 ₹80,000 Lowest | 1,00,000 ₹10,00,000 | 20,000 ₹2,00,000 | 25,000 ₹2,50,000 | 15,000 ₹1,50,000 |
| 1.14 | Material-cum-Geotechnical Engineer- Geologist | 10 | Month | 8,000 ₹80,000 Lowest | 1,00,000 ₹10,00,000 | 20,000 ₹2,00,000 | 20,000 ₹2,00,000 | 15,000 ₹1,50,000 |
| 1.15 | Senior Survey Engineer | 10 | Month | 4,000 ₹40,000 Lowest | 70,000 ₹7,00,000 | 10,000 ₹1,00,000 | 20,000 ₹2,00,000 | 15,000 ₹1,50,000 |
| 1.16 | Traffic and Safety Expert | 6 | Month | 6,000 ₹36,000 Lowest | 80,000 ₹4,80,000 | 10,000 ₹60,000 | 25,000 ₹1,50,000 | 15,000 ₹90,000 |
| 1.17 | Environmental Specialist | 6 | Month | 4,000 ₹24,000 Lowest | 50,000 ₹3,00,000 | 10,000 ₹60,000 | 20,000 ₹1,20,000 | 10,000 ₹60,000 |
| 1.18 | Quantity Surveyor/ Documentation Expert | 10 | Month | 3,000 ₹30,000 Lowest | 50,000 ₹5,00,000 | 10,000 ₹1,00,000 | 25,000 ₹2,50,000 | 10,000 ₹1,00,000 |
| 1.19 | Land Acquisition Expert | 10 | Month | 3,000 ₹30,000 Lowest | 30,000 ₹3,00,000 | 8,000 ₹80,000 | 20,000 ₹2,00,000 | 10,000 ₹1,00,000 |
Tender Value
Refer Docs
EMD Value
₹2 L
Closing Date
4 Aug 2023, 6:00 pmClosed
Executive Engineer NH Division Gadchiroli
Executive Engineer NH Division Gadchiroli
Consultancy services for the preparation of Feasibility studies and Detailed project report for the work of Construction of Major Bridge with Approaches (Alongwith Land Acquisition) Total Length 3.90 Km across Wainganga River near Hardoli village o
2023_MoRTH_758303_1
NIT02/EENH/GAD/2023-24
Open Tender
Civil Works
EPC Contract
300 days
Bramhapuri
Please refer Tender documents.
3 documents required · 3 mandatory
₹5,900
Bharatkosh and GST Paid under RCM
₹2 L
Yes
16 Feb 2024
19 Jun 2023
7 Aug 2023
19 Jun 2023
4 Aug 2023
19 Jun 2023
Amount
Key Personnel
Team Leader cum Senior Highway Engineer
Senior Bridge Engineer
Highway cum Pavement Engineer
Material-cum-Geotechnical Engineer- Geologist
Senior Survey Engineer
Traffic and Safety Expert
Environmental Specialist
Quantity Surveyor/ Documentation Expert
Land Acquisition Expert
Utility Expert
B: Sub Professional Staff (To be assessed by Consultant as per requirement of assignment and one sub-professional be a fresh graduate)
To be filled by Consultant
To be filled by Consultant
To be filled by Consultant
To be filled by Consultant
To be filled by Consultant
To be filled by Consultant
To be filled by Consultant
Support Staff
Office Manager
Typist
Office Boy
Night Watchman
The vehicles provided by the Consultants shall include the cost for rental, drivers, operation, maintenance, repairs, insurance, etc. A. For use of consultants
Duty Travel to Site (Fixed Costs)
Office Rent (Fixed Costs) The rent cost includes maintenance, Cleaning, repairs, etc.
VI. Office Supplies, Utilities and Communication ( Fixed Costs )
Office Supplies Drafting
Supplies computer
Running Costs
Domestic and International Communication
Office Furniture and Equipment ( Rental )
Office Furniture and Equipment
VIII.Reports and Document Printing
Monthly Report (3 per month)
Inception Report & QAP
Environment and Social Impact Screening Report
Draft Feasibility Report
Final Feasibility Report
Strip Plan with L.A. Reports
Draft LA and Clearances I Report
Final LA and Clearances I Report
Draft Environmental Assessment report & RAP
Final Environmental Assessment report & RAP
Draft Detailed Design Report & Drawings etc.
Draft EMP
Draft Bidding Documents
Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings ,etc
Final EMP
Final Bidding Documents
Draft 3(a) ,3(A) and 3(D) notification for land acquisition ( 3 copies each)
LA & Clearances II Report
IX Survey and Investigation
Topographic Survey including hire charges for equipment and supply of survey Teams comprising of project survey field staff etc. inclusive of cost of materials , labourer.
Detailed topographic surveys using Air Borne Tomography and Air Borne LiDAR Technology
B. Investigation (Fixed cost)
Road and Bridge Inventory
FWD Test and Pavement Evaluation
Roughness Survey
Axle Load Survey
Material Survey and Investigation
Sub-grade Investigation
Traffic Survey
Socio-economic & Census Survey/ Studies
Land Acquisition Studies
Any other investigations/surveys
C. NET WORK SURVEY AND GPR
Net work Survey of the existing Highways as a responsitory for civil work as per direction from Authority
GPR Survey for detection of under ground utilities
Cost of supply and fixing boundary pillars
Procuring and fixing boundary pillars and its installation, complete in all respect as per IRC:25,1967:Wherever the proposed alignment follows the existing alignment, the boundary pillars shall be fixed at an interval of 200m on either side of proposed Right of Way. Wherever there is a proposal of realignment of the existing Highway and/or construction of New Bypasses, Consultant shall fix boundary pillars along the proposed alignment on the extreme boundary on either side of the project Highway at 50 m interval. (lumpsum )
Land acquisition Team including support staff and logistics/transportation
Ex-Land revenue inspector/officer or equivalent
EX-kanoogo/Girdwar or equivalent
Ex-Patwari or equivalent
typist
Logistic for Land Acquisition Team
computer including necessary peripherals
printers
Vehicles(Bolero or equivalent )with monthly running limit of 4000 km
Estimate of Cost for Expatriate Consultants (INR) Remuneration of Exptriate staff including per diem allowances
Staff 1
Staff 2
Staff 3
Staff 4
Staff 5
Staff 6
International Airfares (Fixed Cost) Mobilization and Demobilization
Position 1
Position 2
Position 3
Position 4
Inland Travel in Home Country (Fixed Costs)
Airlines
Other Miscellaneous expenses (like DA, internal travel expenses other incidentals)
Income Tax (Expariate)( as per prevaling Norms)
Other Taxes / Duties (if any) Specify clearly
Goods & Service Tax( as per prevaling Norms)
Almondz Global Infra Consultant Limited
Infra Design Studio Pvt Ltd
Dalwankar Projects OPC Pvt Ltd
Spectrum Techno Consultants Pvt Ltd
stage.html
html • 0.03 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .