| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 2₹3.3 LAccepted-AOC 36 151 E 25 PERIYAR NAGAR THANGAMAPURIPATTINAM METTUR DAM 02 | SALEM | TAMIL NADU | 621011 | ₹3.3 L Quoted ₹2.9 L | 2 | Accepted-AOC L1 |
| 2 | 1₹2.8 LRejected-AOC 36 151 E 73 PERIYAR NAGAR THANGAMAPURIPATTINAM METTUR DAM 02 | ₹2.8 L | 1 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | TAM AND CO L2 | SRI VAITHEESWARA CONSTRUCTIONS L1 |
|---|---|---|---|---|---|
| 1.00 | Decoupling the pump, disconnection of the pump from suction and discharge pipe flanges, draining the lub oil from the sump. | 2 | Nos | 4,500 ₹9,000 | 4,465 ₹8,930 |
| 2.00 | Dismantling of the Bearing Covers, Bearing Bracket, Dismantling of shaft sleeve and dismantling of the casing etc., | 2 | Nos | 7,700 ₹15,400 | 7,666 ₹15,332 |
| 3.00 | Dismantling the impeller Assembly from the Casing, Inspection and reconditioning the eroded portions of the casings if required, Inspection, Checking measurements and tolerances of the impeller, shaft, impeller wearing ring, casing ring and neck ring and replace all the above if necessary including machining of the wearing rings to the required size and assembling with the impeller suitably | 2 | Nos | 7,700 ₹15,400 | 7,671 ₹15,342 |
| 4.00 | Reassembling and positioning of the rotor assembly and closing of casing cover, reassembling the sleeve, Bearing Bracket Bearings, Bearing Covers and assembling the coupling in shaft | 2 | Nos | 7,700 ₹15,400 | 7,666 ₹15,332 |
| 5.00 | Checking and correcting the pump alignment with motor and connecting of pump flanges with renewed gaskets. Inspection of couplings, Coupling the pump with motor, connecting the pump from suction and discharge pipe flanges, and other such works required for efficient operation of the pump and commissioning. Cleaning & painting the complete pump assembly & Base structure, Painting inside the pump casings, and painting of the pump base concrete structure, with Oil Distemper (Paint under Contractor’s Scope) | 2 | Nos | 16,800 ₹33,600 | 16,745 ₹33,490 |
| 6.00 | Opening of condenser water box manhole door, cleaning of water box and tubes and removing the entrapped debris (Shells) from the CW inlet pipe line bends. Opening of water box man hole door, arranging the safety ropes and safety equipment’s, cleaning the water box, removal of debris from the water box and tubes and closing of man hole doors with new gaskets. | 1 | No | 11,700 ₹11,700 | 11,673 ₹11,673 |
| 7.00 | Closing of front & Rear manhole doors of 16 Nos for Condenser LHS & RHS. Manhole doors after renewing all the manhole door rubber chords and Providing and removing condenser jack pipes during vacuum tightness test. | 1 | LS | 20,200 ₹20,200 | 20,165 ₹20,165 |
| 8.00 | a) Opening of OLCTC System Ball collecting screen manhole doors LHS & RHS -2 Nos. and cleaning the debris and closing of manhole doors with renewal of gaskets. | 1 | No | 12,300 ₹12,300 | 12,273 ₹12,273 |
| 9.00 | Cleaning and painting works including cost of paintings.
Cleaning and painting of CW Inlet & outlet pipe lines and CW Box of condenser(LHS & RHS) with double coat , Two Coat of side (LHS & RHS) painting of CW Inlet & outlet pipe lines of condenser in outer side (LHS & RHS) | 275 | M2 | 105 ₹28,875 | 100.37 ₹27,601.75 |
| 10.00 | Overhauling of 200mm condenser air release cum vacuum breaking valve and its isolation gate valves and gear mechanism
Dismantling the isolation valve, air release cum vacuum breaking valve of size 200mm,Cleaning all the parts, lapping the seating surface like valve seat and gates, checking blue contact, changing the internals if necessary and reassembling the valves with new gland packing’s, “O” Rings etc. | 2 | Nos | 11,300 ₹22,600 | 11,273 ₹22,546 |
Tender Value
Refer Docs
EMD Value
₹3,000
Closing Date
13 Aug 2025, 2:00 pmClosed
Superintending Engineer /Mechanical-I/MTPS-I
Office of the Superintending Engineer / Mechanical -I Mettur Thermal Power Station- I Mettur Dam-636406
MTPSI TM Unit IV Overhauling of OLCTC System Pump LHS RHS Inspection Cleaning of Condenser CW box steam side Hot well OLCTC System Ball collecting Screen Overhauling of 200 mm condenser air release cum vacuum breaking valve and Condenser Cooling
2025_EB_587152_1
CE / MTPS-I / SE / M-I / TM /OT.169/ 2025-26
Open Tender
Power/Energy Projects/Products
15 days
Mettur Thermal Power Station-I / Mettur Dam
As per the Tender Specifications
4 documents required · 4 mandatory
₹0
₹3,000
Yes
22 May 2026
30 Jul 2025
14 Aug 2025
30 Jul 2025
13 Aug 2025
30 Jul 2025
Amount
Decoupling the pump, disconnection of the pump from suction and discharge pipe flanges, draining the lub oil from the sump.
Dismantling of the Bearing Covers, Bearing Bracket, Dismantling of shaft sleeve and dismantling of the casing etc.,
Dismantling the impeller Assembly from the Casing, Inspection and reconditioning the eroded portions of the casings if required, Inspection, Checking measurements and tolerances of the impeller, shaft, impeller wearing ring, casing ring and neck ring and replace all the above if necessary including machining of the wearing rings to the required size and assembling with the impeller suitably
Reassembling and positioning of the rotor assembly and closing of casing cover, reassembling the sleeve, Bearing Bracket Bearings, Bearing Covers and assembling the coupling in shaft
Checking and correcting the pump alignment with motor and connecting of pump flanges with renewed gaskets. Inspection of couplings, Coupling the pump with motor, connecting the pump from suction and discharge pipe flanges, and other such works required for efficient operation of the pump and commissioning. Cleaning & painting the complete pump assembly & Base structure, Painting inside the pump casings, and painting of the pump base concrete structure, with Oil Distemper (Paint under Contractor’s Scope)
Opening of condenser water box manhole door, cleaning of water box and tubes and removing the entrapped debris (Shells) from the CW inlet pipe line bends. Opening of water box man hole door, arranging the safety ropes and safety equipment’s, cleaning the water box, removal of debris from the water box and tubes and closing of man hole doors with new gaskets.
Closing of front & Rear manhole doors of 16 Nos for Condenser LHS & RHS. Manhole doors after renewing all the manhole door rubber chords and Providing and removing condenser jack pipes during vacuum tightness test.
a) Opening of OLCTC System Ball collecting screen manhole doors LHS & RHS -2 Nos. and cleaning the debris and closing of manhole doors with renewal of gaskets.
Cleaning and painting works including cost of paintings. Cleaning and painting of CW Inlet & outlet pipe lines and CW Box of condenser(LHS & RHS) with double coat , Two Coat of side (LHS & RHS) painting of CW Inlet & outlet pipe lines of condenser in outer side (LHS & RHS)
Overhauling of 200mm condenser air release cum vacuum breaking valve and its isolation gate valves and gear mechanism Dismantling the isolation valve, air release cum vacuum breaking valve of size 200mm,Cleaning all the parts, lapping the seating surface like valve seat and gates, checking blue contact, changing the internals if necessary and reassembling the valves with new gland packing’s, “O” Rings etc.
Inspection and cleaning of Hot well and steam side of condenser (LHS& RHS) Opening/Closing the Condenser Steam side & Hot well manhole doors of 6 Nos., Cleaning inside the hot well to remove the dust and impurities, inspection the steam side area, cleaning of spray nozzle, cleaning the rubber chord seating groove and surface area of the manhole and closing after renewing all the manhole door rubber chords.( Rubber chord contractor scope)
Overhauling of condenser Cooling water Box drain valves/ air vent valve/ cooling water inlet , outlet valve. Dismantling the valve, cleaning all the parts, checking the seating surfaces of Gate/seat. Lapping the seating surfaces of gate/ seat for perfect blue matching. Reassembling the valve with new gland packing rings and bonnet gaskets without any leak.
Renewal of worn out drain lines in condenser Hot well drain lines by Non IBR welder. Labour charges for IBR welding for Replacing the defective drain line valves or equivalent in Cooling water lines and ACW lines by Non IBR welder.( ERW pipe, reduce & bends)Rate for Two number Non IBR cutting and welding.
Charges for Consumables and T&P’s item Sl.No:1 to 13
cutting gas
Enamel paint
Rubber chord
TAM AND CO (BID ID -1425653)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.PDF
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.85 MB
BOQ_701352.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid